NYSDOT contract D265594 bid tabulation

BRIDGE REPLACEMENT - Route 17 over NYS Route 17K. Let by New York State DOT on December 18, 2025, Orange, Region 08. 6 bids received; low bid $17,047,741 by Harrison & Burrowes Bridge Constructors Inc.

Owner
New York State DOT
Letting
18 DEC 2025
Pay items
143
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Harrison & Burrowes Bridge Constructors Inc$17,047,741Low
2Abi-HVB A Joint Venture$18,169,268+7.0%
3Ecco III Enterprises Inc$18,746,000+10%
4DSC Civil LLC$20,857,000+22%
5Carbro Constructors Corp$21,812,928+28%
6Sullivan County Paving & Construction Inc$22,264,035+31%
NYSDOT contract D265594: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Harrison & Burrowes Bridge Constructors Inc2. Abi-HVB A Joint Venture3. Ecco III Enterprises Inc4. DSC Civil LLC5. Carbro Constructors Corp6. Sullivan County Paving & Construction Inc
1Clearing and Grubbing (201.06)LS1$50,000$243,500$100,000$548,948$125,000$50,000
2 (202.120001)LS1$800,000$799,900$900,000$850,000$1,714,315$650,000
3Removal of Substructures (202.19)CY222$225.00$210.00$400.00$500.00$900.00$200.00
4Unclassified Excavation and Disposal (203.02)CY24,247$34.00$42.55$25.00$10.00$15.00$45.00
5Embankment In Place (203.03)CY4,722$65.00$81.00$50.00$50.00$20.00$200.00
6Select Granular Fill (203.07)CY100$150.00$255.00$80.00$60.00$60.00$85.00
7Select Granular Fill, Slope Protection - Type A (203.0801)CY225$100.00$180.00$225.00$150.00$140.00$90.00
8Select Structural Fill (203.21)CY2,490$73.00$112.50$95.00$100.00$110.00$90.00
9Structure Excavation (206.01)CY775$50.00$31.50$65.00$35.00$125.00$77.00
10Trench and Culvert Excavation (206.0201)CY127$80.00$650.00$100.00$300.00$1.00$120.00
11Test Pit Excavation (206.05)EACH4$3,000.00$1,875.00$4,000.00$5,000.00$2,000.00$1,500.00
12Geotextile Separation (207.21)SY3,814$1.75$3.40$3.50$2.00$4.00$5.00
13Prefabricated Composite Integral Abutment Drain (207.27)SY628$13.00$11.50$26.00$50.00$40.00$18.00
14Seed and Mulch – Temporary (209.1003)SY3,564$3.00$1.80$4.00$10.00$4.00$5.00
15Silt Fence - Temporary (209.13)LF5,028$8.00$6.00$14.00$10.00$15.00$10.00
16Drainage Structure Inlet Protection, Silt Fence – Temporary (209.1701)LF80$20.00$12.50$75.00$45.00$67.00$50.00
17Rolled Erosion Control Product, Class II Type A, Intermediate (209.1901)SY1,696$5.75$6.60$7.00$6.00$7.00$5.00
18Stabilized Construction Access (209.22)SY450$40.00$51.00$110.00$50.00$12.00$20.00
19Removal and Disposal of Bond Breaker/Filler ACM (BV14) (210.3312)SF278$80.00$45.15$61.00$100.00$250.00$50.00
20Removal and Disposal of Caulking ACM (BV14) (210.3411)LF5$1,200.00$420.00$1,056.00$100.00$1,750.00$440.00
21 (304.11000008)4,206$95.00$105.75$125.00$100.00$140.00$95.00
22 (404.0001)TON1$120.00$120.00$120.00$120.00$120.00$120.00
23Pavement Density Quality Adjustment to Asphalt Items (404.0002)QUALITY UNIT1$120.00$120.00$120.00$120.00$120.00$120.00
24Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003)QUALITY UNIT1$120.00$120.00$120.00$120.00$120.00$120.00
25 (404.0189)TON700$200.00$175.00$170.00$450.00$198.00$140.00
26 (404.0951)TON478$195.00$184.00$150.00$200.00$186.00$155.00
27 (404.1251)TON1,691$175.00$155.00$140.00$150.00$175.00$145.00
28 (404.1959)TON1,820$160.00$144.25$150.00$340.00$159.00$130.00
29 (404.3769)TON763$140.00$291.50$145.00$330.00$137.00$120.00
30 (404.4389)TON1,150$175.00$204.00$145.00$200.00$164.00$130.00
31 (404.4589)TON2,529$140.00$144.00$145.00$190.00$137.00$120.00
32Straight Tack Coat (407.0103)GAL3,130$12.50$10.00$12.00$6.00$12.00$11.00
33Asphalt Pavement Joint Adhesive (418.7603)LF10,272$4.00$1.75$1.20$2.00$4.00$1.00
34Production Cold Milling of Bituminous Concrete (490.10)SY10,412$12.00$16.00$7.00$13.00$11.00$8.00
35Steel H-Piles (HP 12x53) (551.012053)LF2,282$2.00$14.70$180.00$40.00$225.00$3.00
36Furnishing Equipment for Driving Piles (551.13)LS1$475,000$409,400$200,000$300,000$285,000$330,000
37Shields and Shoring (552.17)SF3,840$0.01$0.50$1.00$2.00$1.00$3.00
38 (554.3001)SF530$75.00$87.50$80.00$60.00$48.00$85.00
39Footing Concrete, Performance (555.0011)CY41$2,000.00$1,155.00$1,400.00$1,400.00$4,000.00$1,700.00
40Concrete for Structures, Performance (555.0021)CY685$2,100.00$1,575.00$1,440.00$1,800.00$3,110.00$2,000.00
41Performance Concrete Quality Adjustment – Footing Concrete (555.9901)QUALITY UNIT1$10.00$10.00$10.00$10.00$10.00$10.00
42Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$12.50$12.50$12.50$12.50$12.50$12.50
43Stainless Steel Bar Reinforcement for Structures (556.0205)LB136,836$4.00$4.72$4.50$3.00$5.00$8.00
44Stud Shear Connectors for Bridges (556.03)EACH9,648$6.50$5.15$5.00$12.00$7.25$7.50
45 (557.1011)SY1,004$675.00$577.50$650.00$600.00$880.00$1,200.00
46 (557.1111)SY1,569$800.00$787.25$750.00$700.00$800.00$1,800.00
47Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29)SY2,362$0.01$1.05$1.00$5.00$44.00$2.50
48Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901)QUALITY UNIT1$15.86$15.86$15.86$15.86$15.86$15.86
49Longitudinal Sawcut Grooving of Structural Slab Surface (558.02)SY2,294$9.00$7.35$11.00$12.00$7.00$12.00
50Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01)SF20,646$0.85$0.85$1.25$2.00$13.00$0.50
51Protective Sealing of New Structural Concrete (559.02)SF4,530$1.20$1.05$1.00$2.00$16.00$2.00
52 (564.0501)LS1$1,950,000$1,942,100$2,200,000$2,500,000$2,725,000$1,860,000
53 (565.30130101)32$500.00$157.00$300.00$25.00$200.00$500.00
54Armorless Bridge Joint (567.60)LF278$390.00$157.00$235.00$610.00$450.00$500.00
55Transition Bridge Railing (568.70)LF80$285.00$300.00$250.00$100.00$230.00$300.00
56Single Slope (Half-Section) Concrete Bridge Barrier (569.04)LF627$525.00$813.50$600.00$550.00$625.00$650.00
57Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99)QUALITY UNIT1$21.49$21.49$21.49$21.49$21.49$21.49
58Lead-Exposure Control Plan (570.01)LS1$1,500.00$1,575.00$1,000.00$25,000$25,000$5.00
59Medical Testing (570.02)DOL3,000$1.00$1.00$1.00$1.00$1.00$1.00
60Personal-Exposure-Monitoring Sample Analysis (570.03)DOL3,000$1.00$1.00$1.00$1.00$1.00$1.00
61Disposal of Hazardous Paint Removal Waste Containing Lead (571.03)LB1,000$0.01$1.05$8.00$12.00$9.00$5.00
62 (572.00020101)LS1$450,000$498,600$600,000$500,000$365,000$475,000
63 (603.051114)LF196$115.00$53.00$200.00$260.00$450.00$80.00
64 (603.16150010)723$225.00$108.00$250.00$220.00$360.00$80.00
65 (603.541514)EACH1$1,000.00$2,050.00$1,600.00$2,000.00$12,000$2,000.00
66 (603.9824)LF533$130.00$53.00$125.00$150.00$300.00$80.00
67 (604.070102)EACH1$3,000.00$2,675.00$6,000.00$3,700.00$8,000.00$3,200.00
68 (604.070801)EACH1$3,000.00$6,700.00$2,000.00$2,900.00$5,509.00$3,200.00
69 (604.301990)LF27$900.00$400.00$850.00$1,700.00$850.00$500.00
70Underdrain Filter, Type II (605.1001)CY156$80.00$198.00$50.00$100.00$80.00$200.00
71 (605.1602)LF1,267$26.00$11.50$15.00$35.00$50.00$25.00
72Box Beam Guide Railing (606.10)LF1,565$58.00$56.25$47.00$85.00$57.00$52.00
73Box Beam Guide Railing End Assembly Type I (606.120102)EACH1$6,000.00$5,275.00$4,400.00$7,000.00$5,500.00$5,000.00
74Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH1$2,600.00$2,750.00$2,300.00$4,000.00$2,700.00$2,500.00
75HPBO (Mod.) Corrugated Beam Guide Railing (606.2701)LF1,445$43.00$40.75$34.00$50.00$46.00$38.00
76Anchorage Units for HPBO (Mod.) Corrugated Beam Guide Railing (606.2703)EACH4$5,000.00$3,840.00$3,200.00$6,500.00$3,300.00$3,500.00
77HPBO (Mod.) Corrugated Beam Median Barrier (606.2801)LF2,390$58.00$51.50$43.00$70.00$59.00$47.00
78Single-Slope Concrete Median Barrier (Optional) (606.3041)LF330$100.00$26.25$20.00$200.00$260.00$300.00
79Removing and Disposing Corrugated Beam Guide Railing (606.71)LF1,795$16.00$15.45$8.00$4.00$4.50$8.00
80Removing and Disposing Corrugated Beam Median Barrier (606.72)LF2,230$15.00$12.90$12.00$5.00$5.00$8.00
81Removing and Disposing Box Beam Guide Railing (606.73)LF1,565$16.00$16.25$8.00$5.00$5.50$8.00
82Removing and Disposing Concrete Barrier-Half Section (606.7510)LF330$45.00$34.00$50.00$80.00$50.00$75.00
83Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910)EACH6$550.00$2,375.00$500.00$4,500.00$625.00$100.00
84Transition: HPBO (Mod.) Corrugated Beam Median Barrier to Single Slope Concrete Median Barrier (606.8906)EACH5$11,000$11,450$8,000.00$10,000$12,000$4,500.00
85 (606.90000011)60$850.00$945.00$400.00$1,100.00$440.00$900.00
86Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT1$120.00$120.00$120.00$120.00$120.00$120.00
87Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON44$450.00$200.00$500.00$900.00$1,100.00$250.00
88Stone Curb – Bridge (Type A) (609.0301)LF36$350.00$210.00$160.00$250.00$500.00$550.00
89Topsoil - Roadside (610.1402)CY273$115.00$96.50$125.00$105.00$120.00$125.00
90Turf Establishment - Roadside (610.1601)SY2,472$3.25$3.00$4.00$4.00$8.00$6.00
91 (617.11000024)LS1$1,500.00$2,625.00$3,500.00$5,000.00$5,000.00$2,000.00
92Basic Work Zone Traffic Control (619.01)LS1$1,190,647$1,139,850$1,399,698$1,566,000$350,000$950,000
93 (619.080102)LF44,430$1.40$1.45$0.79$0.80$0.83$1.32
94 (619.100102)LF63,490$0.80$0.81$0.60$0.60$0.63$0.77
95 (619.110743)EACH4$7,500.00$50,000$45,000$50,000$2,500.00$19,000
96Temporary Glare Screen (619.12)LF3,450$8.00$22.00$20.00$45.00$20.00$75.00
97Temporary Positive Barrier – Category 2 (Pinning Permitted) (619.1712)LF18,195$15.00$41.00$45.00$40.00$85.00$80.00
98Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716)LF3,850$15.00$29.75$50.00$60.00$85.00$80.00
99Temporary Concrete Barrier Back to Corrugated Beam Transition (619.1726)EACH4$2,500.00$300.00$3,600.00$15,000$250.00$6,000.00
100Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803)EACH5$13,000$13,500$20,000$30,000$7,800.00$12,000
101Nighttime Operations (Entire Project) (619.24)LS1$25,000$52,500$150,000$200,000$30,000$500,000
102Traffic Control Supervisor (619.25)MONTH24$500.00$1.00$50.00$2,000.00$100.00$8,000.00
103Pavement Patching (Force Acount) (619.2601)DOL10,000$1.00$1.00$1.00$1.00$1.00$1.00
104Pavement Patching (Tonnage) (619.2602)TON20$770.00$2,200.00$586.00$1,000.00$150.00$1,000.00
105Stone Filling (Light) (620.03)CY16$225.00$335.00$450.00$200.00$300.00$250.00
106Bedding Material, Type 2 (620.0802)CY17$195.00$310.00$400.00$200.00$300.00$200.00
107Crushed Gravel (By Weight) (623.02)TON119$85.00$155.00$70.00$100.00$130.00$200.00
108Asphalt Gutter (624.020101)TON44$265.00$280.00$475.00$350.00$275.00$300.00
109Survey Operations (625.01)LS1$100,000$148,900$600,000$500,000$140,000$160,000
110 (627.50140008)736$7.50$14.50$10.00$8.00$4.00$20.00
111Concrete Cylinder Curing Equipment (637.04)EACH1$5,000.00$6,825.00$3,650.00$7,000.00$6,000.00$1,500.00
112Engineer’s Field Office – Type 4 (637.14)MONTH24$5,000.00$6,300.00$9,000.00$20,000$5,000.00$5,000.00
113Office Technology and Supplies (637.34)DOL5,000$1.00$1.00$1.00$1.00$1.00$1.00
114Partnering Workshop (637.35)DOL5,000$1.00$1.00$1.00$1.00$1.00$1.00
115 (637.41000115)24$125.00$87.50$100.00$200.00$150.00$300.00
116 (637.41000215)24$125.00$87.50$100.00$200.00$150.00$300.00
117 (637.41000315)24$125.00$87.50$100.00$200.00$150.00$300.00
118 (639.21010011)LS1$75,000$75,000$75,000$150,000$75,000$125,000
119Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF186$45.00$48.00$40.00$60.00$52.00$46.00
120Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103)SF130$49.00$50.00$42.00$83.00$51.00$46.00
121Type A Sign Posts (645.81)EACH11$260.00$265.00$220.00$405.00$350.00$240.00
122High-Capacity Type A Sign Posts with Soil Plates Only (645.8106)EACH7$1,400.00$1,500.00$1,260.00$2,000.00$3,000.00$1,300.00
123 (645.830201)EACH2$5,000.00$5,200.00$4,350.00$5,500.00$4,000.00$4,500.00
124Reference Marker Panel (646.21)EACH6$38.00$45.00$34.00$190.00$50.00$37.00
125Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22)EACH36$14.00$15.00$12.00$155.00$27.00$13.00
126Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH4$28.00$30.00$24.00$225.00$33.00$26.00
127Steel Post, 2.0 lb/ft (646.32)EACH20$83.00$85.00$70.00$140.00$132.00$77.00
128Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31)EACH1$350.00$350.00$300.00$870.00$250.00$330.00
129Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH18$82.00$85.00$70.00$85.00$66.00$77.00
130Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size III (Over 100 Square Feet) (647.63)EACH1$2,000.00$1,800.00$250.00$1,300.00$825.00$100.00
131 (647.83001002)20$17.00$30.00$75.00$60.00$11.00$10.00
132Milled-In Audible Roadway Delineators (MIARDs) (649.01)LF3,502$5.65$3.75$5.00$3.00$3.00$4.00
133Parallel Bar Frame 10 PCB & Parallel Bar Grate 10 PCB (655.0901)EACH5$2,000.00$1,925.00$1,700.00$2,000.00$2,250.00$2,200.00
134Welded Frame & Rectangular Grate 22 (655.1022)EACH1$2,000.00$2,000.00$3,000.00$1,800.00$1,500.00$2,200.00
135 (660.04040001)1,481$15.00$23.50$20.00$28.00$70.00$55.00
136 (685.16010014)4,263$4.00$1.55$4.00$4.50$4.10$1.45
137 (685.17010014)2,694$4.00$1.55$4.00$4.50$4.10$1.45
138 (691.04000020)1,050$1.00$1.00$1.00$1.00$1.00$1.00
139Field Change Payment (FCP) (697.03)DOL1,073,199$1.00$1.00$1.00$1.00$1.00$1.00
140Asphalt Price Adjustment (698.04)DOL11,278$1.00$1.00$1.00$1.00$1.00$1.00
141Fuel Price Adjustment (698.05)DOL1,743$1.00$1.00$1.00$1.00$1.00$1.00
142Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00$1.00
143Mobilization (699.040001)LS1$650,000$696,626$700,000$800,000$825,000$770,000
NYSDOT contract D265594: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of December 18, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy