ODOT contract 250388 bid tabulation

MOT-/CLA GR Maint FY26 (GUARDRAIL REBUILDING). Let by Ohio DOT on August 14, 2025, MOT. 1 bid received; low bid $1,082,475 by Lake Erie Construction Company, -0.4% against the engineer's estimate of $1,087,000.

Owner
Ohio DOT
Letting
14 AUG 2025
Pay items
72
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Lake Erie Construction Company$1,082,475Low0.0%
ODOT contract 250388: bids by rank

Engineer's estimate: $1,087,000.

Bid tabulation

LinePay itemUnitQuantity1. Lake Erie Construction Company
1Guardrail removed (202E38000)FT1,900$3.20
2Guardrail post removed (202E38700)EACH14$10.00
3Anchor assembly removed, type A, as per plan (202E42001)EACH1$375.00
4Anchor assembly removed, type E (202E42010)EACH1$245.00
5Removal misc.:impact attenuator removed with site (202E98100)EACH1$395.00
6Guardrail, type 5 (606E13000)FT115$22.00
7Guardrail, type MGS (606E15050)FT1,000$23.20
8Guardrail, type MGS with long posts (606E15100)FT500$25.60
9Guardrail, barrier design, type 5 (606E15500)FT25$38.40
10Guardrail, barrier design, type MGS (606E15550)FT25$39.80
11Guardrail rebuilt, type MGS (606E16050)FT1,725$22.80
12Guardrail rebuilt, type MGS with long posts (606E16560)FT50$26.00
13Guardrail rebuilt, barrier design, type 5 (606E16600)FT125$38.80
14Guardrail rebuilt, barrier design, type MGS (606E16660)FT25$40.40
15Guardrail post (606E17900)EACH25$75.00
16Anchor assembly, type B (606E26000)EACH1$2,550.00
17Anchor assembly, MGS type B (606E26050)EACH1$2,625.00
18Anchor assembly, type E (606E26100)EACH4$3,175.00
19Anchor assembly, MGS type E (MASH 2016) (606E26150)EACH22$3,240.00
20Anchor assembly, type T (606E26500)EACH1$1,150.00
21Anchor assembly, MGS type T (606E26550)EACH3$1,480.00
22Anchor assembly rebuilt, type B, as per plan (606E27841)EACH5$2,480.00
23Anchor assembly rebuilt, MGS type B, as per plan (606E27847)EACH1$2,575.00
24Anchor assembly rebuilt, type E, as per plan (606E27851)EACH40$2,020.00
25Anchor assembly rebuilt, MGS type E, as per plan (606E27861)EACH35$2,625.00
26Anchor assembly rebuilt, type T, as per plan (606E27901)EACH7$680.00
27Anchor assembly rebuilt, MGS type T, as per plan (606E27911)EACH3$1,375.00
28Bridge terminal assembly, type 1 (606E35000)EACH2$1,425.00
29MGS bridge terminal assembly, type 1 (606E35002)EACH1$2,820.00
30Bridge terminal assembly rebuilt, type 1, as per plan (606E35011)EACH3$1,675.00
31MGS bridge terminal assembly rebuilt, type 1, as per plan (606E35013)EACH1$2,450.00
32Bridge terminal assembly rebuilt, type 2, as per plan (606E35111)EACH2$550.00
33MGS bridge terminal assembly rebuilt, type 2, as per plan (606E35113)EACH1$575.00
34Special - cable barrier, anchor repair (606E54950)EACH2$1,550.00
35Special - cable barrier, readjust cable tension (R (606E54950)EACH3$375.00
36Special - cable barrier, tensioning (606E55200)EACH3$395.00
37Special - cable barrier, anchor reconstructed (606E55210)EACH1$2,480.00
38Impact attenuator, type 1 (unidirectional) (606E60002)EACH1$9,125.00
39Impact attenuator, type 1 (bidirectional) (606E60012)EACH5$9,220.00
40Impact attenuator, type 2 (unidirectional)70 MPH, (606E60022)EACH1$32,550
41Impact attenuator, type 2 (bidirectional)70 MPH, 3 (606E60028)EACH1$34,850
42Impact attenuator, type 3 (bidirectional), 60 MPH, (606E60050)EACH1$48,325
43Impact attenuator rebuilt, type 1 (unidirectional), as per plan (606E60061)EACH1$5,650.00
44Impact attenuator rebuilt, type 1 (bidirectional), as per plan (606E60071)EACH1$5,750.00
45Impact attenuator, misc.:belt nose assembly (quard (606E61000)EACH5$3,275.00
46Impact attenuator, misc.:cartridge, type 1 (quadgu (606E61000)EACH25$1,320.00
47Impact attenuator, misc.:cartridge, type 2 (quardg (606E61000)EACH25$1,320.00
48Impact attenuator, misc.:cylinder QE1 (quadguard E (606E61000)EACH3$3,260.00
49Impact attenuator, misc.:cylinder QE2 (quadguard E (606E61000)EACH3$3,495.00
50Impact attenuator, misc.:diaphram assembly (24"-36 (606E61000)EACH6$2,725.00
51Impact attenuator, misc.:diaphram assembly (69"-90 (606E61000)EACH3$4,220.00
52Impact attenuator, misc.:fender panel assembly (QU (606E61000)EACH10$1,725.00
53Impact attenuator, misc.:plastic nose piece (tracc (606E61000)EACH3$625.00
54Guardrail, misc.:type 5 rebuilt using steel post (606E98000)FT462.50$24.40
55Guardrail, misc.:type 5 rebuilt using wood post (606E98000)FT4,000$21.20
56Guardrail, misc.:urgent repair (606E98100)EACH25$650.00
57Special - misc.: concrete barrier end section (690E98000)EACH1$5,820.00
58Special - misc.: class QC1, concrete barrier repai (690E98700)CY11$1,340.00
59Special - misc.: class QC2, superstructure barrier (690E98700)CY6$1,565.00
60Combination curb and gutter, type 4, as per plan (609E23001)FT30$195.00
61Curb, type 4-C (609E24510)FT20$45.00
62Light pole foundation repair (625E14400)EACH1$3,500.00
63Barrier reflector, type 2, bidirectional (626E00110)EACH75$12.00
64Law enforcement officer with patrol car for assistance (614E11110)HR45$52.00
65Maintenance of traffic, one lane closure on A two lane highway (614E13600)EACH90$200.00
66Maintenance of traffic, one lane closure on A four lane undivided highway (614E13700)EACH10$325.00
67Maintenance of traffic, one lane closure on A 4 lane or greater divided highway (614E13800)EACH30$450.00
68Maintenance of traffic for shoulder closure (614E13900)EACH175$180.00
69Railing (deep beam rail with steel tubular backup and type 1 steel posts), as per plan (517E72205)FT30$132.00
70Railing (deep beam rail with steel tubular backup and type 2 steel posts), as per plan (517E72307)FT30$145.00
71Premium for contract performance bond and for payment bond (103E05000)LS1$10,140
72Mobilization (624E15000)EACH260$380.00
ODOT contract 250388: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of August 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy