ODOT contract 250534 bid tabulation
SAN-/SEN-SR 18-00.00/30.47 (TWO LANE RESURFACING). Let by Ohio DOT on November 13, 2025, SAN. 4 bids received; low bid $2,219,320 by Kokosing Construction Company Inc, -11% against the engineer's estimate of $2,507,000.
- Owner
- Ohio DOT
- Letting
- 13 NOV 2025
- Pay items
- 44
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kokosing Construction Company Inc | $2,219,320 | Low | -11% |
| 2 | M & B Asphalt Co Inc | $2,235,110 | +1.0% | -11% |
| 3 | Erie Blacktop Inc | $2,393,819 | +8.0% | -5.0% |
| 4 | Gerken Paving Inc | $2,433,541 | +10% | -3.0% |
Engineer's estimate: $2,507,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kokosing Construction Company Inc | 2. M & B Asphalt Co Inc | 3. Erie Blacktop Inc | 4. Gerken Paving Inc |
|---|---|---|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 255 | $20.00 | $18.00 | $80.00 | $37.50 |
| 2 | Linear grading (209E60500) | MI | 11 | $1,950.00 | $1,400.00 | $1,800.00 | $1,800.00 |
| 3 | Preparing subgrade for shoulder paving (209E72050) | MI | 10.60 | $540.00 | $1,400.00 | $3,500.00 | $500.00 |
| 4 | Longitudinal joint adhesive (875E10000) | LB | 2,759 | $0.70 | $0.50 | $2.25 | $0.65 |
| 5 | Erosion control (832E30000) | EACH | 800 | $1.00 | $1.00 | $1.00 | $1.00 |
| 6 | Catch basin adjusted to grade (611E98630) | EACH | 14 | $1,025.00 | $875.00 | $1,050.00 | $1,050.00 |
| 7 | Manhole adjusted to grade (611E99654) | EACH | 15 | $1,000.00 | $775.00 | $780.00 | $750.00 |
| 8 | Pavement repair (253E02000) | CY | 1,170 | $205.00 | $210.00 | $230.00 | $240.00 |
| 9 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 400 | $5.00 | $7.00 | $12.00 | $8.00 |
| 10 | Pavement planing, asphalt concrete, 1.75" (254E01000) | SY | 67,764 | $1.25 | $1.30 | $1.00 | $1.55 |
| 11 | Pavement planing, asphalt concrete, 3.25" (254E01000) | SY | 33,271 | $2.64 | $3.90 | $1.50 | $2.30 |
| 12 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 53 | $225.00 | $200.00 | $500.00 | $365.00 |
| 13 | Tack coat (407E10000) | GAL | 10,469 | $1.90 | $2.55 | $2.55 | $2.25 |
| 14 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 105 | $210.00 | $220.00 | $246.00 | $250.00 |
| 15 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00200) | CY | 1,387 | $220.00 | $220.00 | $246.00 | $215.00 |
| 16 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00200) | CY | 3,324 | $205.00 | $200.00 | $230.00 | $200.00 |
| 17 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00200) | CY | 28 | $160.00 | $200.00 | $230.00 | $215.00 |
| 18 | Asphalt concrete intermediate course, 12.5 MM, type A (448) (442E20170) | CY | 1,617 | $194.00 | $198.00 | $190.00 | $190.00 |
| 19 | Compacted aggregate (617E10100) | CY | 724 | $30.00 | $69.00 | $65.00 | $85.00 |
| 20 | Rumble stripes, center line (asphalt concrete) (618E40900) | FT | 22,351 | $0.31 | $0.31 | $0.33 | $0.31 |
| 21 | Longitudinal joint preparation (874E20000) | FT | 22,351 | $0.95 | $1.00 | $1.45 | $1.25 |
| 22 | Valve box adjusted to grade (638E10800) | EACH | 3 | $600.00 | $450.00 | $710.00 | $525.00 |
| 23 | RPM (621E00100) | EACH | 345 | $42.00 | $42.00 | $44.00 | $42.00 |
| 24 | Raised pavement marker removed (621E54000) | EACH | 342 | $3.00 | $6.00 | $4.20 | $2.00 |
| 25 | Edge line, 6", type 1 (642E00104) | MI | 10.70 | $850.00 | $900.00 | $895.00 | $900.00 |
| 26 | Center line, type 1 (642E00300) | MI | 6.20 | $850.00 | $1,000.00 | $895.00 | $1,000.00 |
| 27 | Channelizing line, 12", type 1 (642E00404) | FT | 29 | $2.00 | $4.00 | $2.10 | $4.00 |
| 28 | Stop line (644E00500) | FT | 49 | $8.00 | $9.00 | $8.40 | $9.00 |
| 29 | Crosswalk line, 24" (644E00630) | FT | 156 | $8.00 | $9.00 | $8.40 | $9.00 |
| 30 | Railroad symbol marking (644E01000) | EACH | 4 | $500.00 | $800.00 | $525.00 | $800.00 |
| 31 | Lane arrow (644E01300) | EACH | 1 | $150.00 | $250.00 | $158.00 | $250.00 |
| 32 | Speed measurement marking (644E40000) | EACH | 6 | $327.29 | $300.00 | $590.00 | $555.00 |
| 33 | Work zone marking sign (614E12460) | EACH | 12 | $75.00 | $130.00 | $78.75 | $120.00 |
| 34 | Replacement sign (614E12500) | EACH | 5 | $150.00 | $90.00 | $158.00 | $120.00 |
| 35 | Replacement drum (614E12600) | EACH | 5 | $45.00 | $50.00 | $47.00 | $50.00 |
| 36 | Work zone center line, class I (614E21000) | MI | 12.20 | $950.00 | $1,000.00 | $1,000.00 | $1,500.00 |
| 37 | Work zone center line, class III, 642 paint (614E21550) | MI | 6.10 | $950.00 | $900.00 | $1,000.00 | $1,100.00 |
| 38 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,880.00 | $12,000 | $10,500 | $12,000 |
| 39 | Maintaining traffic (614E11000) | LS | 1 | $95,200 | $25,000 | $70,000 | $174,000 |
| 40 | Field office, type B, as per plan (619E16011) | MNTH | 12 | $1,100.00 | $1,650.00 | $2,850.00 | $2,800.00 |
| 41 | Construction layout stakes and surveying (623E10000) | LS | 1 | $1,600.00 | $4,000.00 | $4,500.00 | $6,610.00 |
| 42 | Mobilization (624E10000) | LS | 1 | $110,000 | $100,000 | $80,000 | $121,780 |
| 100 | Railroad flagging services (900E00100) | EACH | 40,855 | $1.00 | $1.00 | $1.00 | $1.00 |
| 101 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $5,600.00 | $10,000 | $4,500.00 | $5,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 13, 2025. Compiled by Mirage Metrics.