ODOT contract 260423 bid tabulation
D07-BP FY27 (BRIDGE REPAIR). Let by Ohio DOT on October 1, 2026, District 7. 6 bids received; low bid $1,747,185 by Apbn Inc, +1.3% against the engineer's estimate of $1,725,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 39
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Apbn Inc | $1,747,185 | Low | +1.0% |
| 2 | 360 Construction Company Inc | $1,926,064 | +10% | +12% |
| 3 | Advanced Painting & Contracting LLC | $1,949,805 | +12% | +13% |
| 4 | Corrosion Resistance LTD | $2,059,760 | +18% | +19% |
| 5 | Vimas Painting Company Inc | $2,095,444 | +20% | +21% |
| 6 | Elite Contractors Inc | $2,119,432 | +21% | +23% |
Engineer's estimate: $1,725,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Apbn Inc | 2. 360 Construction Company Inc | 3. Advanced Painting & Contracting LLC | 4. Corrosion Resistance LTD | 5. Vimas Painting Company Inc | 6. Elite Contractors Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Seeding and mulching (659E10000) | SY | 3,085 | $2.75 | $3.60 | $2.60 | $6.00 | $3.00 | $2.75 |
| 2 | Repair seeding and mulching (659E14000) | SY | 155 | $1.00 | $1.25 | $2.60 | $1.50 | $2.00 | $1.25 |
| 3 | Commercial fertilizer (659E20000) | TON | 0.42 | $1,500.00 | $990.00 | $1,400.00 | $1,000.00 | $1,000.00 | $990.00 |
| 4 | Water (659E35000) | MGAL | 16.70 | $1.00 | $1.00 | $0.20 | $3.00 | $10.00 | $1.00 |
| 5 | Erosion control (832E30000) | EACH | 5,550 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 6 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 700 | $80.00 | $100.00 | $85.00 | $115.00 | $110.00 | $50.00 |
| 7 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 9 | $2,015.24 | $2,015.24 | $2,015.24 | $2,015.24 | $2,200.00 | $2,015.24 |
| 8 | Detour signing (614E12420) | LS | 1 | $15,215 | $15,215 | $15,215 | $15,215 | $20,000 | $15,215 |
| 9 | Barrier reflector, type 1 (one way) (614E13310) | EACH | 63 | $10.54 | $10.54 | $10.54 | $10.54 | $12.00 | $10.54 |
| 10 | Object marker, one way (614E13350) | EACH | 63 | $21.81 | $21.81 | $21.81 | $21.81 | $22.00 | $21.81 |
| 11 | Portable barrier, unanchored (622E41100) | FT | 2,980 | $33.89 | $33.89 | $33.89 | $33.89 | $36.00 | $33.89 |
| 12 | Surface preparation of existing structural steel (514E00050) | SF | 10,010 | $14.00 | $20.00 | $14.25 | $15.00 | $25.00 | $20.00 |
| 13 | Field painting of existing structural steel, prime coat (514E00056) | SF | 10,010 | $5.00 | $8.00 | $7.00 | $7.90 | $10.00 | $5.00 |
| 14 | Field painting structural steel, intermediate coat (514E00060) | SF | 10,010 | $5.00 | $4.00 | $7.00 | $6.90 | $5.00 | $5.00 |
| 15 | Field painting structural steel, finish coat (514E00066) | SF | 10,010 | $5.00 | $2.00 | $7.00 | $7.10 | $5.00 | $5.00 |
| 16 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 17 | $100.00 | $150.00 | $250.00 | $85.00 | $200.00 | $100.00 |
| 17 | Final inspection repair (514E10000) | EACH | 5 | $100.00 | $200.00 | $450.00 | $300.00 | $300.00 | $200.00 |
| 18 | Surface preparation of existing structural steel (514E00050) | SF | 15,230 | $12.00 | $18.00 | $14.50 | $10.60 | $15.00 | $18.00 |
| 19 | Field painting of existing structural steel, prime coat (514E00056) | SF | 15,230 | $5.00 | $8.00 | $5.50 | $5.25 | $4.00 | $5.00 |
| 20 | Field painting structural steel, intermediate coat (514E00060) | SF | 15,230 | $5.00 | $4.00 | $5.50 | $6.90 | $5.00 | $5.00 |
| 21 | Field painting structural steel, finish coat (514E00066) | SF | 15,230 | $5.00 | $2.00 | $5.50 | $5.80 | $5.00 | $5.00 |
| 22 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 27 | $100.00 | $150.00 | $250.00 | $65.00 | $200.00 | $100.00 |
| 23 | Final inspection repair (514E10000) | EACH | 8 | $100.00 | $200.00 | $450.00 | $225.00 | $300.00 | $200.00 |
| 24 | Surface preparation of existing structural steel (514E00050) | SF | 9,350 | $12.00 | $20.00 | $13.50 | $17.35 | $15.00 | $30.00 |
| 25 | Field painting of existing structural steel, prime coat (514E00056) | SF | 9,350 | $5.00 | $8.00 | $5.00 | $5.90 | $3.00 | $5.00 |
| 26 | Field painting structural steel, intermediate coat (514E00060) | SF | 9,350 | $5.00 | $4.00 | $5.00 | $5.25 | $4.00 | $5.00 |
| 27 | Field painting structural steel, finish coat (514E00066) | SF | 9,350 | $5.00 | $2.00 | $5.00 | $5.90 | $4.00 | $5.00 |
| 28 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 16 | $100.00 | $150.00 | $250.00 | $90.00 | $200.00 | $100.00 |
| 29 | Final inspection repair (514E10000) | EACH | 5 | $100.00 | $200.00 | $450.00 | $300.00 | $300.00 | $200.00 |
| 30 | Surface preparation of existing structural steel (514E00050) | SF | 12,300 | $10.00 | $16.00 | $14.00 | $14.15 | $15.00 | $18.00 |
| 31 | Field painting of existing structural steel, prime coat (514E00056) | SF | 12,300 | $5.00 | $8.00 | $7.00 | $6.10 | $4.00 | $5.00 |
| 32 | Field painting structural steel, intermediate coat (514E00060) | SF | 12,300 | $5.00 | $4.00 | $5.50 | $7.00 | $4.00 | $5.00 |
| 33 | Field painting structural steel, finish coat (514E00066) | SF | 12,300 | $5.00 | $2.00 | $5.50 | $7.25 | $4.00 | $5.00 |
| 34 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 20 | $100.00 | $150.00 | $250.00 | $85.00 | $200.00 | $100.00 |
| 35 | Final inspection repair (514E10000) | EACH | 6 | $100.00 | $200.00 | $450.00 | $300.00 | $300.00 | $200.00 |
| 36 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $20,000 | $30,000 | $38,500 | $20,000 | $20,000 | $40,000 |
| 37 | Maintaining traffic (614E11000) | LS | 1 | $145,118 | $100,000 | $80,000 | $125,000 | $240,000 | $100,000 |
| 38 | Construction layout stakes and surveying (623E10000) | LS | 1 | $1,000.00 | $1,000.00 | $5,000.00 | $10,000 | $3,000.00 | $1,000.00 |
| 39 | Mobilization (624E10000) | LS | 1 | $102,000 | $40,000 | $100,000 | $100,000 | $100,000 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.