ODOT contract 260186 bid tabulation

WOO-Roche De Boeuf Interurban (DEMOLITION). Let by Ohio DOT on April 9, 2026, WOO. 3 bids received; low bid $3,062,302 by Kokosing Construction Company Inc, -13% against the engineer's estimate of $3,525,000.

Owner
Ohio DOT
Letting
09 APR 2026
Pay items
26
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Kokosing Construction Company Inc$3,062,302Low-13%
2Geddis Paving & Excavating Inc$3,197,051+4.0%-9.0%
3L M Sessler Excavating & Wrecking Inc$5,667,788+85%+61%
ODOT contract 260186: bids by rank

Engineer's estimate: $3,525,000.

Bid tabulation

LinePay itemUnitQuantity1. Kokosing Construction Company Inc2. Geddis Paving & Excavating Inc3. L M Sessler Excavating & Wrecking Inc
1Clearing and grubbing (201E11000)LS1$7,800.00$6,000.00$25,000
2Excavation (203E10000)CY418$8.00$25.00$55.00
3Embankment (203E20000)CY1,200$54.00$25.00$40.00
4Fence, misc.: temporary construction fence (607E98000)FT2,500$3.75$8.00$15.00
5Soil analysis test (659E00100)EACH2$60.00$60.00$100.00
6Topsoil (659E00300)CY306$70.00$90.00$75.00
7Seeding and mulching (659E10000)SY1,127$3.00$3.00$4.00
8Repair seeding and mulching (659E14000)SY2,229$3.00$3.00$4.00
9Commercial fertilizer (659E20000)TON0.15$850.00$800.00$1,200.00
10Lime (659E31000)ACRE0.23$35.00$100.00$500.00
11Water (659E35000)MGAL7$1.00$1.00$1.00
12Slope erosion protection (670E00500)SY1,127$1.80$2.00$2.50
13Storm water pollution prevention plan (832E15000)LS1$1,025.00$2,800.00$3,500.00
14Storm water pollution prevention inspections (832E15002)LS1$7,000.00$15,000$10,000
15Storm water pollution prevention inspection software (832E15010)LS1$9,000.00$18,500$10,000
16Erosion control (832E30000)EACH75,000$1.00$1.00$1.00
17Planting, misc.: 1" caliper, 3-gallon container TR (661E99900)EACH168$175.00$300.00$350.00
18Planting, misc.: 1-gallon container shrub (661E99900)EACH500$62.00$64.00$85.00
19Landscape watering (662E31000)GAL7,869$1.00$1.00$1.50
20Portions of structure removed, over 20 foot span, as per plan (202E11203)LS1$2,591,407$1,350,000$4,950,000
21Cofferdams and excavation bracing (503E11100)LS1$1.00$1,300,000$1.00
22Premium for contract performance bond and for payment bond (103E05000)LS1$12,000$37,000$35,000
23CPM progress schedule (108E10000)LS1$100.00$3,500.00$8,000.00
24Maintaining traffic (614E11000)LS1$25,000$30,000$120,000
25Construction layout stakes and surveying (623E10000)LS1$1.00$16,400$20,000
26Mobilization (624E10000)LS1$154,400$152,000$150,000
ODOT contract 260186: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy