ODOT contract 250397 bid tabulation
TRU-SR 193-00.00 (FOUR LANE RESURFACING). Let by Ohio DOT on August 28, 2025, TRU. 4 bids received; low bid $1,053,858 by Shelly & Sands Inc, -3.7% against the engineer's estimate of $1,094,000.
- Owner
- Ohio DOT
- Letting
- 28 AUG 2025
- Pay items
- 41
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $1,053,858 | Low | -4.0% |
| 2 | Karvo Companies Inc | $1,175,516 | +12% | +7.0% |
| 3 | Shelly Company | $1,314,502 | +25% | +20% |
| 4 | Barbicas Construction Company Inc | $1,328,377 | +26% | +21% |
Engineer's estimate: $1,094,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Karvo Companies Inc | 3. Shelly Company | 4. Barbicas Construction Company Inc |
|---|---|---|---|---|---|---|---|
| 1 | Walk removed (202E30000) | SF | 915 | $10.00 | $6.00 | $10.00 | $10.00 |
| 2 | Curb removed (202E32000) | FT | 42 | $25.00 | $60.00 | $20.00 | $17.00 |
| 3 | Curb and gutter removed (202E32500) | FT | 68 | $50.00 | $50.00 | $30.00 | $25.00 |
| 4 | 4" concrete walk (608E10000) | SF | 187 | $12.50 | $15.00 | $22.00 | $20.00 |
| 5 | Curb ramp (608E52000) | SF | 818 | $24.50 | $15.00 | $27.00 | $20.00 |
| 6 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 7 | $1,200.00 | $1,200.00 | $1,200.00 | $1,500.00 |
| 7 | Special - as-built construction plans (690E91000) | LS | 1 | $2,200.00 | $500.00 | $10,000 | $100.00 |
| 8 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 9 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 17 | $1,600.00 | $1,600.00 | $1,600.00 | $1,700.00 |
| 10 | Special - gas valve box adjusted to grade (611E99700) | EACH | 4 | $100.00 | $1,100.00 | $1,100.00 | $200.00 |
| 11 | Partial depth pavement repair (441) (251E01000) | SY | 600 | $82.00 | $50.00 | $105.00 | $27.00 |
| 12 | Non-tracking tack coat (407E20000) | GAL | 6,641 | $3.05 | $2.35 | $2.50 | $3.50 |
| 13 | Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100) | CY | 2,563 | $226.00 | $230.00 | $255.00 | $275.00 |
| 14 | Curb, type 6 (609E26000) | FT | 3 | $100.00 | $50.00 | $70.00 | $50.00 |
| 15 | Pavement planing, asphalt concrete, class A (T=1 1 (897E01010) | SY | 73,784 | $1.00 | $2.00 | $2.80 | $3.00 |
| 16 | RPM (621E00100) | EACH | 533 | $34.60 | $34.60 | $36.95 | $45.50 |
| 17 | Raised pavement marker removed (621E54000) | EACH | 424 | $5.00 | $1.00 | $6.00 | $10.00 |
| 18 | Lane line, 6" (646E10110) | MI | 3.94 | $1,800.00 | $1,800.00 | $1,999.00 | $1,800.00 |
| 19 | Center line (646E10200) | MI | 3 | $3,350.00 | $3,350.00 | $3,695.00 | $3,350.00 |
| 20 | Channelizing line, 12" (646E10310) | FT | 3,360 | $1.75 | $1.75 | $1.79 | $1.75 |
| 21 | Stop line (646E10400) | FT | 544 | $12.00 | $12.00 | $12.00 | $12.00 |
| 22 | Crosswalk line, 24" (646E10520) | FT | 480 | $12.00 | $12.00 | $12.00 | $12.00 |
| 23 | Lane arrow (646E20300) | EACH | 38 | $185.00 | $185.00 | $155.00 | $185.00 |
| 24 | Two way left turn arrow (646E20370) | EACH | 10 | $200.00 | $200.00 | $175.00 | $200.00 |
| 25 | Dotted line, 6" (646E20504) | FT | 215 | $1.25 | $1.25 | $3.00 | $1.25 |
| 26 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 150 | $90.00 | $110.00 | $120.00 | $80.00 |
| 27 | Work zone marking sign (614E12460) | EACH | 4 | $65.00 | $65.00 | $65.00 | $65.00 |
| 28 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $500.00 | $50.00 | $175.00 | $280.00 |
| 29 | Work zone lane line, class I, 6" (614E20010) | MI | 3.94 | $550.00 | $550.00 | $750.00 | $550.00 |
| 30 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 3.94 | $550.00 | $550.00 | $750.00 | $550.00 |
| 31 | Work zone center line, class I (614E21000) | MI | 3 | $1,200.00 | $1,200.00 | $1,500.00 | $1,200.00 |
| 32 | Work zone center line, class III, 642 paint (614E21550) | MI | 3 | $1,200.00 | $1,200.00 | $1,500.00 | $1,200.00 |
| 33 | Work zone channelizing line, class I, 12" (614E23010) | FT | 3,360 | $0.75 | $0.75 | $0.75 | $0.75 |
| 34 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 3,360 | $0.75 | $0.75 | $0.75 | $0.75 |
| 35 | Work zone stop line, class I (614E26000) | FT | 544 | $3.50 | $3.50 | $4.00 | $3.50 |
| 36 | Work zone stop line, class III, 642 paint (614E26610) | FT | 544 | $3.50 | $3.50 | $4.00 | $3.50 |
| 37 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $2,500.00 | $15,000 | $10,000 | $8,500.00 |
| 38 | Maintaining traffic (614E11000) | LS | 1 | $85,890 | $79,900 | $95,000 | $58,000 |
| 39 | Field office, type B (619E16010) | MNTH | 6 | $3,200.00 | $3,200.00 | $3,200.00 | $1,800.00 |
| 40 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,000.00 | $2,500.00 | $7,000.00 | $1,800.00 |
| 41 | Mobilization (624E10000) | LS | 1 | $40,000 | $105,000 | $40,000 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 28, 2025. Compiled by Mirage Metrics.