NYSDOT contract D265747 bid tabulation
PAVEMENT RESURFACING - Route 5 Bypass. Let by New York State DOT on March 5, 2026, Onondaga, Region 03. 3 bids received; low bid $7,282,602 by Seneca Stone Corp.
- Owner
- New York State DOT
- Letting
- 05 MAR 2026
- Pay items
- 44
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Seneca Stone Corp | $7,282,602 | Low |
| 2 | Barrett Paving Materials Inc | $8,020,460 | +10% |
| 3 | Sealand Contractors Corp. | $12,790,000 | +76% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Seneca Stone Corp | 2. Barrett Paving Materials Inc | 3. Sealand Contractors Corp. |
|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 8,134 | $50.00 | $40.00 | $107.00 |
| 2 | (203.24010017) | 500 | $50.00 | $55.00 | $195.00 | |
| 3 | Subbase Course, Optional Type (304.15) | CY | 4,445 | $50.00 | $60.00 | $168.00 |
| 4 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 114 | $110.00 | $110.00 | $110.00 |
| 5 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 1,200 | $110.00 | $110.00 | $110.00 |
| 6 | (404.0189) | TON | 1,312 | $100.00 | $100.00 | $165.00 |
| 7 | (404.1989) | TON | 2,251 | $140.00 | $90.00 | $277.00 |
| 8 | (404.3789) | TON | 3,751 | $150.00 | $70.00 | $271.00 |
| 9 | (406.0952) | TON | 34,969 | $96.00 | $110.00 | $135.00 |
| 10 | Straight Tack Coat (407.0103) | GAL | 18,074 | $2.50 | $2.71 | $16.50 |
| 11 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 218,965 | $0.10 | $0.42 | $1.00 |
| 12 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 295,988 | $1.00 | $1.90 | $4.25 |
| 13 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $400,000 | $681,933 | $618,414 |
| 14 | Type III Construction Barricades (619.04) | EACH | 36 | $100.00 | $90.00 | $300.00 |
| 15 | (619.0901) | LF | 48,839 | $0.25 | $0.23 | $0.25 |
| 16 | (619.111113) | EACH | 4 | $10,000 | $6,000.00 | $20,000 |
| 17 | Maintain Traffic Signal Equipment (Requirement C) Intersection (619.1613) | MONTH | 6 | $100.00 | $100.00 | $105.00 |
| 18 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $1,000.00 | $15,000 | $100,000 |
| 19 | Traffic Control Supervisor (619.25) | MONTH | 6 | $1,000.00 | $6,000.00 | $25,000 |
| 20 | Survey Operations (625.01) | LS | 1 | $1,000.00 | $32,000 | $28,000 |
| 21 | (627.50140008) | 1,100 | $20.00 | $4.50 | $20.00 | |
| 22 | Engineer’s Field Office – Type 1 (637.11) | MONTH | 6 | $2,500.00 | $3,000.00 | $3,000.00 |
| 23 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 | $1.00 |
| 24 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 |
| 25 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 26 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 87,041 | $0.30 | $0.30 | $0.50 |
| 27 | (680.05010007) | 2 | $27,603 | $27,603 | $29,000 | |
| 28 | (680.05020007) | 2 | $4,263.00 | $4,263.00 | $4,500.00 | |
| 29 | (680.05040004) | 1 | $3,663.00 | $3,663.00 | $3,900.00 | |
| 30 | (680.77000105) | 1 | $1,715.00 | $1,715.00 | $1,800.00 | |
| 31 | (680.77000205) | 1 | $3,712.00 | $4,158.00 | $3,900.00 | |
| 32 | (680.80324515) | 2 | $2,451.00 | $2,451.00 | $2,600.00 | |
| 33 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 172,604 | $0.41 | $0.36 | $0.38 |
| 34 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 91,701 | $0.41 | $0.36 | $0.38 |
| 35 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 48,678 | $2.15 | $2.75 | $2.90 |
| 36 | Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204) | LF | 8,170 | $2.15 | $2.75 | $2.90 |
| 37 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 40 | $115.00 | $49.00 | $52.00 |
| 38 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 41 | $220.00 | $210.00 | $221.00 |
| 39 | (691.04000020) | 21,000 | $1.00 | $1.00 | $1.00 | |
| 40 | Field Change Payment (FCP) (697.03) | DOL | 580,000 | $1.00 | $1.00 | $1.00 |
| 41 | Asphalt Price Adjustment (698.04) | DOL | 37,378 | $1.00 | $1.00 | $1.00 |
| 42 | Fuel Price Adjustment (698.05) | DOL | 1,496 | $1.00 | $1.00 | $1.00 |
| 43 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 44 | Mobilization (699.040001) | LS | 1 | $260,000 | $271,223 | $491,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 5, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.