| 1 | Wearing course removed (202E23500) | SY | 10,084 | $6.90 | $7.00 |
| 2 | Walk removed (202E30000) | SF | 881 | $10.00 | $5.75 |
| 3 | Curb removed (202E32000) | FT | 123 | $14.00 | $43.00 |
| 4 | Preparing subgrade for shoulder paving, as per plan (209E72051) | MI | 20.62 | $1,400.00 | $2,500.00 |
| 5 | 4" concrete walk (608E10000) | SF | 48 | $24.00 | $34.00 |
| 6 | Curb ramp, as per plan (608E52001) | SF | 1,031 | $18.00 | $20.50 |
| 7 | Detectable warning (608E53020) | SF | 16 | $37.50 | $36.00 |
| 8 | Curb, type 6 (609E26000) | FT | 62 | $45.00 | $63.50 |
| 9 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 13 | $1,050.00 | $800.00 |
| 10 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 5 | $1,400.00 | $3,000.00 |
| 11 | Manhole adjusted to grade (611E99654) | EACH | 39 | $1,050.00 | $900.00 |
| 12 | Valve box adjusted to grade (638E10800) | EACH | 12 | $395.00 | $900.00 |
| 13 | Pavement repair (253E02000) | CY | 850 | $306.50 | $300.00 |
| 14 | Pavement planing, asphalt concrete, 1.50" (254E01000) | SY | 151,504 | $1.32 | $1.15 |
| 15 | Pavement planing, asphalt concrete, 3.25" (254E01000) | SY | 76,877 | $3.05 | $2.40 |
| 16 | Non-tracking tack coat (407E20000) | GAL | 28,412 | $4.10 | $2.65 |
| 17 | Prime coat, as per plan (408E10001) | GAL | 9,950 | $4.50 | $4.00 |
| 18 | Asphalt concrete surface course, type 1, (448), as per plan (441E50101) | CY | 9,512 | $206.00 | $235.00 |
| 19 | Asphalt concrete intermediate course, type 2, (448), as per plan (441E50301) | CY | 3,517 | $199.00 | $215.00 |
| 20 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 354 | $335.00 | $450.00 |
| 21 | 2" deep joint sealer, as per plan (516E31011) | FT | 568 | $35.00 | $35.00 |
| 22 | Compacted aggregate, as per plan (617E10101) | CY | 1,400 | $69.50 | $30.00 |
| 23 | Rumble stripes, center line (asphalt concrete) (618E43000) | MI | 7.38 | $1,353.00 | $935.00 |
| 24 | Longitudinal joint preparation (874E21000) | MI | 8.29 | $3,250.00 | $1,500.00 |
| 25 | Delineator, misc.: raised curb channelizing system (620E70010) | FT | 275 | $99.00 | $99.00 |
| 26 | Delineator, misc.: raised curb channelizing system (620E70010) | FT | 175 | $6.45 | $6.45 |
| 27 | RPM (621E00100) | EACH | 1,018 | $36.00 | $36.00 |
| 28 | Raised pavement marker removed (621E54000) | EACH | 1,018 | $5.00 | $2.00 |
| 30 | Edge line, 6" (644E00104) | MI | 21.92 | $3,455.00 | $3,455.00 |
| 31 | Center line (644E00300) | MI | 13.04 | $3,455.00 | $3,455.00 |
| 32 | Channelizing line, 8" (644E00400) | FT | 3,312 | $2.70 | $2.70 |
| 33 | Stop line (644E00500) | FT | 858 | $8.85 | $8.85 |
| 34 | Crosswalk line, 12" (644E00620) | FT | 1,365 | $4.25 | $4.25 |
| 35 | Transverse/diagonal line (644E00700) | FT | 1,159 | $8.45 | $8.45 |
| 36 | Railroad symbol marking (644E01000) | EACH | 1 | $880.00 | $880.00 |
| 37 | School symbol marking, 96" (644E01110) | EACH | 2 | $880.00 | $880.00 |
| 38 | Lane arrow (644E01300) | EACH | 40 | $95.00 | $95.00 |
| 39 | Two way left turn arrow (644E01370) | EACH | 9 | $190.00 | $190.00 |
| 40 | Word on pavement, 96" (644E01410) | EACH | 24 | $160.00 | $160.00 |
| 41 | Yield line (644E20800) | FT | 58 | $12.50 | $12.50 |
| 42 | Edge line, 6" (646E10010) | MI | 0.38 | $16,050 | $16,050 |
| 43 | Center line (646E10200) | MI | 0.20 | $25,980 | $25,980 |
| 44 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 600 | $75.00 | $90.00 |
| 45 | Work zone marking sign (614E12460) | EACH | 81 | $87.50 | $87.50 |
| 46 | Asphalt concrete for maintaining traffic (614E13000) | CY | 8 | $225.00 | $150.00 |
| 47 | Portable changeable message sign, as per plan (614E18601) | SNMT | 16 | $625.00 | $625.00 |
| 48 | Work zone center line, class I, 642 paint (614E21100) | MI | 4.39 | $1,600.00 | $2,225.00 |
| 49 | Work zone center line, class III, 642 paint (614E21550) | MI | 13.04 | $857.00 | $1,450.00 |
| 50 | Work zone channelizing line, class I, 8", 642 paint (614E23200) | FT | 2,750 | $0.72 | $0.85 |
| 51 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 3,295 | $0.62 | $1.25 |
| 52 | Work zone stop line, class I, 642 paint (614E26200) | FT | 189 | $8.00 | $8.00 |
| 53 | Work zone stop line, class III, 642 paint (614E26610) | FT | 189 | $7.00 | $7.00 |
| 54 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $3,000.00 | $3,000.00 |
| 55 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,000.00 | $20,000 |
| 56 | Maintaining traffic (614E11000) | LS | 1 | $350,000 | $316,356 |
| 57 | Field office, type C (619E16020) | MNTH | 12 | $2,500.00 | $2,500.00 |
| 58 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,000.00 | $4,000.00 |
| 59 | Mobilization (624E10000) | LS | 1 | $90,000 | $255,000 |