ODOT contract 250395 bid tabulation

MRW-SR 61-03.40 (TWO LANE RESURFACING). Let by Ohio DOT on August 28, 2025, MRW. 2 bids received; low bid $2,048,303 by Kokosing Construction Company Inc, -15% against the engineer's estimate of $2,414,000.

Owner
Ohio DOT
Letting
28 AUG 2025
Pay items
48
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Kokosing Construction Company Inc$2,048,303Low-15%
2Shelly & Sands Inc$2,083,603+2.0%-14%
ODOT contract 250395: bids by rank

Engineer's estimate: $2,414,000.

Bid tabulation

LinePay itemUnitQuantity1. Kokosing Construction Company Inc2. Shelly & Sands Inc
1Guardrail removed, as per plan (202E38001)FT1,325$2.50$2.00
2Anchor assembly removed, type A, as per plan (202E42001)EACH10$350.00$345.00
3Removal misc.: concrete steps (202E98100)EACH1$850.00$500.00
4Embankment, as per plan (203E20001)CY482$40.00$68.50
5Linear grading (209E60500)MI19.44$1,250.00$1,500.00
6Guardrail, type MGS (606E15050)FT1,125$20.50$18.60
7Guardrail, type MGS with long posts (606E15100)FT350$21.50$20.80
8Guardrail, type MGS, 25' long-span (606E17350)FT100$24.00$24.00
9Anchor assembly, MGS type E, as per plan (MASH 201 (606E26151)EACH8$2,450.00$2,550.00
10Anchor assembly, MGS type T (606E26550)EACH2$1,250.00$1,385.00
11Monument assembly adjusted to grade (623E39500)EACH13$950.00$1,500.00
12Topsoil (659E00300)CY181$50.00$47.50
13Seeding and mulching (659E10000)SY12,992$1.00$3.20
14Repair seeding and mulching (659E14000)SY77$1.00$3.00
15Inter-seeding (659E15000)SY77$1.00$0.20
16Commercial fertilizer (659E20000)TON1.76$1,250.00$620.00
17Lime (659E31000)ACRE2.70$150.00$50.00
18Water (659E35000)MGAL70$1.00$0.40
19Erosion control (832E30000)EACH1,000$1.00$1.00
20Pipe removed, 24" and under (202E35100)FT557$9.00$9.00
21Catch basin removed (202E58100)EACH1$450.00$450.00
22Class QC1 concrete, headwall (511E46610)CY0.60$4,900.00$4,900.00
2330" conduit, type B (611E13400)FT557$120.00$95.00
24Catch basin, no. 2-4 (611E98540)EACH3$5,000.00$4,750.00
25Partial depth pavement repair (asphalt concrete base), as per plan (251E01041)SY268$80.00$100.00
26Pavement planing, asphalt concrete, as per plan, 1 (254E01001)SY152,580$0.84$1.00
27Non-tracking tack coat (407E20000)GAL12,970$2.90$3.00
28Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000)CY6,285$192.00$176.00
29Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY72$400.00$425.00
30Compacted aggregate (617E10100)CY340$95.00$85.00
31Shoulder preparation (617E20000)SY11,425$0.20$0.75
32Water (617E25000)MGAL5$1.00$10.00
33RPM (621E00100)EACH685$36.50$36.50
34Raised pavement marker removed (621E54000)EACH685$3.00$5.00
35Barrier reflector, type 2, bidirectional (626E00110)EACH45$12.00$12.40
36Removal of ground mounted sign and reerection (630E85100)EACH2$125.00$125.00
37Edge line, 6" (644E00104)MI19.46$3,443.00$3,443.00
38Center line (644E00300)MI9.73$3,390.00$3,390.00
39Stop line (644E00500)FT28$15.00$15.00
40Speed measurement marking (644E40000)EACH7$600.00$1,600.00
41Work zone marking sign, as per plan (614E12461)EACH70$80.00$80.00
42Work zone center line, class III, 642 paint (614E21550)MI9.73$835.00$835.00
43Work zone edge line, class III, 6", 642 paint (614E22360)MI19.46$535.00$535.00
44Work zone stop line, class III, 642 paint (614E26610)FT28$5.00$5.00
45Premium for contract performance bond and for payment bond (103E05000)LS1$8,200.00$10,000
46Maintaining traffic (614E11000)LS1$87,500$137,625
47Construction layout stakes and surveying, as per plan (623E10001)LS1$1,750.00$8,000.00
48Mobilization (624E10000)LS1$102,000$100,000
ODOT contract 250395: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of August 28, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy