ODOT contract 250138 bid tabulation

WYA-East Wyandot Ave. (TWO LANE RESURFACING). Let by Ohio DOT on February 27, 2025, WYA. 3 bids received; low bid $825,004 by Helms and Sons Excavating, +7.4% against the engineer's estimate of $768,000.

Owner
Ohio DOT
Letting
27 FEB 2025
Pay items
59
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Helms and Sons Excavating$825,004Low+7.0%
2Kokosing Construction Company Inc$860,343+4.0%+12%
3Shelly Company$876,302+6.0%+14%
ODOT contract 250138: bids by rank

Engineer's estimate: $768,000.

Bid tabulation

LinePay itemUnitQuantity1. Helms and Sons Excavating2. Kokosing Construction Company Inc3. Shelly Company
1Curb removed (202E32000)FT10$108.00$12.00$20.00
2Curb and gutter removed (202E32500)FT33$50.00$16.00$20.00
3Excavation (203E10000)CY127$45.00$55.00$60.00
4Reshaping under guardrail, as per plan (209E15001)STA7.05$2,000.00$550.00$250.00
5Topsoil furnished and placed (653E10000)CY57$125.00$125.00$150.00
6Seeding and mulching, class 2, as per plan (659E00511)SY1,018$2.00$1.50$5.00
7Catch basin adjusted to grade (611E98630)EACH2$2,000.00$1,100.00$1,500.00
8Pavement repair, as per plan (253E01001)SY2,889$65.00$70.00$100.00
9Pavement planing, asphalt concrete, 1.5" (254E01000)SY22,478$3.00$1.10$2.88
10Aggregate base (304E20000)CY19$150.00$145.00$120.00
11Non-tracking tack coat (407E20000)GAL1,958$3.00$2.75$2.00
12Asphalt concrete surface course, 12.5 MM, type A (448) (442E20000)CY849.10$325.00$320.00$260.00
13Asphalt concrete intermediate course, 9.5 MM, type A (448), as per plan (442E20101)CY75$310.00$320.00$280.00
14Asphalt concrete surface course, 12.5 MM, type A (449) (driveways) (442E22120)CY10.10$500.00$1,200.00$1,000.00
156" non-reinforced concrete pavement, class QC MS (452E10050)SY68$132.00$97.18$118.50
16Combination curb and gutter, type 2 (609E12000)FT33$97.00$42.00$79.00
17Curb, type 6 (609E26000)FT10$162.00$37.00$69.00
18Compacted aggregate (617E10100)CY77$109.00$30.00$120.00
19Rumble stripes, edge line (asphalt concrete) (618E41000)MI1.30$5,500.00$5,300.00$5,300.00
20Valve box adjusted to grade, as per plan (638E10801)EACH1$2,000.00$900.00$725.00
21Manhole adjusted to grade (611E99654)EACH2$3,000.00$975.00$1,400.00
22RPM (621E00100)EACH100$85.00$65.00$67.70
23Raised pavement marker removed (621E54000)EACH100$9.00$1.00$9.00
24Ground mounted support, no. 3 post (630E03100)FT883$12.00$12.00$12.00
25Street name sign support, no. 3 post (630E08520)FT2$12.00$12.00$12.00
26Sign, flat sheet, as per plan (630E80101)SF436.10$25.00$25.00$25.00
27Sign, double faced, street name (630E80500)EACH4$125.00$125.00$125.00
28Removal of ground mounted sign and disposal (630E84900)EACH111$20.00$20.00$20.00
29Removal of ground mounted post support and disposal (630E86002)EACH77$20.00$20.00$20.00
30Edge line, 4", type 1 (642E00100)MI0.16$5,000.00$2,000.00$5,000.00
31Center line, type 1 (642E00300)MI0.09$10,000$2,000.00$10,000
32Channelizing line, 8", type 1 (642E00400)FT320$1.00$1.00$1.00
33Stop line, type 1 (642E00500)FT36$3.00$3.00$3.00
34Transverse/diagonal line, type 1 (642E00700)FT242$3.00$3.00$3.00
35Island marking, type 1 (642E00900)SF96$5.00$3.00$5.00
36Lane arrow, type 1 (642E01300)EACH6$50.00$55.00$50.00
37Word on pavement, 96", type 1 (642E01410)EACH3$100.00$75.00$100.00
38Edge line, 4" (644E00100)MI1.30$2,750.00$4,000.00$2,750.00
39Center line (644E00300)MI1.25$5,500.00$7,000.00$5,500.00
40Channelizing line, 8" (644E00400)FT824$2.00$2.00$2.00
41Stop line (644E00500)FT84$8.00$7.00$8.00
42Transverse/diagonal line (644E00700)FT196$7.00$7.00$7.00
43Island marking (644E00900)SF157$10.00$5.00$10.00
44Lane arrow (644E01300)EACH16$85.00$100.00$85.00
45Asphalt concrete for maintaining traffic (614E13000)CY2$600.00$1,500.00$300.00
46Work zone center line, class III, 642 paint (614E21550)MI2.72$1,400.00$2,000.00$1,400.00
47Work zone edge line, class III, 4", 642 paint (614E22350)MI1.10$700.00$2,000.00$700.00
48Work zone channelizing line, class III, 8", 642 paint (614E23680)FT1,648$0.50$1.00$0.50
49Work zone transverse/diagonal line, class III, 642 paint (614E25620)FT196$3.00$3.00$3.00
50Work zone stop line, class III, 642 paint (614E26610)FT168$3.00$3.00$3.00
51Work zone arrow, class III, 642 paint (614E30650)EACH28$30.00$55.00$30.00
52Work zone island marking, class III, 642 paint (614E32800)SF157$5.00$3.00$5.00
53Premium for contract performance bond and for payment bond (103E05000)LS1$12,000$3,500.00$2,103.68
54Maintaining traffic (614E11000)LS1$35,750$150,325$90,000
55Construction layout stakes and surveying (623E10000)LS1$12,500$1,100.00$2,430.00
56Preconstruction survey monument verification and report (623E50000)LS1$7,500.00$1,250.00$3,000.00
57Post construction survey monument verification and report (623E51000)LS1$7,500.00$1,250.00$3,000.00
58Mobilization (624E10000)LS1$40,000$43,000$40,000
100Law enforcement officer with patrol car for assistance (614E11110)HR40$75.00$100.00$75.00
ODOT contract 250138: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy