NYSDOT contract D265612 bid tabulation

NY Route 410 over the Black River Bridge Replacement. Let by New York State DOT on December 18, 2025, Lewis, Region 07. 2 bids received; low bid $24,193,378 by Tioga Construction Company Inc.

Owner
New York State DOT
Letting
18 DEC 2025
Pay items
176
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Tioga Construction Company Inc$24,193,378Low
2Vector Construction Corp$35,611,877+47%
NYSDOT contract D265612: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Tioga Construction Company Inc2. Vector Construction Corp
1Clearing and Grubbing (201.06)LS1$250,000$220,000
2 (202.120001)LS1$900,000$3,000,000
3Removal of Substructures (202.19)CY318$150.00$200.00
4Unclassified Excavation and Disposal (203.02)CY55,638$25.00$25.00
5Embankment In Place (203.03)CY37,460$36.00$36.00
6Select Granular Fill (203.07)CY211$100.00$80.00
7Surface Settlement Gauges (203.10)EACH7$1,000.00$1,400.00
8 (203.12030017)216,610$1.38$1.60
9 (203.12230017)LS1$250,000$280,000
10 (203.12430017)70,195$0.05$0.75
11Select Structural Fill (203.21)CY366$80.00$80.00
12Structure Excavation (206.01)CY4,590$23.00$50.00
13Trench and Culvert Excavation (206.0201)CY833$50.00$40.00
14Conduit Excavation and Backfill including Surface Restoration (206.03)LF580$65.00$15.00
15Geotextile Bedding (207.20)SY7$120.00$200.00
16Geotextile Separation (207.21)SY16,334$1.50$3.00
17Geotextile Drainage (207.22)SY539$2.60$4.00
18Prefabricated Composite Integral Abutment Drain (207.27)SY202$18.00$22.00
19 (208.01030022)117$80.00$90.00
20 (208.01040022)3$500.00$800.00
21Seed and Mulch – Temporary (209.1003)SY16,082$1.00$0.78
22Check Dam (Ditch Bottom Width >10′), Gravel Bag – Temporary (209.110204)EACH3$900.00$800.00
23Check Dam, (Ditch Bottom Width >3′ to 6′), Stone – Permanent (209.110602)EACH11$1,600.00$800.00
24Rolled Erosion Control Product, Class II Type A, Intermediate (209.1901)SY285$5.00$7.00
25Rolled Erosion Control Product, Class II Type D, Intermediate (209.1904)SY7,738$4.00$5.00
26Soil Stabilizers, Class IV Type A (209.2101)SY8,423$2.00$1.00
27Sediment Filter Log, 12″ (209.2301)LF5,633$8.00$8.00
28Subbase Course, Type 2 (304.12)CY7,185$90.00$82.00
29 (404.0001)TON258$80.00$80.00
30 (404.0983)TON1,264$130.00$140.00
31 (404.1989)TON1,782$114.00$125.00
32 (404.2589)TON2,115$109.00$123.00
33 (404.4289)TON154$186.00$186.00
34Diluted Tack Coat (407.0102)GAL1,564$9.00$11.00
35Asphalt Pavement Joint Adhesive (418.7603)LF9,202$0.45$0.50
36Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY1,717$10.00$12.00
37Steel H-Piles (HP 12x74) (551.012074)LF10,178$65.00$30.00
38Steel H-Piles (HP 16x162) (551.016162)LF6,840$140.00$65.00
39Splices for Steel H-Piles (551.12)EACH73$50.00$1.00
40Furnishing Equipment for Driving Piles (551.13)LS1$600,000$4,000,000
41Permanent Steel Sheeting (552.11)SF13,436$120.00$80.00
42Interim Steel Sheeting (552.15)SF1,843$50.00$80.00
43 (553.010001)EACH1$190,000$220,000
44 (553.010002)EACH1$300,000$850,000
45 (553.010003)EACH1$300,000$850,000
46 (553.030001)EACH1$10,000$500.00
47 (553.030002)EACH1$10,000$500.00
48 (553.030003)EACH1$10,000$500.00
49 (554.3001)SF1,350$60.00$76.00
50Footing Concrete, Performance (555.0011)CY404$1,200.00$2,200.00
51Concrete for Structures, Performance (555.0021)CY441$1,600.00$2,800.00
52Concrete for Structures, Performance (Deposited Under Water) (555.0031)CY351$750.00$1,400.00
53Performance Concrete Quality Adjustment – Footing Concrete (555.9901)QUALITY UNIT1$4.50$4.50
54Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$8.75$8.75
55Performance Concrete Quality Adjustment - Concrete Deposited Under Water (555.9903)QUALITY UNIT1$9.25$9.25
56Galvanized Bar Reinforcement for Structures (556.0203)LB98,643$2.50$3.00
57Stud Shear Connectors for Bridges (556.03)EACH13,370$4.50$6.00
58 (557.1019)SY236$625.00$800.00
59 (557.1119)SY2,758$625.00$800.00
60Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29)SY2,958$0.10$0.01
61Sidewalks and Safety Walks (557.30)SY242$200.00$500.00
62 (557.60010004)2,657$18.00$22.00
63Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901)QUALITY UNIT1$8.45$8.45
64Performance Concrete Quality Adjustment – Sidewalks and Safety Walks (557.9902)QUALITY UNIT1$8.10$8.10
65Longitudinal Sawcut Grooving of Structural Slab Surface (558.02)SY2,657$6.50$6.00
66Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01)SF2,898$0.50$2.00
67Protective Sealing of New Structural Concrete (559.02)SF10,056$0.50$2.00
68 (564.0501)LS1$4,000,000$6,320,000
69 (565.20310003)25$6,000.00$9,000.00
70Modular Expansion Joint System - Two Cell (566.02)LF70$2,200.00$2,500.00
71Steel Bridge Railing (Three-Rail) (568.54)LF1,305$181.00$220.00
72Transition Bridge Railing (568.70)LF128$168.00$200.00
73Lead-Exposure Control Plan (570.01)LS1$100.00$1.00
74Medical Testing (570.02)DOL5,000$1.00$1.00
75Personal-Exposure-Monitoring Sample Analysis (570.03)DOL2,500$1.00$1.00
76Decontamination Facilities (570.04)CALENDAR WEEK20$100.00$1.00
77 (570.09)LS1$500.00$1.00
78 (570.10)LS1$800.00$1.00
79 (572.010001)SF2,481$60.00$60.00
80Scuppers (Type B) (576.02)EACH18$4,000.00$3,400.00
81 (589.01)203,187$0.80$1.60
82 (603.171216)EACH9$400.00$250.00
83 (603.171614)EACH4$800.00$600.00
84 (603.9815)LF416$25.00$38.00
85 (603.9824)LF123$50.00$65.00
86 (604.302122)LF7.30$1,200.00$1,200.00
87Underdrain Filter, Type II (605.1001)CY36$110.00$110.00
88 (605.1701)LF2,458$3.00$4.50
89Box Beam Guide Railing (606.10)LF5,626$43.00$45.00
90Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002)LF298$52.00$55.00
91Box Beam Guide Railing (Shop Mitered) (606.100003)LF66$65.00$145.00
92Box Beam End Piece (606.120101)EACH3$545.00$650.00
93Box Beam Guide Railing End Assembly Type I (606.120102)EACH1$4,000.00$4,500.00
94Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH10$2,100.00$2,200.00
95Resetting Box Beam Guide Railing (New Posts) (606.5348)LF70$55.00$32.00
96Removing and Storing Box Beam Guide Railing End Assembly (606.6920)EACH1$300.00$700.00
97Removing and Disposing Cable Guide Railing (606.70)LF5,312$3.00$4.00
98Removing and Disposing Box Beam Guide Railing (606.73)LF512$5.00$6.00
99Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79)EACH12$60.00$240.00
100 (607.41010010)4,873$3.50$6.00
101Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT18$80.00$80.00
102Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON361$145.00$150.00
103Stone Curb – Bridge (Type A) (609.0301)LF60$55.00$90.00
104Stone Curb – Bridge (Type F1) (609.0302)LF1,304$53.00$70.00
105Mycorrhizal Fungi (610.0701)LB120$30.00$60.00
106Topsoil – Reuse On-Site Materials (610.1401)CY617$50.00$65.00
107Topsoil - Roadside (610.1402)CY860$100.00$98.00
108Topsoil - Lawns (610.1403)CY34$120.00$110.00
109Topsoil – Wetland Materials (610.1407)CY2,303$110.00$85.00
110Turf Establishment - Roadside (610.1601)SY7,738$1.25$1.00
111Turf Establishment -Lawns (610.1602)SY303$3.00$5.00
112Wildflower Seeding (610.17)SY10,361$1.50$2.00
113Watering Vegetation – As Specified (610.1901)1,000 GALLONS2,990$2.00$20.00
114Mowing (610.21)SY606$2.00$2.00
115 (611.0142)EACH18$675.00$670.00
116 (611.0232)EACH6$200.00$440.00
117 (611.0442)EACH348$60.00$90.00
118 (611.0722)EACH1,658$25.00$30.00
119Transplanting Herbaceous Plants (611.16)EACH10$50.00$300.00
120 (611.19010024)4$30.00$275.00
121 (611.19020024)2$20.00$130.00
122 (611.19040024)70$2.00$27.00
123 (613.04000001)43$50.00$220.00
124 (615.02050124)50$20.00$165.00
125 (615.02060124)7$80.00$640.00
126 (616.07000024)1,543$10.00$18.00
127 (616.15000024)3,608$20.00$35.00
128 (617.01020024)4,635$1.00$5.00
129 (617.01030024)859$15.00$27.00
130 (617.10000024)859$10.00$50.00
131 (617.11000024)LS1$500.00$5,000.00
132Basic Work Zone Traffic Control (619.01)LS1$150,000$775,000
133 (619.111112)EACH4$7,000.00$25,000
134Mailboxes (619.27)EACH4$300.00$310.00
135Stone Filling (Light) (620.03)CY2$400.00$310.00
136Stone Filling (Heavy) (620.05)CY1,046$130.00$125.00
137Bedding Material, Type 1 (620.0801)CY176$90.00$100.00
138Crushed Stone (In-Place Measure) (623.12)CY2,643$110.00$120.00
139Survey Operations (625.01)LS1$250,000$340,000
140Concrete Right of Way Markers Type H (High) (625.03)EACH2$2,000.00$1,000.00
141Steel Pin and Cap Right of Way Markers (625.05)EACH3$900.00$500.00
142Permanent Survey Markers (625.06)EACH4$2,500.00$1,000.00
143 (627.50140008)68$5.00$10.00
144Field Laboratory (637.01)EACH1$2,500.00$4,000.00
145Concrete Cylinder Curing Equipment (637.04)EACH1$5,000.00$7,500.00
146Engineer’s Field Office – Type 2 (637.12)MONTH30$2,500.00$2,500.00
147Rain Gauge (637.26)EACH1$50.00$100.00
148Office Technology and Supplies (637.34)DOL2,500$1.00$1.00
149Partnering Workshop (637.35)DOL5,000$1.00$1.00
150Construction Testing supplies – Consumables (637.36)DOL100$1.00$1.00
151 (637.41000115)30$150.00$100.00
152 (637.41000215)30$150.00$100.00
153 (637.41000315)30$150.00$100.00
154 (645.34010104)1$500.00$2,500.00
155 (645.34010204)1$500.00$2,500.00
156Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF91.30$55.00$44.00
157Type A Sign Posts (645.81)EACH19$240.00$210.00
158Reference Marker Panel (646.21)EACH8$45.00$30.00
159Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22)EACH26$18.00$13.00
160Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH2$24.00$17.00
161Steel Post, 1.1 lb/ft (646.31)EACH12$90.00$135.00
162Steel Post, 2.0 lb/ft (646.32)EACH24$110.00$70.00
163Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31)EACH5$160.00$250.00
164Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41)EACH3$7.00$50.00
165Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH25$7.00$25.00
166 (647.83001002)13$6.00$20.00
167Welded Frame & Reticuline Grate 22 (655.1122)EACH1$2,000.00$1,700.00
168 (662.60840201)LS1$10,000$42,000
169White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF12,846$0.85$1.00
170Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF5,486$0.85$1.00
171 (691.04000020)109,200$1.00$1.00
172Field Change Payment (FCP) (697.03)DOL1,206,000$1.00$1.00
173Asphalt Price Adjustment (698.04)DOL11,245$1.00$1.00
174Fuel Price Adjustment (698.05)DOL26,330$1.00$1.00
175Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00
176Mobilization (699.040001)LS1$930,000$1,280,000
NYSDOT contract D265612: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of December 18, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way