ODOT contract 250554 bid tabulation

DEF-SR 18-28.93 (TWO LANE RESURFACING). Let by Ohio DOT on December 4, 2025, DEF. 2 bids received; low bid $1,797,217 by Gerken Paving Inc, +1.2% against the engineer's estimate of $1,776,000.

Owner
Ohio DOT
Letting
04 DEC 2025
Pay items
18
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Gerken Paving Inc$1,797,217Low+1.0%
2Ebony Construction Co$2,175,006+21%+22%
ODOT contract 250554: bids by rank

Engineer's estimate: $1,776,000.

Bid tabulation

LinePay itemUnitQuantity1. Gerken Paving Inc2. Ebony Construction Co
1Excavation (203E10000)CY10,170$24.50$32.00
2Preparing subgrade for shoulder paving, as per plan (209E72051)MI8.74$60.00$5,200.00
3Seeding and mulching (659E10000)SY400$4.50$5.80
4Commercial fertilizer (659E20000)TON0.40$850.00$580.00
5Water (659E35000)MGAL4$1.00$58.00
6Erosion control (832E30000)EACH1,000$1.00$1.00
7Asphalt concrete base, (449), as per PLANPG64-22 (302E56001)CY2,438$195.00$208.00
8Aggregate base (304E20000)CY5,606$60.25$88.00
9Tack coat (407E10000)GAL2,603$2.50$3.00
10Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000)CY714$275.00$330.60
11Asphalt concrete intermediate course, type 2, (448) (441E50300)CY735$260.00$330.60
12Compacted aggregate, as per plan (617E10101)CY1,064$105.00$100.00
13Longitudinal joint adhesive (875E10000)LB11,285$1.25$0.20
14Edge line, 6", type 1 (642E00104)MI8.61$788.00$1,044.00
15Stop line (644E00500)FT24$6.00$17.00
16Premium for contract performance bond and for payment bond (103E05000)LS1$8,500.00$20,000
17Maintaining traffic (614E11000)LS1$100,000$55,000
18Mobilization (624E10000)LS1$96,000$120,000
ODOT contract 250554: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of December 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy