ODOT contract 260437 bid tabulation
SEN-SR 18-02.76/31.37 Bridge Paint (BRIDGE PAINTING). Let by Ohio DOT on October 1, 2026, SEN. 5 bids received; low bid $492,907 by Advanced Painting & Contracting LLC, -10% against the engineer's estimate of $550,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 32
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Advanced Painting & Contracting LLC | $492,907 | Low | -10% |
| 2 | Apbn Inc | $515,265 | +5.0% | -6.0% |
| 3 | Vimas Painting Company Inc | $543,255 | +10% | -1.0% |
| 4 | 360 Construction Company Inc | $700,429 | +42% | +27% |
| 5 | Elite Contractors Inc | $891,665 | +81% | +62% |
Engineer's estimate: $550,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Advanced Painting & Contracting LLC | 2. Apbn Inc | 3. Vimas Painting Company Inc | 4. 360 Construction Company Inc | 5. Elite Contractors Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 2 | Pavement planing, asphalt concrete, 1.75" (254E01000) | SY | 500 | $17.00 | $8.00 | $25.00 | $80.00 | $20.00 |
| 3 | Tack coat (407E10000) | GAL | 50 | $2.50 | $1.00 | $4.00 | $7.00 | $5.00 |
| 4 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 25 | $715.00 | $100.00 | $1,100.00 | $2,000.00 | $2,600.00 |
| 5 | Compacted aggregate (617E10100) | CY | 10 | $400.00 | $100.00 | $500.00 | $500.00 | $200.00 |
| 6 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 2 | $2,235.38 | $2,235.38 | $2,300.00 | $2,235.38 | $2,235.38 |
| 7 | Replacement sign (614E12500) | EACH | 2 | $239.36 | $239.36 | $250.00 | $239.36 | $239.36 |
| 8 | Replacement drum (614E12600) | EACH | 5 | $55.00 | $55.00 | $55.00 | $55.00 | $55.00 |
| 9 | Barrier reflector, type 1, bidirectional (614E13310) | EACH | 7 | $10.54 | $10.54 | $11.00 | $10.54 | $10.54 |
| 10 | Object marker, two way (614E13360) | EACH | 7 | $19.81 | $19.81 | $20.00 | $19.81 | $19.81 |
| 11 | Portable changeable message sign, as per plan (614E18601) | SNMT | 4 | $1,153.79 | $1,153.79 | $1,200.00 | $1,153.79 | $1,153.79 |
| 12 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.20 | $15,478 | $15,478 | $15,500 | $15,478 | $15,478 |
| 13 | Work zone edge line, class I, 4", 740.06, type I (614E22200) | MI | 0.10 | $10,245 | $10,245 | $10,300 | $10,245 | $10,245 |
| 14 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 24 | $6.89 | $6.89 | $7.00 | $6.89 | $6.89 |
| 15 | Portable barrier, unanchored (622E41100) | FT | 300 | $66.68 | $66.68 | $67.00 | $66.68 | $66.68 |
| 16 | Reinforcing steel, replacement of existing reinforcing steel (509E20000) | LB | 200 | $6.56 | $15.00 | $10.00 | $6.56 | $6.56 |
| 17 | Surface preparation of existing structural steel (514E00050) | SF | 2,385 | $18.50 | $25.00 | $25.00 | $40.00 | $65.00 |
| 18 | Field painting of existing structural steel, prime coat (514E00056) | SF | 2,385 | $8.00 | $10.00 | $10.00 | $25.00 | $15.00 |
| 19 | Field painting structural steel, intermediate coat (514E00060) | SF | 2,385 | $8.00 | $10.00 | $10.00 | $5.00 | $15.00 |
| 20 | Field painting structural steel, finish coat (514E00066) | SF | 2,385 | $8.00 | $10.00 | $10.00 | $5.00 | $15.00 |
| 21 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 8 | $250.00 | $100.00 | $200.00 | $150.00 | $100.00 |
| 22 | Final inspection repair (514E10000) | EACH | 2 | $100.00 | $100.00 | $300.00 | $200.00 | $200.00 |
| 23 | Patching concrete structure (519E11100) | SF | 520 | $240.00 | $175.00 | $180.00 | $175.00 | $165.06 |
| 24 | Surface preparation of existing structural steel (514E00050) | SF | 2,838 | $18.50 | $25.00 | $25.00 | $40.00 | $65.00 |
| 25 | Field painting of existing structural steel, prime coat (514E00056) | SF | 2,838 | $9.00 | $10.00 | $10.00 | $25.00 | $15.00 |
| 26 | Field painting structural steel, intermediate coat (514E00060) | SF | 2,838 | $9.00 | $10.00 | $10.00 | $5.00 | $15.00 |
| 27 | Field painting structural steel, finish coat (514E00066) | SF | 2,838 | $9.00 | $10.00 | $10.00 | $5.00 | $15.00 |
| 28 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 8 | $250.00 | $100.00 | $200.00 | $150.00 | $100.00 |
| 29 | Final inspection repair (514E10000) | EACH | 2 | $100.00 | $100.00 | $300.00 | $200.00 | $200.00 |
| 30 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $9,802.10 | $10,000 | $10,000 | $12,500 | $15,000 |
| 31 | Maintaining traffic (614E11000) | LS | 1 | $30,390 | $49,108 | $40,000 | $50,000 | $30,000 |
| 32 | Mobilization (624E10000) | LS | 1 | $25,870 | $30,000 | $25,000 | $20,000 | $70,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.