ODOT contract 250121 bid tabulation
D12-West Woods Road Replace (CULVERT REPLACEMENT). Let by Ohio DOT on February 27, 2025, District 12. 2 bids received; low bid $817,437 by Eclipse Co LLC, +19% against the engineer's estimate of $686,000.
- Owner
- Ohio DOT
- Letting
- 27 FEB 2025
- Pay items
- 47
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eclipse Co LLC | $817,437 | Low | +19% |
| 2 | Union Industrial Contractors Inc | $826,294 | +1.0% | +20% |
Engineer's estimate: $686,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eclipse Co LLC | 2. Union Industrial Contractors Inc |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $8,500.00 | $7,500.00 |
| 2 | Pavement removed (202E23000) | SY | 63 | $11.25 | $55.00 |
| 3 | Excavation (203E10000) | CY | 67 | $39.25 | $36.00 |
| 4 | Subgrade compaction (204E10000) | SY | 193 | $1.00 | $3.00 |
| 5 | Crushed aggregate slope protection, as per plan (601E20001) | SY | 53 | $75.25 | $46.00 |
| 6 | Guardrail, misc.:steel backed timber guardrail typ (606E98000) | FT | 100 | $139.00 | $133.50 |
| 7 | Guardrail, misc.:steel backed timber guardrail ter (606E98100) | EACH | 2 | $4,640.00 | $4,480.00 |
| 8 | Fence, misc.:timber guardrail (607E98000) | FT | 71 | $90.00 | $85.00 |
| 9 | Topsoil (659E00300) | CY | 12 | $102.75 | $100.00 |
| 10 | Seeding and mulching (659E10000) | SY | 112 | $19.75 | $19.80 |
| 11 | Repair seeding and mulching (659E14000) | SY | 6 | $6.50 | $6.50 |
| 12 | Commercial fertilizer (659E20000) | TON | 0.02 | $840.00 | $840.00 |
| 13 | Lime (659E31000) | ACRE | 0.02 | $50.00 | $50.00 |
| 14 | Water (659E35000) | MGAL | 0.60 | $1.00 | $1.00 |
| 15 | Erosion control (832E30000) | EACH | 3,500 | $1.00 | $1.00 |
| 16 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 17 | $600.00 | $380.00 |
| 17 | Aggregate base (304E20000) | CY | 32 | $112.00 | $110.00 |
| 18 | Tack coat (407E10000) | GAL | 8 | $100.00 | $5.00 |
| 19 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 5 | $1,000.00 | $550.00 |
| 20 | Edge line, 4" (646E10000) | MI | 0.04 | $44,220 | $30,000 |
| 21 | Center line (646E10200) | MI | 0.02 | $88,415 | $40,000 |
| 22 | Structure removed (202E11000) | LS | 1 | $23,982 | $52,500 |
| 23 | Embankment (203E20000) | CY | 601 | $35.75 | $100.00 |
| 24 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $29,292 | $15,000 |
| 25 | Unclassified excavation (503E21100) | CY | 128 | $53.25 | $150.00 |
| 26 | Pile driving equipment mobilization (505E11100) | LS | 1 | $40,000 | $45,000 |
| 27 | 16" cast-in-place reinforced concrete piles, driven (507E00700) | FT | 1,210 | $106.50 | $75.00 |
| 28 | 16" cast-in-place reinforced concrete piles, furnished (507E00750) | FT | 1,320 | $91.25 | $120.00 |
| 29 | Epoxy coated steel reinforcement (509E10000) | LB | 6,981 | $3.50 | $2.65 |
| 30 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 10 | $3,342.25 | $1,895.00 |
| 31 | Class QC1 concrete, footing (511E46510) | CY | 81 | $844.50 | $707.00 |
| 32 | Class QC1 concrete, headwall (511E46610) | CY | 3 | $2,109.50 | $996.00 |
| 33 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 81 | $22.00 | $70.00 |
| 34 | Type 2 waterproofing (512E33000) | SY | 203 | $22.75 | $25.00 |
| 35 | 1" preformed expansion joint filler (516E13600) | SF | 34 | $5.75 | $20.00 |
| 36 | Porous backfill with geotextile fabric, as per plan (518E21201) | CY | 15 | $104.75 | $300.00 |
| 37 | 4" perforated corrugated plastic pipe (518E39800) | FT | 10 | $5.50 | $25.00 |
| 38 | Dynamic load testing (523E20000) | EACH | 1 | $13,000 | $5,000.00 |
| 39 | Special - structures: temporary bridle trail bridg (530E00200) | LS | 1 | $15,361 | $22,500 |
| 40 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 34 | $175.75 | $170.00 |
| 41 | Conduit, type A, precast reinforced concrete three sided flat topped culvert, as per plan (611E70001) | FT | 52 | $2,696.50 | $2,350.00 |
| 42 | Special - utility test hole (690E98000) | EACH | 2 | $289.75 | $3,500.00 |
| 43 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,000 | $8,000.00 |
| 44 | CPM progress schedule (108E10000) | LS | 1 | $8,324.50 | $2,000.00 |
| 45 | Maintaining traffic (614E11000) | LS | 1 | $6,210.75 | $5,000.00 |
| 46 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,482.25 | $7,500.00 |
| 47 | Mobilization (624E10000) | LS | 1 | $20,871 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.