ODOT contract 260395 bid tabulation
GUE-ODNR Salt Fork SP FY2027 (PARKING AREAS). Let by Ohio DOT on August 27, 2026, GUE. 3 bids received; low bid $1,355,988 by NLS Paving, Inc, +26% against the engineer's estimate of $1,077,000.
- Owner
- Ohio DOT
- Letting
- 27 AUG 2026
- Pay items
- 32
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | NLS Paving, Inc | $1,355,988 | Low | +26% |
| 2 | Shelly & Sands Inc | $1,404,241 | +4.0% | +30% |
| 3 | Alan Stone Co Inc | $1,475,100 | +9.0% | +37% |
Engineer's estimate: $1,077,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. NLS Paving, Inc | 2. Shelly & Sands Inc | 3. Alan Stone Co Inc |
|---|---|---|---|---|---|---|
| 1 | Wearing course removed (202E23500) | SY | 614 | $15.00 | $12.50 | $15.00 |
| 2 | Special - parking block removed and reset (202E53010) | EACH | 298 | $90.00 | $115.00 | $90.00 |
| 3 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 10 | $2,000.00 | $2,250.00 | $540.00 |
| 4 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 1 | $2,500.00 | $3,750.00 | $2,000.00 |
| 5 | Manhole adjusted to grade (611E99654) | EACH | 3 | $1,150.00 | $1,550.00 | $1,400.00 |
| 6 | Pavement repair (253E02000) | CY | 25 | $600.00 | $425.00 | $790.00 |
| 7 | Pavement repair (253E02000) | CY | 75 | $550.00 | $450.00 | $570.00 |
| 8 | Pavement planing, asphalt concrete, 1.50" (254E01000) | SY | 62,036 | $2.45 | $3.55 | $2.65 |
| 9 | Non-tracking tack coat (407E20000) | GAL | 5,322 | $3.25 | $3.50 | $4.50 |
| 10 | Prime coat, as per plan (408E10001) | GAL | 266 | $5.00 | $5.00 | $20.00 |
| 11 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 2,772 | $265.00 | $255.50 | $290.00 |
| 12 | Compacted aggregate, as per plan (617E10101) | CY | 37 | $150.00 | $125.00 | $220.00 |
| 13 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 26 | $25.00 | $25.00 | $25.00 |
| 14 | Sign, flat sheet (630E80100) | SF | 12.50 | $45.00 | $45.00 | $50.00 |
| 15 | Center line (644E00300) | MI | 0.38 | $10,000 | $10,000 | $11,000 |
| 16 | Stop line (644E00500) | FT | 136 | $9.00 | $9.00 | $10.00 |
| 17 | Parking lot stall marking (644E01200) | FT | 22,071 | $1.85 | $1.85 | $2.00 |
| 18 | Lane arrow (644E01300) | EACH | 13 | $100.00 | $100.00 | $110.00 |
| 19 | Handicap symbol marking, type B125 (647E20212) | EACH | 30 | $190.00 | $190.00 | $210.00 |
| 20 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.38 | $2,850.00 | $2,850.00 | $3,100.00 |
| 21 | Wearing course removed (202E23500) | SY | 81 | $15.00 | $9.50 | $25.00 |
| 22 | Special - parking block removed and reset (202E53010) | EACH | 6 | $90.00 | $465.00 | $300.00 |
| 23 | Pavement repair (253E02000) | CY | 75 | $550.00 | $425.00 | $450.00 |
| 24 | Non-tracking tack coat (407E20000) | GAL | 813 | $3.25 | $3.50 | $4.00 |
| 25 | Prime coat, as per plan (408E10001) | GAL | 89 | $5.00 | $5.00 | $4.00 |
| 26 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 424 | $265.00 | $230.00 | $280.00 |
| 27 | Compacted aggregate, as per plan (617E10101) | CY | 13 | $150.00 | $200.00 | $200.00 |
| 28 | Parking lot stall marking (644E01200) | FT | 1,059 | $1.85 | $1.85 | $2.00 |
| 30 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $6,000.99 | $5,510.00 | $10,000 |
| 31 | Maintaining traffic (614E11000) | LS | 1 | $40,000 | $80,000 | $43,000 |
| 32 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,500.00 | $12,500 | $9,800.00 |
| 33 | Mobilization (624E10000) | LS | 1 | $60,000 | $40,000 | $72,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 27, 2026. Compiled by Mirage Metrics.