ODOT contract 250327 bid tabulation
CLA-Old Reid Park Access Road (TWO LANE RESURFACING). Let by Ohio DOT on June 26, 2025, CLA. 2 bids received; low bid $257,800 by Fillmore Construction, -12% against the engineer's estimate of $294,000.
- Owner
- Ohio DOT
- Letting
- 26 JUN 2025
- Pay items
- 22
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fillmore Construction | $257,800 | Low | -12% |
| 2 | Cox Paving LLC | $266,246 | +3.0% | -9.0% |
Engineer's estimate: $294,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fillmore Construction | 2. Cox Paving LLC |
|---|---|---|---|---|---|
| 1 | Excavation (203E10000) | CY | 366 | $40.00 | $75.00 |
| 2 | Subgrade compaction (204E10000) | SY | 1,420 | $5.00 | $3.00 |
| 3 | Proof rolling (204E45000) | HR | 1 | $200.00 | $300.00 |
| 4 | Topsoil furnished and placed, as per plan (653E10001) | CY | 35 | $80.00 | $150.00 |
| 5 | Seeding and mulching, class 1, as per plan (659E00501) | SY | 300 | $5.00 | $6.00 |
| 6 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 |
| 7 | Pavement repair, as per plan (253E01001) | SY | 350 | $100.00 | $60.00 |
| 8 | Pavement planing, asphalt concrete, as per plan, ( (254E01001) | SY | 4,795 | $3.00 | $3.50 |
| 9 | Aggregate base (304E20000) | CY | 223 | $80.00 | $92.00 |
| 10 | Non-tracking tack coat (407E20000) | GAL | 910 | $3.50 | $4.25 |
| 11 | Stabilized crushed aggregate, as per plan (411E10001) | CY | 20 | $200.00 | $230.00 |
| 12 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 254 | $240.00 | $230.00 |
| 13 | Asphalt concrete intermediate course, type 1, (448) (441E50200) | CY | 200 | $220.00 | $231.00 |
| 14 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 90 | $216.00 | $215.00 |
| 15 | Valve box adjusted to grade (638E10800) | EACH | 2 | $1,000.00 | $120.00 |
| 16 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 4 | $2,500.00 | $1,500.00 |
| 17 | Parking lot stall marking, type 1 (642E01200) | FT | 242 | $7.00 | $5.00 |
| 18 | Handicap symbol marking, type 1 (642E01702) | EACH | 1 | $356.00 | $500.00 |
| 19 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,500.00 | $1,500.00 |
| 20 | Maintaining traffic (614E11000) | LS | 1 | $4,700.00 | $12,500 |
| 21 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $2,500.00 | $1,500.00 |
| 22 | Mobilization (624E10000) | LS | 1 | $5,000.00 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 26, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.