ODOT contract 250419 bid tabulation
WAS-Marietta SRTS FY2026 (SIDEWALK). Let by Ohio DOT on September 11, 2025, WAS. 3 bids received; low bid $464,954 by LMS Construction Inc, -7.2% against the engineer's estimate of $501,000.
- Owner
- Ohio DOT
- Letting
- 11 SEP 2025
- Pay items
- 60
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | LMS Construction Inc | $464,954 | Low | -7.0% |
| 2 | Shelly & Sands Inc | $488,839 | +5.0% | -2.0% |
| 3 | Alan Stone Co Inc | $694,322 | +49% | +39% |
Engineer's estimate: $501,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. LMS Construction Inc | 2. Shelly & Sands Inc | 3. Alan Stone Co Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,000.00 | $800.00 | $9,900.00 |
| 2 | Pavement removed (202E23000) | SY | 43 | $60.00 | $21.00 | $50.00 |
| 3 | Walk removed (202E30000) | SF | 2,415 | $5.00 | $3.00 | $2.00 |
| 4 | Curb removed (202E32000) | FT | 181 | $15.00 | $25.00 | $25.00 |
| 5 | Curb and gutter removed (202E32500) | FT | 157 | $40.00 | $28.00 | $25.00 |
| 6 | Removal misc.:gate post removed (202E98100) | EACH | 2 | $200.00 | $150.00 | $490.00 |
| 7 | Removal misc.:brick pavers removed, salvaged, and (202E98400) | SF | 2,538 | $13.00 | $14.00 | $10.00 |
| 8 | Excavation (203E10000) | CY | 35 | $300.00 | $120.00 | $70.00 |
| 9 | Embankment (203E20000) | CY | 26 | $300.00 | $119.01 | $50.00 |
| 10 | Subgrade compaction (204E10000) | SY | 859 | $6.00 | $3.00 | $9.00 |
| 11 | Geotextile fabric (204E50000) | SY | 243 | $8.00 | $4.00 | $3.00 |
| 12 | Fence, misc.:range plastic construction fence (607E98000) | FT | 440 | $11.00 | $13.00 | $15.00 |
| 13 | 4" concrete walk (608E10000) | SF | 2,847 | $11.00 | $11.00 | $15.00 |
| 14 | Curb ramp (608E52000) | SF | 644 | $28.00 | $34.00 | $65.00 |
| 15 | Detectable warning (608E53020) | SF | 95 | $37.00 | $42.00 | $2.50 |
| 16 | Walkway, misc.:brick paver walk (608E98000) | SF | 2,184 | $35.00 | $28.50 | $25.00 |
| 17 | Special - bicycle rack (690E50560) | EACH | 3 | $2,600.00 | $725.00 | $2,900.00 |
| 18 | Soil analysis test (659E00100) | EACH | 2 | $100.00 | $162.03 | $150.00 |
| 19 | Topsoil (659E00300) | CY | 143 | $25.00 | $88.00 | $95.00 |
| 20 | Seeding and mulching (659E10000) | SY | 1,286 | $2.00 | $2.50 | $2.50 |
| 21 | Repair seeding and mulching (659E14000) | SY | 65 | $2.00 | $2.50 | $10.00 |
| 22 | Inter-seeding (659E15000) | SY | 65 | $2.00 | $2.50 | $5.00 |
| 23 | Commercial fertilizer (659E20000) | TON | 0.17 | $1,000.00 | $1,350.24 | $680.00 |
| 24 | Lime (659E31000) | ACRE | 0.27 | $1,000.00 | $162.04 | $980.00 |
| 25 | Water (659E35000) | MGAL | 7 | $5.00 | $1.10 | $120.00 |
| 26 | Mowing (659E40000) | MSF | 3 | $100.00 | $540.00 | $2,200.00 |
| 27 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 |
| 28 | 4" base pipe underdrains (605E06000) | FT | 277 | $15.00 | $18.00 | $20.00 |
| 29 | Pavement repair (253E01000) | SY | 93 | $150.00 | $240.00 | $220.00 |
| 30 | Aggregate base (304E20000) | CY | 45 | $280.00 | $230.00 | $130.00 |
| 31 | 6" non-reinforced concrete pavement, class QC 1P with QC/QA (452E10020) | SY | 49 | $198.00 | $325.00 | $150.00 |
| 32 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 23 | $86.00 | $85.00 | $90.00 |
| 33 | Combination curb and gutter, type 4, as per plan (609E23001) | FT | 58 | $115.00 | $104.00 | $85.00 |
| 34 | Curb, type 4-C (609E24510) | FT | 49 | $86.00 | $85.00 | $100.00 |
| 35 | Curb, type 6 (609E26000) | FT | 29 | $86.00 | $85.00 | $90.00 |
| 36 | Curb, type 6, as per plan (609E26001) | FT | 874 | $37.00 | $49.00 | $65.00 |
| 37 | Valve box adjusted to grade (638E10800) | EACH | 5 | $400.00 | $415.00 | $150.00 |
| 38 | Ground mounted support, no. 2 post (630E02100) | FT | 60 | $20.00 | $27.00 | $30.00 |
| 39 | Sign post reflector (630E08600) | EACH | 4 | $25.00 | $54.00 | $60.00 |
| 40 | Sign, flat sheet (630E80100) | SF | 26 | $50.00 | $32.00 | $35.00 |
| 41 | Removal of ground mounted sign and disposal (630E84900) | EACH | 4 | $30.00 | $22.00 | $25.00 |
| 42 | Removal of ground mounted sign and reerection (630E85100) | EACH | 4 | $75.00 | $125.00 | $150.00 |
| 43 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $30.00 | $22.00 | $25.00 |
| 44 | Signing, misc.:solar powered rectangular rapid fla (630E97700) | EACH | 2 | $6,000.00 | $12,500 | $18,000 |
| 45 | Crosswalk line, 24" (644E00630) | FT | 220 | $6.00 | $19.00 | $20.00 |
| 46 | Transverse/diagonal line (644E00700) | FT | 70 | $18.00 | $11.50 | $15.00 |
| 47 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $90.00 | $87.00 | $130.00 |
| 48 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $500.00 | $6,175.00 | $500.00 |
| 49 | 1" preformed expansion joint filler (516E13600) | SF | 16 | $15.00 | $8.75 | $1.50 |
| 50 | Prefabricated modular retaining wall (870E10000) | SF | 360 | $135.00 | $75.00 | $250.00 |
| 51 | Wall excavation (870E11000) | CY | 290 | $10.00 | $155.00 | $55.00 |
| 52 | Natural soil (870E11100) | CY | 45 | $25.00 | $71.00 | $60.00 |
| 53 | 6" drainage pipe, perforated (870E12000) | FT | 60 | $12.00 | $6.75 | $4.50 |
| 54 | 6" drainage pipe, non-perforated (870E12100) | FT | 20 | $12.00 | $6.25 | $8.00 |
| 55 | On-site assistance (870E14000) | DAY | 1 | $1,500.00 | $3,250.00 | $1,800.00 |
| 56 | PMRW inspection and compaction testing (870E15000) | LS | 1 | $1,500.00 | $2,700.00 | $3,200.00 |
| 57 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $20,000 | $2,800.00 | $10,000 |
| 58 | Maintaining traffic (614E11000) | LS | 1 | $12,000 | $4,000.00 | $75,000 |
| 59 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,000.00 | $4,000.00 | $6,100.00 |
| 60 | Mobilization (624E10000) | LS | 1 | $23,500 | $25,000 | $77,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 11, 2025. Compiled by Mirage Metrics.