NCDOT contract C205224 bid tabulation
BRIDGE REPLACEMENT (EXPRESS DESIGN-BUILD). BRIDGE #800239 OVER CATHEYS CREEK ON SR-1325 (NANNEYTOWN RD). Let by North Carolina DOT on August 18, 2026, Rutherford. 4 bids received; low bid $1,484,000 by R.E. Burns & Sons Co., Inc..
- Owner
- North Carolina DOT
- Letting
- 18 AUG 2026
- Pay items
- 7
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | R.E. Burns & Sons Co., Inc. | $1,484,000 | Low |
| 2 | Kemp Sigmon Construction Co Inc | $1,672,000 | +13% |
| 3 | Wright Brothers Civil Construction LLC | $2,303,000 | +55% |
| 4 | Blythe Construction Inc | $2,486,005 | +68% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R.E. Burns & Sons Co., Inc. | 2. Kemp Sigmon Construction Co Inc | 3. Wright Brothers Civil Construction LLC | 4. Blythe Construction Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $148,000 | $160,000 | $230,000 | $240,000 |
| 0002 | Generic miscellaneous item (LS) - design and construction of bridge #800239 (0000900000-N) | LS | 1 | $425,000 | $820,000 | $1,309,475 | $1,595,505 |
| 0003 | Generic miscellaneous item (EA) - end bents structure #800239 (0000915000-N) | EACH | 2 | $65,000 | $60,000 | $81,000 | $60,000 |
| 0004 | Generic miscellaneous item (EA) - right of way acquisition at bridge #800239 (0000915000-N) | EACH | 4 | $8,000.00 | $7,200.00 | $9,500.00 | $7,000.00 |
| 0005 | Generic miscellaneous item (LF) - bridge length structure #800239 (0000930000-E) | LF | 100 | $6,740.00 | $4,800.00 | $4,935.00 | $4,500.00 |
| 0006 | Generic miscellaneous item (LF) - foundation length at end bent #1 structure #800239 (0000930000-E) | LF | 32 | $1,000.00 | $900.00 | $905.00 | $700.00 |
| 0007 | Generic miscellaneous item (LF) - foundation length at end bent #2 structure #800239 (0000930000-E) | LF | 43 | $1,000.00 | $800.00 | $955.00 | $700.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of August 18, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.