ODOT contract 250074 bid tabulation
MRG-Appalachian Hills WLA-NR1 (TWO LANE RESURFACING). Let by Ohio DOT on January 30, 2025, MRG. 4 bids received; low bid $304,403 by Shelly & Sands Inc, -6.9% against the engineer's estimate of $327,000.
- Owner
- Ohio DOT
- Letting
- 30 JAN 2025
- Pay items
- 34
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $304,403 | Low | -7.0% |
| 2 | Alan Stone Co Inc | $359,548 | +18% | +10% |
| 3 | MC Kee Paving & Sealing LLC | $363,911 | +20% | +11% |
| 4 | NLS Paving, Inc | $384,450 | +26% | +18% |
Engineer's estimate: $327,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Alan Stone Co Inc | 3. MC Kee Paving & Sealing LLC | 4. NLS Paving, Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 | $2,600.00 | $10,000 | $3,000.00 |
| 2 | Pavement removed (202E23000) | SY | 193 | $7.00 | $20.00 | $20.00 | $8.00 |
| 3 | Excavation (203E10000) | CY | 812 | $38.00 | $25.00 | $20.00 | $50.00 |
| 4 | Embankment (203E20000) | CY | 214 | $25.00 | $30.00 | $20.00 | $40.00 |
| 5 | Subgrade compaction (204E10000) | SY | 1,153 | $10.00 | $6.00 | $4.00 | $4.00 |
| 6 | Ditch cleanout (209E10000) | FT | 50 | $20.00 | $20.00 | $20.00 | $35.00 |
| 7 | Linear grading, as per plan (209E60501) | MI | 0.29 | $12,445 | $20,000 | $30,000 | $20,000 |
| 8 | Curb ramp (608E52000) | SF | 50 | $70.00 | $200.00 | $24.15 | $90.00 |
| 9 | Riprap, type D (601E11000) | SY | 1.80 | $1,425.00 | $1,700.00 | $1,450.00 | $2,500.00 |
| 10 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 12.30 | $210.00 | $230.00 | $525.00 | $500.00 |
| 11 | Seeding and mulching (659E10000) | SY | 6,700 | $1.00 | $1.50 | $4.00 | $1.00 |
| 12 | Commercial fertilizer (659E20000) | TON | 0.60 | $1,350.00 | $670.00 | $1,600.00 | $1,330.00 |
| 13 | Lime (659E31000) | ACRE | 1.39 | $160.00 | $950.00 | $300.00 | $160.00 |
| 14 | Water (659E35000) | MGAL | 36 | $1.00 | $120.00 | $1.00 | $1.00 |
| 15 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 16 | Class QC1 concrete, headwall (511E46610) | CY | 0.70 | $4,375.00 | $7,400.00 | $4,000.00 | $4,150.00 |
| 17 | Class QC1 concrete, culvert (511E47010) | CY | 2.60 | $515.00 | $280.00 | $450.00 | $1,650.00 |
| 18 | 18" conduit, type A (611E07200) | FT | 52 | $165.00 | $170.00 | $130.00 | $215.00 |
| 19 | Pavement repair, as per plan (253E02001) | CY | 10 | $375.00 | $200.00 | $257.00 | $250.00 |
| 20 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 518 | $190.00 | $260.00 | $256.00 | $215.00 |
| 21 | Aggregate base (304E20000) | CY | 331 | $100.00 | $75.00 | $107.50 | $140.00 |
| 22 | Non-tracking tack coat (407E20000) | GAL | 177 | $3.25 | $5.00 | $5.00 | $4.00 |
| 23 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 147 | $300.00 | $340.00 | $290.00 | $280.00 |
| 24 | Ground mounted support, no. 3 post (630E03100) | FT | 70 | $37.50 | $35.00 | $25.00 | $25.00 |
| 25 | Sign post reflector (630E08600) | EACH | 1 | $55.00 | $120.00 | $100.00 | $100.00 |
| 26 | Sign, flat sheet (630E80100) | SF | 39.25 | $35.00 | $40.00 | $40.00 | $40.00 |
| 27 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $260.00 | $120.00 | $50.00 | $500.00 |
| 28 | Center line (644E00300) | MI | 0.26 | $12,500 | $14,000 | $17,000 | $13,600 |
| 29 | Stop line (644E00500) | FT | 25 | $10.00 | $10.00 | $15.00 | $13.00 |
| 30 | Crosswalk line, 24" (644E00630) | FT | 30 | $10.00 | $10.00 | $32.00 | $10.00 |
| 31 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $1,250.00 | $4,500.00 | $5,500.00 | $2,143.60 |
| 32 | Maintaining traffic (614E11000) | LS | 1 | $4,250.00 | $17,000 | $10,000 | $25,000 |
| 33 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,649.48 | $7,100.00 | $10,000 | $10,000 |
| 34 | Mobilization (624E10000) | LS | 1 | $15,101 | $11,500 | $12,000 | $25,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 30, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.