NYSDOT contract D265687 bid tabulation
Ground Mounted Sign Replacement Project, Various locations. Let by New York State DOT on February 5, 2026, Oswego, Region 03. 6 bids received; low bid $487,375 by US Traffic Control Inc.
- Owner
- New York State DOT
- Letting
- 05 FEB 2026
- Pay items
- 28
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | US Traffic Control Inc | $487,375 | Low |
| 2 | Emi Guide Rail LLC | $592,999 | +22% |
| 3 | O H Striping Inc | $629,381 | +29% |
| 4 | Elderlee Inc | $721,949 | +48% |
| 5 | Power Line Constructors Inc | $746,824 | +53% |
| 6 | DD&N Contracting LLC | $796,000 | +63% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. US Traffic Control Inc | 2. Emi Guide Rail LLC | 3. O H Striping Inc | 4. Elderlee Inc | 5. Power Line Constructors Inc | 6. DD&N Contracting LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | (201.07010004) | 10 | $500.00 | $330.00 | $345.60 | $250.00 | $568.00 | $1,000.00 | |
| 2 | Turf Establishment - Roadside (610.1601) | SY | 25 | $100.00 | $23.00 | $127.46 | $50.00 | $82.83 | $60.00 |
| 3 | Basic Work Zone Traffic Control (Daily Operations) (619.0101) | LS | 1 | $25,000 | $120,000 | $132,387 | $101,000 | $163,805 | $146,082 |
| 4 | Survey Operations (625.01) | LS | 1 | $1,000.00 | $600.00 | $37,153 | $500.00 | $6,063.00 | $500.00 |
| 5 | Engineer’s Field Office – Type 1 (637.11) | MONTH | 12 | $1,500.00 | $1,750.00 | $2,500.00 | $4,000.00 | $1,967.00 | $1,800.00 |
| 6 | Office Technology and Supplies (637.34) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 7 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 305 | $31.00 | $25.25 | $17.56 | $64.00 | $48.08 | $43.00 |
| 8 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 3,930 | $32.00 | $25.75 | $20.64 | $46.00 | $34.62 | $47.00 |
| 9 | Type A Sign Posts (645.81) | EACH | 825 | $175.00 | $230.00 | $182.35 | $220.00 | $243.00 | $236.00 |
| 10 | Type A Sign Posts with Extra Embedment (645.8104) | EACH | 190 | $180.00 | $231.50 | $142.74 | $250.00 | $258.00 | $242.00 |
| 11 | High-Capacity Type A Sign Posts with Soil Plates Only (645.8106) | EACH | 12 | $1,100.00 | $1,300.00 | $1,259.98 | $1,100.00 | $1,546.00 | $982.00 |
| 12 | (645.81090003) | 60 | $65.00 | $40.00 | $63.17 | $100.00 | $50.65 | $90.00 | |
| 13 | (645.830202) | EACH | 4 | $2,500.00 | $2,750.00 | $3,497.23 | $4,000.00 | $3,283.00 | $2,030.00 |
| 14 | Pole-Mounted Sign Support System (Band Mounting) (645.85) | EACH | 2 | $225.00 | $50.00 | $214.12 | $350.00 | $191.00 | $212.00 |
| 15 | Reference Marker Panel (646.21) | EACH | 218 | $30.00 | $35.00 | $57.16 | $38.00 | $38.34 | $44.00 |
| 16 | Steel Post, 2.0 lb/ft (646.32) | EACH | 210 | $70.00 | $65.00 | $122.86 | $75.00 | $75.69 | $178.00 |
| 17 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 1 | $150.00 | $150.00 | $732.08 | $260.00 | $123.00 | $400.00 |
| 18 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 5 | $25.00 | $22.50 | $424.93 | $35.00 | $18.91 | $75.00 |
| 19 | Remove and Dispose Sign Panel, Sign Panel Assembly Size II (30-100 Square Feet) (647.52) | EACH | 5 | $75.00 | $23.50 | $424.93 | $70.00 | $191.00 | $75.00 |
| 20 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 570 | $40.00 | $7.00 | $37.27 | $40.00 | $52.52 | $75.00 |
| 21 | Remove and Dispose High Capacity Type A Ground Mounted Sign Support and Foundation (647.64) | EACH | 6 | $100.00 | $140.00 | $293.14 | $80.00 | $214.00 | $75.00 |
| 22 | Remove and Dispose Type B Ground Mounted Sign Support and Foundation (647.65) | EACH | 1 | $350.00 | $500.00 | $988.92 | $150.00 | $903.00 | $75.00 |
| 23 | (647.83001002) | 190 | $25.00 | $5.00 | $47.37 | $15.00 | $12.27 | $75.00 | |
| 24 | Field Change Payment (FCP) (697.03) | DOL | 25,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 25 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 26 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 27 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 28 | Mobilization (699.040001) | LS | 1 | $18,745 | $22,450 | $24,207 | $27,000 | $25,000 | $21,038 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 5, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.