NYSDOT contract D265568 bid tabulation

CULVERT RESILIENCY OF STATE SYSTEM - REHABILITATION WITH ROW. Let by New York State DOT on December 18, 2025, Clinton, Jefferson, St. Lawrence, Region 07. 3 bids received; low bid $2,492,000 by Barrett Paving Materials Inc.

Owner
New York State DOT
Letting
18 DEC 2025
Pay items
55
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Barrett Paving Materials Inc$2,492,000Low
2Kubricky-Jointa Lime LLC$3,625,269+45%
3Slate Hill Constructors Inc$3,675,747+48%
NYSDOT contract D265568: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Barrett Paving Materials Inc2. Kubricky-Jointa Lime LLC3. Slate Hill Constructors Inc
1Clearing and Grubbing (201.06)LS1$13,000$51,000$310,000
2 (203.24010017)170$115.60$235.00$90.00
3Structure Excavation (206.01)CY692$37.70$51.00$85.00
4Trench and Culvert Excavation (206.0201)CY163$63.00$72.00$120.00
5Seed and Mulch – Temporary (209.1003)SY16,442$0.75$1.05$1.20
6Check Dam (Ditch Bottom Width 0.0 to 3′), Gravel Bag – Temporary (209.110201)EACH4$169.00$290.00$550.00
7Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301)SY4,642$5.20$5.75$6.50
8Stabilized Construction Access (209.22)SY1,064$9.00$33.50$38.00
9Sediment Filter Log, 12″ (209.2301)LF5,904$6.65$11.50$10.00
10 (553.030001)EACH1$35,500$59,400$1.00
11 (553.030002)EACH1$36,500$60,900$1.00
12 (553.030003)EACH1$51,000$126,000$1.00
13 (553.030004)EACH1$36,000$58,900$1.00
14Stud Shear Connectors for Bridges (556.03)EACH3,100$8.30$10.50$6.00
15Structural Paving of Inverts with Portland Cement Concrete (602.2002)SF1,471$39.50$49.00$72.00
16 (602.2654)LF165$960.00$2,450.00$1,150.00
17 (602.27010807)162$2,170.00$1,450.00$2,200.00
18 (602.90100807)104$3,340.00$4,550.00$3,800.00
19Box Beam Guide Railing (606.10)LF4,254$58.50$47.50$50.00
20Box Beam Guide Railing End Assembly Type I (606.120102)EACH10$5,400.00$4,400.00$4,500.00
21Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH4$2,860.00$2,300.00$2,400.00
22Resetting Box Beam Guide Railing (New Posts) (606.5348)LF300$52.00$72.50$42.00
23Resetting Box Beam Guide Rail Turned-Down Terminal (606.5920)EACH2$585.00$1,400.00$500.00
24Removing and Disposing Cable Guide Railing (606.70)LF4,263$5.50$12.50$7.00
25Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79)EACH12$500.00$730.00$900.00
26Mycorrhizal Fungi (610.0701)LB43$5.00$31.50$80.00
27Turf Establishment – Performance (610.1605)SY16,442$3.50$2.65$10.00
28 (611.0121)EACH18$550.00$265.00$800.00
29 (611.0323)EACH25$300.00$125.00$220.00
30 (611.0331)EACH11$390.00$210.00$300.00
31 (611.0333)EACH11$390.00$210.00$300.00
32 (611.0341)EACH38$400.00$315.00$400.00
33 (613.04000001)25$126.00$170.00$160.00
34 (615.01010108)33$72.00$130.00$185.00
35 (615.82010108)6$2,700.00$2,150.00$3,500.00
36Basic Work Zone Traffic Control (619.01)LS1$92,883$735,000$850,000
37Stone Filling (Heavy) (620.05)CY647$182.00$175.00$170.00
38Bedding Material, Type 1 (620.0801)CY180$173.40$180.00$155.00
39 (620.29020008)124$141.50$185.00$250.00
40 (621.51050003)4,735$8.50$4.00$5.00
41Survey Operations (625.01)LS1$30,000$51,000$25,000
42Concrete Right of Way Markers Type H (High) (625.03)EACH2$790.00$1,550.00$2,300.00
43Concrete Cylinder Curing Equipment (637.04)EACH4$900.00$550.00$200.00
44Engineer’s Field Office – Type 2 (637.12)MONTH23$4,200.00$1,925.00$2,800.00
45Office Technology and Supplies (637.34)DOL5,000$1.00$1.00$1.00
46Construction Testing supplies – Consumables (637.36)DOL100$1.00$1.00$1.00
47 (637.41000115)23$175.00$48.00$140.00
48 (637.41000215)23$175.00$48.00$140.00
49Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH34$40.00$31.50$35.00
50Steel Post, 2.0 lb/ft (646.32)EACH27$91.00$73.50$75.00
51Field Change Payment (FCP) (697.03)DOL220,000$1.00$1.00$1.00
52Asphalt Price Adjustment (698.04)DOL100$1.00$1.00$1.00
53Fuel Price Adjustment (698.05)DOL100$1.00$1.00$1.00
54Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00
55Mobilization (699.040001)LS1$87,000$130,000$120,000
NYSDOT contract D265568: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of December 18, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy