NYSDOT contract D265657 bid tabulation

CULVERT RESILIENCY PROJECT - VARIOUS LOCATIONS. Let by New York State DOT on December 18, 2025, Clinton, Franklin, Jefferson, St. Lawrence, Region 07. 2 bids received; low bid $9,137,555 by Kubricky-Jointa Lime LLC.

Owner
New York State DOT
Letting
18 DEC 2025
Pay items
136
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Kubricky-Jointa Lime LLC$9,137,555Low
2Luck Brothers Inc$12,601,601+38%
NYSDOT contract D265657: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Kubricky-Jointa Lime LLC2. Luck Brothers Inc
1Clearing and Grubbing (201.06)LS1$42,261$74,706
2 (202.120001)LS1$25,200$18,514
3Unclassified Excavation and Disposal (203.02)CY5,475$24.50$55.86
4Embankment In Place (203.03)CY11,456$23.00$89.96
5Select Granular Fill (203.07)CY1,268$105.00$142.22
6Structure Excavation (206.01)CY11,832$19.50$73.03
7Trench and Culvert Excavation (206.0201)CY498$37.00$108.36
8Geotextile Bedding (207.20)SY684$3.70$3.52
9Geotextile Drainage (207.22)SY54$10.50$32.11
10Geotextile Stabilization (207.24)SY1,719$0.95$3.14
11Prefabricated Composite Structural Drain (207.26)SY648$16.00$26.81
12 (208.01030022)29$345.00$154.74
13Seed and Mulch – Temporary (209.1003)SY7,344$2.10$2.02
14 (209.11000001)6$87.50$1,551.39
15Check Dam (Ditch Bottom Width 0.0 to 3′), Gravel Bag – Temporary (209.110201)EACH4$260.00$915.55
16Check Dam (Ditch Bottom Width >3′ to 6′), Gravel Bag – Temporary (209.110202)EACH5$520.00$1,111.34
17Check Dam, (Ditch Bottom Width 0.0 to 3′), Stone – Permanent (209.110601)EACH2$830.00$1,527.76
18Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301)SY2,685$7.60$8.27
19Stabilized Construction Access (209.22)SY800$25.00$43.33
20Sediment Filter Log, 12″ (209.2301)LF4,182$10.50$9.58
21Subbase Course, Type 1 (304.11)CY18$31.00$351.64
22Subbase Course, Type 2 (304.12)CY3,850$80.50$101.82
23 (404.0001)TON215$90.00$90.00
24 (404.0983)TON1,133$175.00$168.05
25 (404.1989)TON1,301$140.00$161.06
26 (404.2589)TON1,836$125.00$144.20
27 (404.4289)TON296$175.00$199.96
28 (404.4389)TON444$145.00$157.53
29Diluted Tack Coat (407.0102)GAL1,607$4.00$5.54
30Asphalt Pavement Joint Adhesive (418.7603)LF2,675$4.35$1.16
31Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY4,182$11.50$18.68
32Temporary Steel Sheeting (552.13)SF7,300$45.00$56.21
33 (552.2001)LF234$205.00$280.05
34 (552.2101)LF48$1,050.00$2,462.85
35 (552.2201)LF391$585.00$699.72
36 (552.230201)SF1,234$40.00$35.49
37 (553.020001)EACH1$13,800$343,661
38 (553.020002)EACH1$13,800$320,455
39 (553.030001)EACH1$28,600$145,511
40 (553.030002)EACH1$29,700$134,789
41 (553.030003)EACH1$56,100$132,541
42 (553.030004)EACH1$60,900$118,801
43 (554.3001)SF436$69.50$46.58
44Footing Concrete, Performance (555.0011)CY79.50$1,100.00$1,174.84
45Concrete for Structures, Performance (555.0021)CY44$1,950.00$2,264.63
46Performance Concrete Quality Adjustment – Footing Concrete (555.9901)QUALITY UNIT1$6.50$6.50
47Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$13.50$13.50
48Uncoated Bar Reinforcement for Concrete Structures (556.0201)LB3,548$4.15$13.10
49Epoxy-Coated Bar Reinforcement for Structures (556.0202)LB5,121$3.40$13.59
50Protective Sealing of New Structural Concrete (559.02)SF919$2.25$1.02
51 (562.0101)SY79$2,000.00$2,120.84
52Performance Concrete Quality Adjustment (562.99)QUALITY UNIT1$20.00$20.00
53Steel Bridge Railing (Three-Rail) (568.54)LF89$265.00$253.70
54Transition Bridge Railing (568.70)LF256$195.00$189.49
55Drilling and Grouting Bolts or Reinforcing Bars (586.0201)EACH30$75.00$343.80
56 (595.50000018)10,348$4.60$3.28
57 (603.171316)EACH4$1,150.00$960.40
58 (603.171614)EACH4$1,900.00$1,237.60
59 (603.64080815)78$2,300.00$2,705.00
60 (603.64160815)170.50$3,150.00$3,917.34
61 (603.67000001)234$2,800.00$3,005.53
62 (603.9818)LF68$115.00$117.58
63 (603.9824)LF165$88.00$98.37
64Underdrain Filter, Type I (605.0901)CY10$63.00$216.03
65 (605.1502)LF121$18.00$39.92
66Box Beam Guide Railing (606.10)LF2,808$52.00$50.31
67Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002)LF102$63.50$61.31
68Box Beam Guide Railing End Assembly Type I (606.120102)EACH9$4,700.00$4,529.89
69Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH9$2,450.00$2,383.17
70Removing and Storing Box Beam Guide Railing (606.63)LF1,208$5.15$4.99
71Removing and Storing Box Beam Guide Railing End Assembly (606.6920)EACH10$170.00$166.19
72Removing and Disposing Cable Guide Railing (606.70)LF1,885$2.30$2.22
73Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79)EACH7$575.00$553.93
74 (607.41010010)500$6.70$6.09
75 (607.96000008)48$26.00$34.67
76Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT4$90.00$90.00
77Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON81$350.00$412.12
78Stone Curb – Bridge (Type A) (609.0301)LF69$290.00$415.05
79Optional Curb (Precast Concrete Type PT4 or Cast-In-Place Concrete Type T4) (609.0903)LF450$265.00$138.36
80Mycorrhizal Fungi (610.0701)LB2$57.50$55.40
81Turf Establishment – Performance (610.1605)SY7,344$17.00$12.59
82 (611.0132)EACH1$1,050.00$997.09
83 (611.0272)EACH1$915.00$886.30
84 (611.0452)EACH3$140.00$132.95
85 (613.04000001)77$205.00$276.58
86 (615.01010108)263$170.00$254.22
87Basic Work Zone Traffic Control (619.01)LS1$1,185,000$1,224,547
88Type III Construction Barricades (619.04)EACH54$155.00$169.86
89 (619.080101)LF25,209$1.15$1.11
90 (619.080102)LF19,705$1.15$1.11
91 (619.100101)LF24,879$1.15$1.11
92 (619.111112)EACH8$4,350.00$9,726.14
93 (619.130101)EACH1$70,600$99,238
94 (619.130201)EACH1$10,100$36,517
95 (619.130202)EACH1$13,400$46,012
96Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711)LF890$45.50$22.65
97Temporary Positive Barrier – Category 3 (Pinning Prohibited) (619.1713)LF560$18.00$32.04
98Temporary Positive Barrier – Category 4 (Pinning Permitted) (619.1714)LF521$56.00$41.16
99Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715)LF695$37.00$30.95
100Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716)LF1,390$55.50$30.95
101Warning Lights on Temporary Positive Barriers (619.1719)EACH156$27.50$71.53
102Temporary Impact Attenuator - Redirective (Test Level 2) (619.1802)EACH9$7,350.00$6,759.68
103Temporary Rumble Strips (619.22)LF1,728$9.95$16.68
104Stone Filling (Light) (620.03)CY33$315.00$174.58
105Stone Filling (Medium) (620.04)CY1,376$140.00$113.50
106Bedding Material, Type 1 (620.0801)CY426$105.00$109.08
107Bedding Material, Type 2 (620.0802)CY62$105.00$122.29
108 (621.05020004)1,010$13.50$11.41
109Crushed Stone (In-Place Measure) (623.12)CY186$180.00$332.26
110Survey Operations (625.01)LS1$225,000$122,098
111Concrete Right of Way Markers Type H (High) (625.03)EACH26$1,600.00$1,756.62
112 (625.110001)EACH1$23,500$75,266
113 (627.50140008)2,986$6.05$7.65
114Field Laboratory (637.01)EACH2$25,400$3,161.05
115Concrete Cylinder Curing Equipment (637.04)EACH4$145.00$1,531.17
116Engineer’s Field Office – Type 2 (637.12)MONTH48$2,200.00$2,976.93
117Rain Gauge (637.26)EACH1$185.00$167.04
118Office Technology and Supplies (637.34)DOL5,000$1.00$1.00
119Construction Testing supplies – Consumables (637.36)DOL100$1.00$1.00
120 (637.41000115)24$140.00$321.59
121 (637.41000215)24$140.00$321.59
122Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF41$47.00$45.42
123Type A Sign Posts (645.81)EACH6$230.00$221.57
124Reference Marker Panel (646.21)EACH4$32.00$31.02
125Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH36$18.50$17.73
126Steel Post, 2.0 lb/ft (646.32)EACH30$74.50$72.01
127White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF10,100$2.85$2.77
128Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF10,647$2.85$2.77
129White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304)EACH8$86.00$83.09
130White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404)EACH3$285.00$276.97
131 (691.04000020)63,700$1.00$1.00
132Field Change Payment (FCP) (697.03)DOL671,000$1.00$1.00
133Asphalt Price Adjustment (698.04)DOL6,485$1.00$1.00
134Fuel Price Adjustment (698.05)DOL3,240$1.00$1.00
135Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00
136Mobilization (699.040001)LS1$345,000$390,121
NYSDOT contract D265657: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of December 18, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy