NYSDOT contract D265594 bid tabulation
BRIDGE REPLACEMENT - Route 17 over NYS Route 17K. Let by New York State DOT on December 18, 2025, Orange, Region 08. 6 bids received; low bid $17,047,741 by Harrison & Burrowes Bridge Constructors Inc.
- Owner
- New York State DOT
- Letting
- 18 DEC 2025
- Pay items
- 143
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Harrison & Burrowes Bridge Constructors Inc | $17,047,741 | Low |
| 2 | Abi-HVB A Joint Venture | $18,169,268 | +7.0% |
| 3 | Ecco III Enterprises Inc | $18,746,000 | +10% |
| 4 | DSC Civil LLC | $20,857,000 | +22% |
| 5 | Carbro Constructors Corp | $21,812,928 | +28% |
| 6 | Sullivan County Paving & Construction Inc | $22,264,035 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Harrison & Burrowes Bridge Constructors Inc | 2. Abi-HVB A Joint Venture | 3. Ecco III Enterprises Inc | 4. DSC Civil LLC | 5. Carbro Constructors Corp | 6. Sullivan County Paving & Construction Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $50,000 | $243,500 | $100,000 | $548,948 | $125,000 | $50,000 |
| 2 | (202.120001) | LS | 1 | $800,000 | $799,900 | $900,000 | $850,000 | $1,714,315 | $650,000 |
| 3 | Removal of Substructures (202.19) | CY | 222 | $225.00 | $210.00 | $400.00 | $500.00 | $900.00 | $200.00 |
| 4 | Unclassified Excavation and Disposal (203.02) | CY | 24,247 | $34.00 | $42.55 | $25.00 | $10.00 | $15.00 | $45.00 |
| 5 | Embankment In Place (203.03) | CY | 4,722 | $65.00 | $81.00 | $50.00 | $50.00 | $20.00 | $200.00 |
| 6 | Select Granular Fill (203.07) | CY | 100 | $150.00 | $255.00 | $80.00 | $60.00 | $60.00 | $85.00 |
| 7 | Select Granular Fill, Slope Protection - Type A (203.0801) | CY | 225 | $100.00 | $180.00 | $225.00 | $150.00 | $140.00 | $90.00 |
| 8 | Select Structural Fill (203.21) | CY | 2,490 | $73.00 | $112.50 | $95.00 | $100.00 | $110.00 | $90.00 |
| 9 | Structure Excavation (206.01) | CY | 775 | $50.00 | $31.50 | $65.00 | $35.00 | $125.00 | $77.00 |
| 10 | Trench and Culvert Excavation (206.0201) | CY | 127 | $80.00 | $650.00 | $100.00 | $300.00 | $1.00 | $120.00 |
| 11 | Test Pit Excavation (206.05) | EACH | 4 | $3,000.00 | $1,875.00 | $4,000.00 | $5,000.00 | $2,000.00 | $1,500.00 |
| 12 | Geotextile Separation (207.21) | SY | 3,814 | $1.75 | $3.40 | $3.50 | $2.00 | $4.00 | $5.00 |
| 13 | Prefabricated Composite Integral Abutment Drain (207.27) | SY | 628 | $13.00 | $11.50 | $26.00 | $50.00 | $40.00 | $18.00 |
| 14 | Seed and Mulch – Temporary (209.1003) | SY | 3,564 | $3.00 | $1.80 | $4.00 | $10.00 | $4.00 | $5.00 |
| 15 | Silt Fence - Temporary (209.13) | LF | 5,028 | $8.00 | $6.00 | $14.00 | $10.00 | $15.00 | $10.00 |
| 16 | Drainage Structure Inlet Protection, Silt Fence – Temporary (209.1701) | LF | 80 | $20.00 | $12.50 | $75.00 | $45.00 | $67.00 | $50.00 |
| 17 | Rolled Erosion Control Product, Class II Type A, Intermediate (209.1901) | SY | 1,696 | $5.75 | $6.60 | $7.00 | $6.00 | $7.00 | $5.00 |
| 18 | Stabilized Construction Access (209.22) | SY | 450 | $40.00 | $51.00 | $110.00 | $50.00 | $12.00 | $20.00 |
| 19 | Removal and Disposal of Bond Breaker/Filler ACM (BV14) (210.3312) | SF | 278 | $80.00 | $45.15 | $61.00 | $100.00 | $250.00 | $50.00 |
| 20 | Removal and Disposal of Caulking ACM (BV14) (210.3411) | LF | 5 | $1,200.00 | $420.00 | $1,056.00 | $100.00 | $1,750.00 | $440.00 |
| 21 | (304.11000008) | 4,206 | $95.00 | $105.75 | $125.00 | $100.00 | $140.00 | $95.00 | |
| 22 | (404.0001) | TON | 1 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 23 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 24 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 1 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 25 | (404.0189) | TON | 700 | $200.00 | $175.00 | $170.00 | $450.00 | $198.00 | $140.00 |
| 26 | (404.0951) | TON | 478 | $195.00 | $184.00 | $150.00 | $200.00 | $186.00 | $155.00 |
| 27 | (404.1251) | TON | 1,691 | $175.00 | $155.00 | $140.00 | $150.00 | $175.00 | $145.00 |
| 28 | (404.1959) | TON | 1,820 | $160.00 | $144.25 | $150.00 | $340.00 | $159.00 | $130.00 |
| 29 | (404.3769) | TON | 763 | $140.00 | $291.50 | $145.00 | $330.00 | $137.00 | $120.00 |
| 30 | (404.4389) | TON | 1,150 | $175.00 | $204.00 | $145.00 | $200.00 | $164.00 | $130.00 |
| 31 | (404.4589) | TON | 2,529 | $140.00 | $144.00 | $145.00 | $190.00 | $137.00 | $120.00 |
| 32 | Straight Tack Coat (407.0103) | GAL | 3,130 | $12.50 | $10.00 | $12.00 | $6.00 | $12.00 | $11.00 |
| 33 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 10,272 | $4.00 | $1.75 | $1.20 | $2.00 | $4.00 | $1.00 |
| 34 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 10,412 | $12.00 | $16.00 | $7.00 | $13.00 | $11.00 | $8.00 |
| 35 | Steel H-Piles (HP 12x53) (551.012053) | LF | 2,282 | $2.00 | $14.70 | $180.00 | $40.00 | $225.00 | $3.00 |
| 36 | Furnishing Equipment for Driving Piles (551.13) | LS | 1 | $475,000 | $409,400 | $200,000 | $300,000 | $285,000 | $330,000 |
| 37 | Shields and Shoring (552.17) | SF | 3,840 | $0.01 | $0.50 | $1.00 | $2.00 | $1.00 | $3.00 |
| 38 | (554.3001) | SF | 530 | $75.00 | $87.50 | $80.00 | $60.00 | $48.00 | $85.00 |
| 39 | Footing Concrete, Performance (555.0011) | CY | 41 | $2,000.00 | $1,155.00 | $1,400.00 | $1,400.00 | $4,000.00 | $1,700.00 |
| 40 | Concrete for Structures, Performance (555.0021) | CY | 685 | $2,100.00 | $1,575.00 | $1,440.00 | $1,800.00 | $3,110.00 | $2,000.00 |
| 41 | Performance Concrete Quality Adjustment – Footing Concrete (555.9901) | QUALITY UNIT | 1 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 42 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $12.50 | $12.50 | $12.50 | $12.50 | $12.50 | $12.50 |
| 43 | Stainless Steel Bar Reinforcement for Structures (556.0205) | LB | 136,836 | $4.00 | $4.72 | $4.50 | $3.00 | $5.00 | $8.00 |
| 44 | Stud Shear Connectors for Bridges (556.03) | EACH | 9,648 | $6.50 | $5.15 | $5.00 | $12.00 | $7.25 | $7.50 |
| 45 | (557.1011) | SY | 1,004 | $675.00 | $577.50 | $650.00 | $600.00 | $880.00 | $1,200.00 |
| 46 | (557.1111) | SY | 1,569 | $800.00 | $787.25 | $750.00 | $700.00 | $800.00 | $1,800.00 |
| 47 | Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29) | SY | 2,362 | $0.01 | $1.05 | $1.00 | $5.00 | $44.00 | $2.50 |
| 48 | Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901) | QUALITY UNIT | 1 | $15.86 | $15.86 | $15.86 | $15.86 | $15.86 | $15.86 |
| 49 | Longitudinal Sawcut Grooving of Structural Slab Surface (558.02) | SY | 2,294 | $9.00 | $7.35 | $11.00 | $12.00 | $7.00 | $12.00 |
| 50 | Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01) | SF | 20,646 | $0.85 | $0.85 | $1.25 | $2.00 | $13.00 | $0.50 |
| 51 | Protective Sealing of New Structural Concrete (559.02) | SF | 4,530 | $1.20 | $1.05 | $1.00 | $2.00 | $16.00 | $2.00 |
| 52 | (564.0501) | LS | 1 | $1,950,000 | $1,942,100 | $2,200,000 | $2,500,000 | $2,725,000 | $1,860,000 |
| 53 | (565.30130101) | 32 | $500.00 | $157.00 | $300.00 | $25.00 | $200.00 | $500.00 | |
| 54 | Armorless Bridge Joint (567.60) | LF | 278 | $390.00 | $157.00 | $235.00 | $610.00 | $450.00 | $500.00 |
| 55 | Transition Bridge Railing (568.70) | LF | 80 | $285.00 | $300.00 | $250.00 | $100.00 | $230.00 | $300.00 |
| 56 | Single Slope (Half-Section) Concrete Bridge Barrier (569.04) | LF | 627 | $525.00 | $813.50 | $600.00 | $550.00 | $625.00 | $650.00 |
| 57 | Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99) | QUALITY UNIT | 1 | $21.49 | $21.49 | $21.49 | $21.49 | $21.49 | $21.49 |
| 58 | Lead-Exposure Control Plan (570.01) | LS | 1 | $1,500.00 | $1,575.00 | $1,000.00 | $25,000 | $25,000 | $5.00 |
| 59 | Medical Testing (570.02) | DOL | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 60 | Personal-Exposure-Monitoring Sample Analysis (570.03) | DOL | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 61 | Disposal of Hazardous Paint Removal Waste Containing Lead (571.03) | LB | 1,000 | $0.01 | $1.05 | $8.00 | $12.00 | $9.00 | $5.00 |
| 62 | (572.00020101) | LS | 1 | $450,000 | $498,600 | $600,000 | $500,000 | $365,000 | $475,000 |
| 63 | (603.051114) | LF | 196 | $115.00 | $53.00 | $200.00 | $260.00 | $450.00 | $80.00 |
| 64 | (603.16150010) | 723 | $225.00 | $108.00 | $250.00 | $220.00 | $360.00 | $80.00 | |
| 65 | (603.541514) | EACH | 1 | $1,000.00 | $2,050.00 | $1,600.00 | $2,000.00 | $12,000 | $2,000.00 |
| 66 | (603.9824) | LF | 533 | $130.00 | $53.00 | $125.00 | $150.00 | $300.00 | $80.00 |
| 67 | (604.070102) | EACH | 1 | $3,000.00 | $2,675.00 | $6,000.00 | $3,700.00 | $8,000.00 | $3,200.00 |
| 68 | (604.070801) | EACH | 1 | $3,000.00 | $6,700.00 | $2,000.00 | $2,900.00 | $5,509.00 | $3,200.00 |
| 69 | (604.301990) | LF | 27 | $900.00 | $400.00 | $850.00 | $1,700.00 | $850.00 | $500.00 |
| 70 | Underdrain Filter, Type II (605.1001) | CY | 156 | $80.00 | $198.00 | $50.00 | $100.00 | $80.00 | $200.00 |
| 71 | (605.1602) | LF | 1,267 | $26.00 | $11.50 | $15.00 | $35.00 | $50.00 | $25.00 |
| 72 | Box Beam Guide Railing (606.10) | LF | 1,565 | $58.00 | $56.25 | $47.00 | $85.00 | $57.00 | $52.00 |
| 73 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 1 | $6,000.00 | $5,275.00 | $4,400.00 | $7,000.00 | $5,500.00 | $5,000.00 |
| 74 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 1 | $2,600.00 | $2,750.00 | $2,300.00 | $4,000.00 | $2,700.00 | $2,500.00 |
| 75 | HPBO (Mod.) Corrugated Beam Guide Railing (606.2701) | LF | 1,445 | $43.00 | $40.75 | $34.00 | $50.00 | $46.00 | $38.00 |
| 76 | Anchorage Units for HPBO (Mod.) Corrugated Beam Guide Railing (606.2703) | EACH | 4 | $5,000.00 | $3,840.00 | $3,200.00 | $6,500.00 | $3,300.00 | $3,500.00 |
| 77 | HPBO (Mod.) Corrugated Beam Median Barrier (606.2801) | LF | 2,390 | $58.00 | $51.50 | $43.00 | $70.00 | $59.00 | $47.00 |
| 78 | Single-Slope Concrete Median Barrier (Optional) (606.3041) | LF | 330 | $100.00 | $26.25 | $20.00 | $200.00 | $260.00 | $300.00 |
| 79 | Removing and Disposing Corrugated Beam Guide Railing (606.71) | LF | 1,795 | $16.00 | $15.45 | $8.00 | $4.00 | $4.50 | $8.00 |
| 80 | Removing and Disposing Corrugated Beam Median Barrier (606.72) | LF | 2,230 | $15.00 | $12.90 | $12.00 | $5.00 | $5.00 | $8.00 |
| 81 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 1,565 | $16.00 | $16.25 | $8.00 | $5.00 | $5.50 | $8.00 |
| 82 | Removing and Disposing Concrete Barrier-Half Section (606.7510) | LF | 330 | $45.00 | $34.00 | $50.00 | $80.00 | $50.00 | $75.00 |
| 83 | Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910) | EACH | 6 | $550.00 | $2,375.00 | $500.00 | $4,500.00 | $625.00 | $100.00 |
| 84 | Transition: HPBO (Mod.) Corrugated Beam Median Barrier to Single Slope Concrete Median Barrier (606.8906) | EACH | 5 | $11,000 | $11,450 | $8,000.00 | $10,000 | $12,000 | $4,500.00 |
| 85 | (606.90000011) | 60 | $850.00 | $945.00 | $400.00 | $1,100.00 | $440.00 | $900.00 | |
| 86 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 87 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 44 | $450.00 | $200.00 | $500.00 | $900.00 | $1,100.00 | $250.00 |
| 88 | Stone Curb – Bridge (Type A) (609.0301) | LF | 36 | $350.00 | $210.00 | $160.00 | $250.00 | $500.00 | $550.00 |
| 89 | Topsoil - Roadside (610.1402) | CY | 273 | $115.00 | $96.50 | $125.00 | $105.00 | $120.00 | $125.00 |
| 90 | Turf Establishment - Roadside (610.1601) | SY | 2,472 | $3.25 | $3.00 | $4.00 | $4.00 | $8.00 | $6.00 |
| 91 | (617.11000024) | LS | 1 | $1,500.00 | $2,625.00 | $3,500.00 | $5,000.00 | $5,000.00 | $2,000.00 |
| 92 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $1,190,647 | $1,139,850 | $1,399,698 | $1,566,000 | $350,000 | $950,000 |
| 93 | (619.080102) | LF | 44,430 | $1.40 | $1.45 | $0.79 | $0.80 | $0.83 | $1.32 |
| 94 | (619.100102) | LF | 63,490 | $0.80 | $0.81 | $0.60 | $0.60 | $0.63 | $0.77 |
| 95 | (619.110743) | EACH | 4 | $7,500.00 | $50,000 | $45,000 | $50,000 | $2,500.00 | $19,000 |
| 96 | Temporary Glare Screen (619.12) | LF | 3,450 | $8.00 | $22.00 | $20.00 | $45.00 | $20.00 | $75.00 |
| 97 | Temporary Positive Barrier – Category 2 (Pinning Permitted) (619.1712) | LF | 18,195 | $15.00 | $41.00 | $45.00 | $40.00 | $85.00 | $80.00 |
| 98 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 3,850 | $15.00 | $29.75 | $50.00 | $60.00 | $85.00 | $80.00 |
| 99 | Temporary Concrete Barrier Back to Corrugated Beam Transition (619.1726) | EACH | 4 | $2,500.00 | $300.00 | $3,600.00 | $15,000 | $250.00 | $6,000.00 |
| 100 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 5 | $13,000 | $13,500 | $20,000 | $30,000 | $7,800.00 | $12,000 |
| 101 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $25,000 | $52,500 | $150,000 | $200,000 | $30,000 | $500,000 |
| 102 | Traffic Control Supervisor (619.25) | MONTH | 24 | $500.00 | $1.00 | $50.00 | $2,000.00 | $100.00 | $8,000.00 |
| 103 | Pavement Patching (Force Acount) (619.2601) | DOL | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 104 | Pavement Patching (Tonnage) (619.2602) | TON | 20 | $770.00 | $2,200.00 | $586.00 | $1,000.00 | $150.00 | $1,000.00 |
| 105 | Stone Filling (Light) (620.03) | CY | 16 | $225.00 | $335.00 | $450.00 | $200.00 | $300.00 | $250.00 |
| 106 | Bedding Material, Type 2 (620.0802) | CY | 17 | $195.00 | $310.00 | $400.00 | $200.00 | $300.00 | $200.00 |
| 107 | Crushed Gravel (By Weight) (623.02) | TON | 119 | $85.00 | $155.00 | $70.00 | $100.00 | $130.00 | $200.00 |
| 108 | Asphalt Gutter (624.020101) | TON | 44 | $265.00 | $280.00 | $475.00 | $350.00 | $275.00 | $300.00 |
| 109 | Survey Operations (625.01) | LS | 1 | $100,000 | $148,900 | $600,000 | $500,000 | $140,000 | $160,000 |
| 110 | (627.50140008) | 736 | $7.50 | $14.50 | $10.00 | $8.00 | $4.00 | $20.00 | |
| 111 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $5,000.00 | $6,825.00 | $3,650.00 | $7,000.00 | $6,000.00 | $1,500.00 |
| 112 | Engineer’s Field Office – Type 4 (637.14) | MONTH | 24 | $5,000.00 | $6,300.00 | $9,000.00 | $20,000 | $5,000.00 | $5,000.00 |
| 113 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 114 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 115 | (637.41000115) | 24 | $125.00 | $87.50 | $100.00 | $200.00 | $150.00 | $300.00 | |
| 116 | (637.41000215) | 24 | $125.00 | $87.50 | $100.00 | $200.00 | $150.00 | $300.00 | |
| 117 | (637.41000315) | 24 | $125.00 | $87.50 | $100.00 | $200.00 | $150.00 | $300.00 | |
| 118 | (639.21010011) | LS | 1 | $75,000 | $75,000 | $75,000 | $150,000 | $75,000 | $125,000 |
| 119 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 186 | $45.00 | $48.00 | $40.00 | $60.00 | $52.00 | $46.00 |
| 120 | Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103) | SF | 130 | $49.00 | $50.00 | $42.00 | $83.00 | $51.00 | $46.00 |
| 121 | Type A Sign Posts (645.81) | EACH | 11 | $260.00 | $265.00 | $220.00 | $405.00 | $350.00 | $240.00 |
| 122 | High-Capacity Type A Sign Posts with Soil Plates Only (645.8106) | EACH | 7 | $1,400.00 | $1,500.00 | $1,260.00 | $2,000.00 | $3,000.00 | $1,300.00 |
| 123 | (645.830201) | EACH | 2 | $5,000.00 | $5,200.00 | $4,350.00 | $5,500.00 | $4,000.00 | $4,500.00 |
| 124 | Reference Marker Panel (646.21) | EACH | 6 | $38.00 | $45.00 | $34.00 | $190.00 | $50.00 | $37.00 |
| 125 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 36 | $14.00 | $15.00 | $12.00 | $155.00 | $27.00 | $13.00 |
| 126 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 4 | $28.00 | $30.00 | $24.00 | $225.00 | $33.00 | $26.00 |
| 127 | Steel Post, 2.0 lb/ft (646.32) | EACH | 20 | $83.00 | $85.00 | $70.00 | $140.00 | $132.00 | $77.00 |
| 128 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 1 | $350.00 | $350.00 | $300.00 | $870.00 | $250.00 | $330.00 |
| 129 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 18 | $82.00 | $85.00 | $70.00 | $85.00 | $66.00 | $77.00 |
| 130 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size III (Over 100 Square Feet) (647.63) | EACH | 1 | $2,000.00 | $1,800.00 | $250.00 | $1,300.00 | $825.00 | $100.00 |
| 131 | (647.83001002) | 20 | $17.00 | $30.00 | $75.00 | $60.00 | $11.00 | $10.00 | |
| 132 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 3,502 | $5.65 | $3.75 | $5.00 | $3.00 | $3.00 | $4.00 |
| 133 | Parallel Bar Frame 10 PCB & Parallel Bar Grate 10 PCB (655.0901) | EACH | 5 | $2,000.00 | $1,925.00 | $1,700.00 | $2,000.00 | $2,250.00 | $2,200.00 |
| 134 | Welded Frame & Rectangular Grate 22 (655.1022) | EACH | 1 | $2,000.00 | $2,000.00 | $3,000.00 | $1,800.00 | $1,500.00 | $2,200.00 |
| 135 | (660.04040001) | 1,481 | $15.00 | $23.50 | $20.00 | $28.00 | $70.00 | $55.00 | |
| 136 | (685.16010014) | 4,263 | $4.00 | $1.55 | $4.00 | $4.50 | $4.10 | $1.45 | |
| 137 | (685.17010014) | 2,694 | $4.00 | $1.55 | $4.00 | $4.50 | $4.10 | $1.45 | |
| 138 | (691.04000020) | 1,050 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 139 | Field Change Payment (FCP) (697.03) | DOL | 1,073,199 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 140 | Asphalt Price Adjustment (698.04) | DOL | 11,278 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 141 | Fuel Price Adjustment (698.05) | DOL | 1,743 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 142 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 143 | Mobilization (699.040001) | LS | 1 | $650,000 | $696,626 | $700,000 | $800,000 | $825,000 | $770,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of December 18, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.