ODOT contract 250332 bid tabulation

HAM-US 22-11.41 (BRIDGE REPAIR). Let by Ohio DOT on June 26, 2025, HAM. 1 bid received; low bid $364,463 by Evers Steel Construction LLC, +35% against the engineer's estimate of $270,000.

Owner
Ohio DOT
Letting
26 JUN 2025
Pay items
17
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Evers Steel Construction LLC$364,463Low+35%
ODOT contract 250332: bids by rank

Engineer's estimate: $270,000.

Bid tabulation

LinePay itemUnitQuantity1. Evers Steel Construction LLC
2Structural steel members, level UF, as per plan (513E10201)LB399$18.00
3Structural steel, misc.: repair of damaged structu (513E95000)FT1.30$500.00
4Structural steel, misc.: repair of damaged structu (513E95000)FT16$400.00
5Structural steel, misc.: replace splice bolts (513E95030)EACH120$105.00
6Field painting of damaged structural steel, as per plan (514E20001)SF15$3,000.00
7Jacking and temporary support of superstructure, as per plan (516E47001)LS1$5,500.00
8Patching concrete structures with trowelable mortar (843E50000)SF1$12,500
9Damage assessment (849E10000)LS1$3,500.00
10Surface preparation (849E10500)LS1$3,500.00
11Repairing damaged members by grinding (849E10600)HR4$205.00
12Straightening damaged members (849E10700)LS1$69,800
13Grinding fins, tears, slivers on existing structural steel (885E00504)MNHR4$305.00
14Premium for contract performance bond and for payment bond (103E05000)LS1$8,500.00
15Maintaining traffic (614E11000)LS1$118,000
16Construction layout stakes and surveying (623E10000)LS1$1.00
17Mobilization (624E10000)LS1$67,000
100Portions of structure removed, as per plan(seconda (202E11401)LB229$10.00
ODOT contract 250332: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of June 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy