ODOT contract 15616 bid tabulation
I-84: farewell bend - n. fork jacobsen gulch. Let by Oregon DOT on October 30, 2025, Region 5. 6 bids received.
- Owner
- Oregon DOT
- Letting
- 30 OCT 2025
- Pay items
- 157
- Data through
- 13 AUG 2026
Bidders
| Rank | Total bid | Against the low bid |
|---|---|---|
| 1 | Low | |
| 2 | ||
| 3 | ||
| 4 | ||
| 5 | ||
| 6 |
Bid tabulation
| Line | Pay item | Unit | Quantity | Rank 1 | Rank 2 | Rank 3 | Rank 4 | Rank 5 | Rank 6 |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Terminal anchors (0755-0200000F) | LF | 156 | $400.00 | $331.00 | $476.00 | $334.27 | $320.00 | $350.00 |
| 2 | Guardrail transition (0810-0126000E) | EACH | 2 | $2,900.00 | $3,675.00 | $2,875.00 | $3,600.00 | $3,018.75 | $3,360.00 |
| 3 | Finishing roadbeds (0370-0100000A) | SY | 1,700 | $50.00 | $37.46 | $5.12 | $76.47 | $88.24 | $5.44 |
| 4 | Pole foundations (0970-0100000A) | EACH | 23 | $2,173.91 | $3,926.09 | $844.22 | $3,826.09 | $4,347.83 | $4,347.83 |
| 5 | Portable changeable message signs, roller mounted (0222-0167300E) | EACH | 2 | $15,000 | $11,000 | $4,400.00 | $9,925.00 | $13,000 | $14,000 |
| 6 | Level 3, 1/2 inch lime treated ACP (0745-0322000M) | TON | 15,400 | $66.50 | $101.00 | $106.00 | $135.00 | $92.79 | $110.00 |
| 7 | Automatic traffic recorder installation, 23-016 (0990-0107000A) | EACH | 1 | $12,500 | $13,020 | $10,000 | $12,750 | $20,000 | $14,500 |
| 8 | Temporary barricades, type III (0224-0105000E) | EACH | 18 | $200.00 | $210.00 | $95.00 | $205.00 | $175.00 | $200.00 |
| 9 | Repair temporary impact attenuator, truck mounted (0226-0141400E) | EACH | 1 | $1.00 | $5,250.00 | $10,000 | $18,500 | $500.00 | $17,500 |
| 10 | Cold plane pavement removal, 0 - 4 inches deep (0620-0107000J) | SY | 6,740 | $3.00 | $4.05 | $2.85 | $3.85 | $2.65 | $3.50 |
| 11 | Bridge approach slab cold plane pavement removal, 2 - 4 inches deep (0503-0103100J) | SY | 260 | $7.50 | $31.80 | $43.50 | $42.00 | $10.00 | $9.50 |
| 12 | Control joint (0585-0300000A) | LF | 267 | $22.47 | $31.46 | $20.39 | $54.87 | $37.45 | $22.17 |
| 13 | Temporary impact attenuator, truck mounted (0226-0138000E) | EACH | 2 | $35,000 | $35,280 | $26,300 | $72,000 | $50,000 | $68,300 |
| 14 | Flaggers (0223-0168000T) | HR | 200 | $85.00 | $129.00 | $84.60 | $125.00 | $80.00 | $130.00 |
| 15 | Asphalt pavement sawcutting, 12 inches deep (0310-0119100F) | LF | 700 | $15.25 | $4.40 | $9.00 | $4.35 | $10.00 | $8.00 |
| 16 | Temporary work access and containment (0253-0106000A) | LS | 1 | $20,000 | $26,250 | $90,000 | $105,000 | $15,000 | $22,500 |
| 17 | Granular structure backfill (0510-0108000A) | CY | 170 | $188.24 | $154.41 | $122.35 | $147.06 | $147.06 | $253.53 |
| 18 | Temporary signs (0222-0102000J) | SF | 2,000 | $30.00 | $8.40 | $17.25 | $8.25 | $25.00 | $41.00 |
| 19 | Asphalt pavement sawcutting, 1 1/2 inches deep (0310-0119100F) | LF | 59,000 | $1.05 | $1.05 | $1.04 | $1.05 | $1.50 | $1.00 |
| 20 | Level 4, 1/2 inch lime treated ACP (0745-0422000M) | TON | 93,000 | $43.00 | $94.50 | $101.00 | $115.00 | $83.11 | $100.00 |
| 21 | Reconditioning existing roadway (0610-0103000A) | LS | 1 | $15,000 | $12,185 | $43,300 | $1.00 | $40,000 | $17,700 |
| 22 | Level 3, 1/2 inch lime treated ACP in leveling (0745-0334000M) | TON | 600 | $75.00 | $116.00 | $118.00 | $150.00 | $210.00 | $240.00 |
| 23 | Extra for 8 foot posts (0810-0133000E) | EACH | 1,800 | $35.00 | $47.30 | $35.00 | $46.00 | $36.75 | $41.00 |
| 24 | Signs, standard sheeting, extruded aluminum (0940-0201000J) | SF | 125 | $33.00 | $39.90 | $40.00 | $42.00 | $40.00 | $44.00 |
| 25 | Mainline video inspection (0415-0100000F) | LF | 394 | $10.00 | $21.00 | $18.00 | $17.00 | $10.00 | $5.00 |
| 26 | Bridge removal work (0501-0100000A) | SF | 2,286 | $37.18 | $27.56 | $35.00 | $13.12 | $21.87 | $7.13 |
| 27 | Surface texturing (0540-0401000J) | SY | 337 | $30.00 | $40.40 | $25.00 | $72.50 | $10.00 | $23.00 |
| 28 | 42 inch diameter signal support drilled shaft (0963-0102000F) | LF | 16 | $800.00 | $1,208.00 | $600.00 | $1,185.00 | $650.00 | $1,340.00 |
| 29 | Electrical systems installation, site 2 (0985-0100000A) | LS | 1 | $50,000 | $55,650 | $35,000 | $54,500 | $80,000 | $61,900 |
| 30 | Telecommunications, splicing and testing (0987-0120000A) | LS | 1 | $6,000.00 | $3,780.00 | $5,400.00 | $3,700.00 | $10,000 | $4,200.00 |
| 31 | Telecommunications, installation (0987-0110000A) | LS | 1 | $7,000.00 | $3,675.00 | $6,200.00 | $3,600.00 | $10,000 | $4,090.00 |
| 32 | Concrete curbs, mountable curb (0759-0118000F) | LF | 560 | $60.00 | $90.30 | $46.00 | $33.50 | $50.00 | $58.00 |
| 33 | Cold plane pavement removal, 2 inches deep (0620-0120000J) | SY | 212,500 | $1.50 | $2.40 | $2.00 | $2.40 | $1.95 | $3.50 |
| 34 | Paved culvert end slopes (0460-0100000J) | SF | 82 | $100.00 | $121.00 | $70.50 | $160.00 | $160.00 | $76.00 |
| 35 | 15 inch culvert pipe, 5 FT depth (0445-010015AF) | LF | 358 | $105.00 | $122.00 | $86.00 | $91.00 | $200.00 | $100.00 |
| 36 | Sediment barrier, type 3 (0280-0115030F) | LF | 188 | $8.00 | $13.00 | $10.25 | $1.80 | $6.00 | $10.00 |
| 37 | Temporary flexible pavement markers (0225-0149000E) | EACH | 22,000 | $0.55 | $3.65 | $3.00 | $1.90 | $2.10 | $2.00 |
| 38 | Type "F" concrete rail (0587-0120000A) | LF | 96 | $364.58 | $601.56 | $437.50 | $835.94 | $520.83 | $409.38 |
| 39 | Emulsified asphalt for tack coat (0730-0100000M) | TON | 280 | $1.00 | $549.50 | $1.00 | $1,130.00 | $650.00 | $770.00 |
| 40 | Foundation excavation (0330-0102000K) | CY | 200 | $100.00 | $53.80 | $38.25 | $44.00 | $50.00 | $79.00 |
| 41 | Gap pattern rumble strips (0857-0101500L) | MI | 27 | $2,100.00 | $2,205.00 | $2,100.00 | $2,150.00 | $2,205.00 | $2,450.00 |
| 42 | Pavement legend, type B: arrows (0867-0103000E) | EACH | 9 | $600.00 | $577.50 | $550.00 | $565.00 | $577.50 | $640.00 |
| 43 | Triangular base breakaway sign supports (0930-0112000A) | LB | 320 | $12.50 | $11.22 | $12.50 | $22.58 | $15.63 | $12.47 |
| 44 | Luminaires, lamps, and ballasts (0970-0104000A) | EACH | 23 | $869.57 | $776.09 | $860.87 | $760.87 | $1,304.35 | $860.87 |
| 45 | Cable barrier terminals (0811-0103000E) | EACH | 3 | $10,000 | $14,700 | $8,439.00 | $14,400 | $8,860.95 | $9,850.00 |
| 46 | Type 1 fence (1050-0100000F) | LF | 3,600 | $16.00 | $9.45 | $11.00 | $25.00 | $25.00 | $13.00 |
| 47 | Cable barrier, test level 3 (0811-0101000F) | LF | 560 | $85.00 | $94.50 | $81.50 | $92.00 | $85.58 | $95.00 |
| 48 | PG 70-28ER asphalt in level 4, 1/2 inch lime treated ACP (0745-0642100M) | TON | 5,600 | $815.00 | $0.01 | $1.00 | $1.00 | $787.50 | $890.00 |
| 49 | Concrete repair (0542-0102001J) | SF | 14 | $675.00 | $997.50 | $577.13 | $1,135.00 | $500.00 | $370.00 |
| 50 | Delineators, type 1 (0840-0100000E) | EACH | 1,100 | $52.50 | $60.90 | $75.00 | $87.00 | $94.50 | $68.00 |
| 51 | Impact attenuator, type B - valtir energite III (0830-0115000E) | EACH | 1 | $6,500.00 | $4,200.00 | $4,000.00 | $12,300 | $4,200.00 | $4,900.00 |
| 52 | Cold plane pavement removal, 3 inches deep (0620-0122000J) | SY | 103,100 | $1.50 | $3.35 | $2.90 | $3.00 | $2.20 | $3.75 |
| 53 | Structure excavation (0510-0101000A) | CY | 350 | $114.29 | $153.00 | $88.29 | $6.83 | $57.14 | $85.14 |
| 54 | Loose riprap, class 50 (0390-0105000K) | CY | 74 | $85.00 | $221.50 | $105.00 | $130.00 | $300.00 | $80.00 |
| 55 | Riprap geotextile, type 1 (0350-0103000J) | SY | 200 | $5.00 | $6.75 | $3.45 | $11.75 | $4.50 | $2.50 |
| 56 | Repair temporary impact attenuator, narrow site system (0226-0141300E) | EACH | 1 | $4,000.00 | $4,200.00 | $4,000.00 | $11,850 | $4,000.00 | $4,900.00 |
| 57 | Radar speed trailer (0222-0167500E) | EACH | 2 | $10,000 | $12,600 | $6,600.00 | $12,500 | $15,000 | $14,000 |
| 58 | Portable changeable message signs (0222-0164000E) | EACH | 5 | $12,000 | $16,537 | $8,200.00 | $16,250 | $23,000 | $23,200 |
| 59 | Bridge rail silane sealing (1999-9Z90000J) | SF | 1,481 | $4.25 | $4.45 | $13.00 | $2.55 | $2.70 | $1.00 |
| 60 | Guardrail blocks (0812-0108000E) | EACH | 310 | $25.00 | $5.25 | $21.00 | $5.10 | $195.30 | $25.00 |
| 61 | Delineators, type 6 (0840-0105500E) | EACH | 740 | $12.00 | $52.50 | $12.00 | $31.00 | $12.60 | $14.00 |
| 62 | Remove existing signs (0905-0100000A) | LS | 1 | $1,500.00 | $1,050.00 | $1,500.00 | $14,450 | $10,000 | $1,170.00 |
| 63 | Sign support footings (0920-0100000A) | CY | 3 | $7,333.33 | $2,100.00 | $2,333.33 | $10,167 | $4,666.67 | $2,333.33 |
| 64 | Multi-post breakaway sign supports (0930-0111000A) | LB | 1,687 | $8.89 | $7.67 | $6.37 | $8.54 | $11.86 | $9.66 |
| 65 | 42 inch barrier silane sealing (1999-9Z90000F) | LF | 16,708 | $7.50 | $10.10 | $2.50 | $5.30 | $13.85 | $40.00 |
| 66 | Guardrail terminals, non-flared (0810-0129000E) | EACH | 17 | $3,500.00 | $3,675.00 | $3,125.00 | $3,600.00 | $3,281.25 | $3,650.00 |
| 67 | Terminal expansion joint (0755-0400000F) | LF | 52 | $250.00 | $383.50 | $338.38 | $412.00 | $400.00 | $440.00 |
| 68 | Continuously reinforced concrete pavement 10 inches thick (0755-0106000J) | SY | 84,300 | $124.75 | $124.00 | $132.50 | $115.50 | $114.56 | $150.00 |
| 69 | Cold plane pavement removal, 1 - 2 inches deep (0620-0111000J) | SY | 40,000 | $1.50 | $2.40 | $1.70 | $2.00 | $2.05 | $3.00 |
| 70 | Elastomeric concrete nosing material (0584-0103000C) | CF | 63 | $95.00 | $131.50 | $80.64 | $105.00 | $250.00 | $120.00 |
| 71 | Moving temporary impact attenuators, narrow site system (0226-0137000E) | EACH | 2 | $1,000.00 | $2,047.00 | $1,950.00 | $1,550.00 | $2,000.00 | $2,390.00 |
| 72 | Level 3, 1/2 inch lime treated ACP in leveling and temporary (0745-0371000M) | TON | 54 | $250.00 | $263.00 | $198.00 | $336.00 | $210.00 | $120.00 |
| 73 | Signs, standard sheeting, sheet aluminum (0940-0202000J) | SF | 50 | $28.00 | $29.40 | $30.00 | $18.50 | $35.00 | $33.00 |
| 74 | Permanent seeding (1030-0108000R) | ACRE | 1 | $4,000.00 | $9,841.00 | $10,000 | $11,000 | $5,400.00 | $16,800 |
| 75 | Cold plane pavement removal, 2 - 3 inches deep (0620-0112000J) | SY | 650 | $4.00 | $4.95 | $3.75 | $3.90 | $4.60 | $6.50 |
| 76 | Class 2 preparation (0504-0100000J) | SY | 69 | $250.00 | $236.50 | $351.08 | $255.00 | $650.00 | $290.00 |
| 77 | Lighting poles and arms (0970-0200000A) | EACH | 23 | $8,695.65 | $7,989.09 | $7,060.87 | $7,826.09 | $8,695.65 | $8,869.57 |
| 78 | Telecommunications, material (0987-0100000A) | LS | 1 | $1,600.00 | $3,150.00 | $1,584.00 | $3,075.00 | $10,000 | $3,500.00 |
| 79 | Cold plane pavement removal, 7.5 inches deep (0620-0126000J) | SY | 13,500 | $2.25 | $8.10 | $9.00 | $6.65 | $6.10 | $9.00 |
| 80 | Temporary plastic drums (0224-0145000E) | EACH | 430 | $50.00 | $21.00 | $22.00 | $20.00 | $50.00 | $58.00 |
| 81 | Remove and reinstall existing concrete barrier, tall (0820-0510000F) | LF | 16,708 | $10.50 | $11.90 | $11.29 | $1.05 | $11.85 | $18.00 |
| 82 | Permanent surface mounted tubular markers (0856-0101000E) | EACH | 10 | $300.00 | $577.50 | $550.00 | $155.00 | $577.50 | $640.00 |
| 83 | Sign support footings (0920-0100000A) | CY | 2.50 | $8,000.00 | $6,804.00 | $520.00 | $9,400.00 | $16,000 | $10,720 |
| 84 | 12 inch subgrade stabilization (0331-0106000J) | SY | 500 | $50.00 | $84.30 | $42.50 | $92.00 | $45.00 | $86.00 |
| 85 | Plural component, sprayed, grooved (0866-0114000F) | LF | 410,000 | $1.00 | $1.00 | $0.96 | $1.00 | $1.01 | $1.00 |
| 86 | Multi-post breakaway sign supports (0930-0111000A) | LB | 1,126 | $6.66 | $6.46 | $6.80 | $7.77 | $17.76 | $8.81 |
| 87 | Automated flagger assistance device (0223-0200000E) | EACH | 2 | $3,500.00 | $14,490 | $15,350 | $14,250 | $3,500.00 | $1,280.00 |
| 88 | Plural component, sprayed, surface (0866-0113000F) | LF | 19,300 | $1.25 | $1.20 | $1.15 | $1.20 | $1.21 | $1.50 |
| 89 | Minimum deflection bridge temporary barrier (0226-0147000F) | LF | 87.50 | $235.00 | $94.50 | $90.00 | $235.00 | $100.00 | $110.00 |
| 90 | Cold plane pavement removal, 0 - 7 inches deep (0620-0109000J) | SY | 56,700 | $2.40 | $6.95 | $4.00 | $4.25 | $3.65 | $4.50 |
| 91 | Amg cold plane pavement removal, 2 - 14 inches deep (0621-0100000J) | SY | 84,300 | $10.00 | $7.40 | $9.10 | $6.85 | $9.50 | $11.00 |
| 92 | PG 64-28 asphalt in level 3, 1/2 inch lime treated ACP (0745-0622000M) | TON | 950 | $750.00 | $0.01 | $1.00 | $1.00 | $682.50 | $770.00 |
| 93 | Core correlation of nuclear gauge readings (0745-0900000E) | EACH | 5 | $2,300.00 | $5,433.00 | $2,200.00 | $3,050.00 | $1,575.00 | $1,770.00 |
| 94 | Extra for hand dug guardrail post holes (0810-0145000E) | EACH | 2 | $450.00 | $315.00 | $450.00 | $305.00 | $472.50 | $530.00 |
| 95 | Thrie-beam to W-beam transition (0810-0126000E) | EACH | 1 | $500.00 | $1,575.00 | $500.00 | $1,550.00 | $525.00 | $580.00 |
| 96 | Sequential arrow signs (0222-0162000E) | EACH | 2 | $5,500.00 | $2,625.00 | $2,750.00 | $2,550.00 | $8,000.00 | $7,000.00 |
| 97 | Guardrail posts (0812-0106000E) | EACH | 90 | $90.00 | $52.50 | $80.00 | $51.63 | $84.00 | $93.00 |
| 98 | Perforated steel square tube slip base sign supports (0930-0114000A) | LB | 180 | $6.67 | $7.58 | $8.33 | $16.94 | $16.67 | $8.44 |
| 99 | Adjusting inlets (0490-0105000E) | EACH | 34 | $1,000.00 | $2,800.00 | $460.00 | $985.00 | $1,600.00 | $1,100.00 |
| 100 | Trench resurfacing (0495-0100000J) | SY | 16 | $250.00 | $170.50 | $142.50 | $35.00 | $145.00 | $120.00 |
| 101 | Bridge identification markers (0842-0401000E) | EACH | 4 | $300.00 | $367.50 | $60.00 | $525.00 | $250.00 | $580.00 |
| 102 | Electrical systems installation, site 3 (0985-0100000A) | LS | 1 | $200,000 | $183,749 | $146,800 | $180,000 | $250,000 | $204,000 |
| 103 | Guardrail anchors, type 1 modified (0810-0120000E) | EACH | 1 | $1,500.00 | $1,575.00 | $1,500.00 | $1,550.00 | $1,575.00 | $1,750.00 |
| 104 | Concrete slope paving (0599-0100000J) | SF | 1,275 | $32.50 | $47.30 | $35.25 | $60.00 | $38.00 | $25.00 |
| 105 | Camera poles and foundations (0965-0100000A) | LS | 1 | $25,000 | $20,475 | $22,900 | $20,000 | $30,000 | $22,800 |
| 106 | Sign support footings (0920-0100000A) | CY | 2.50 | $2,000.00 | $2,016.00 | $4,800.00 | $8,240.00 | $2,000.00 | $10,720 |
| 107 | Concrete barrier, tall (0820-0127000F) | LF | 492 | $140.00 | $205.00 | $195.00 | $25.75 | $204.75 | $240.00 |
| 108 | Guardrail terminals, downstream anchor terminal (0810-0132200E) | EACH | 5 | $1,700.00 | $2,100.00 | $1,650.00 | $2,050.00 | $1,732.50 | $1,930.00 |
| 109 | Secondary cold plane pavement removal, 3 inches deep (0620-0146000J) | SY | 8,500 | $2.50 | $3.60 | $3.50 | $4.45 | $2.30 | $3.50 |
| 110 | Switching, conduit, and wiring (0970-0105000A) | LF | 5,125 | $48.78 | $34.83 | $23.61 | $34.15 | $39.02 | $38.63 |
| 111 | General excavation (0330-0105000K) | CY | 2,980 | $22.00 | $41.70 | $39.00 | $26.00 | $38.00 | $33.00 |
| 112 | Electrical systems installation, site 4 (0985-0100000A) | LS | 1 | $50,000 | $45,150 | $47,000 | $44,000 | $55,000 | $50,200 |
| 113 | Removal of structures and obstructions (0310-0106000A) | LS | 1 | $250,000 | $103,991 | $250,000 | $53,000 | $500,000 | $150,000 |
| 114 | Surface mounted tubular markers (0224-0142000E) | EACH | 1,385 | $68.00 | $236.50 | $225.00 | $61.00 | $62.00 | $260.00 |
| 115 | Metal beam rails (0812-0104000E) | EACH | 30 | $200.00 | $94.50 | $186.00 | $92.00 | $3.78 | $220.00 |
| 116 | Midwest guardrail system, type 2A (0810-0146100F) | LF | 14,100 | $25.50 | $24.20 | $25.25 | $23.50 | $26.51 | $29.00 |
| 117 | Penetrating concrete sealing (0537-0101000J) | SF | 20,469 | $1.45 | $2.00 | $1.28 | $1.05 | $0.70 | $1.00 |
| 118 | Bridge approach sleeper slabs (0545-0100200F) | LF | 97 | $400.00 | $562.00 | $628.28 | $550.00 | $230.00 | $490.00 |
| 119 | Electrical systems installation, site 6 (0985-0100000A) | LS | 1 | $100,000 | $120,750 | $71,000 | $118,000 | $130,000 | $134,000 |
| 120 | Multi-post breakaway sign supports (0930-0111000A) | LB | 1,687 | $8.00 | $7.67 | $6.33 | $8.54 | $11.86 | $9.66 |
| 121 | Temporary barrier (0226-0126100F) | LF | 19,335 | $5.25 | $7.35 | $7.00 | $14.50 | $7.00 | $8.50 |
| 122 | Guardrail height conversion, type 2A (0810-0147000E) | EACH | 8 | $1,600.00 | $1,575.00 | $1,555.00 | $1,550.00 | $1,632.75 | $1,820.00 |
| 123 | Sign support footings (0920-0100000A) | CY | 2.50 | $8,000.00 | $6,804.00 | $480.00 | $9,500.00 | $12,000 | $9,320.00 |
| 124 | Drainage curbs (0480-0100000F) | LF | 7,000 | $13.50 | $24.70 | $13.20 | $23.00 | $13.50 | $19.00 |
| 125 | Multi-post breakaway sign supports (0930-0111000A) | LB | 520 | $50.00 | $11.41 | $11.54 | $15.38 | $19.23 | $12.69 |
| 126 | Adjusting guardrail (0812-0101000F) | LF | 35,325 | $3.65 | $5.25 | $3.60 | $5.10 | $3.78 | $4.00 |
| 127 | Guardrail end pieces, type B (0810-0122000E) | EACH | 1 | $165.00 | $157.50 | $165.00 | $155.00 | $173.25 | $190.00 |
| 128 | 6 inch asphalt concrete pavement repair (0748-0103000J) | SY | 2,200 | $46.00 | $44.00 | $15.00 | $30.00 | $35.00 | $42.00 |
| 129 | Constructing elastomeric concrete nosing (0584-0104000J) | SF | 324 | $85.00 | $121.00 | $52.92 | $145.00 | $55.00 | $160.00 |
| 130 | Replace surface mounted tubular markers (0224-0143000E) | EACH | 215 | $100.00 | $189.00 | $180.00 | $30.00 | $60.00 | $210.00 |
| 131 | Stone embankment (0330-0126000K) | CY | 2,512 | $60.00 | $60.40 | $52.25 | $105.00 | $60.00 | $81.00 |
| 132 | Temporary impact attenuator, narrow site system (0226-0134000E) | EACH | 5 | $5,500.00 | $4,042.00 | $3,850.00 | $14,750 | $4,000.00 | $4,720.00 |
| 133 | Drainage geotextile, type 1 (0350-0100000J) | SY | 1,009 | $2.15 | $5.20 | $2.30 | $2.60 | $2.30 | $2.00 |
| 134 | Rectangular tube retrofit (0587-0139000A) | LF | 510 | $127.45 | $154.41 | $222.55 | $156.86 | $156.86 | $572.55 |
| 135 | Aggregate base (0641-0102000M) | TON | 1,720 | $50.00 | $50.50 | $53.50 | $47.25 | $58.00 | $56.00 |
| 136 | Crack sealing (0746-0100000F) | LF | 59,000 | $1.15 | $1.00 | $0.67 | $1.35 | $1.50 | $2.00 |
| 137 | Continuously reinforced concrete pavement 12 inches thick (0755-0108000J) | SY | 231 | $315.00 | $325.50 | $219.00 | $314.00 | $376.94 | $350.00 |
| 138 | Continuous rumble strips (0857-0101000L) | MI | 24 | $2,100.00 | $2,205.00 | $2,100.00 | $2,150.00 | $2,205.00 | $2,450.00 |
| 139 | Pavement bar, type B (0867-0145000J) | SF | 150 | $20.00 | $19.40 | $18.50 | $19.00 | $19.43 | $22.00 |
| 140 | Electrical systems installation, site 1 (0985-0100000A) | LS | 1 | $85,000 | $63,000 | $66,000 | $61,000 | $100,000 | $70,000 |
| 141 | Inject and seal cracks (0538-0100000F) | LF | 40 | $400.00 | $278.50 | $185.19 | $85.00 | $160.00 | $92.00 |
| 142 | Midwest guardrail system, type 3 (0810-0146100F) | LF | 537.50 | $55.00 | $63.00 | $51.20 | $61.75 | $53.76 | $60.00 |
| 143 | Electrical systems installation, site 5 (0985-0100000A) | LS | 1 | $50,000 | $45,150 | $45,000 | $44,000 | $54,393 | $50,200 |
| 144 | Cold plane pavement removal, 4 inches deep (0620-0123000J) | SY | 5,900 | $3.65 | $4.95 | $4.10 | $5.95 | $4.65 | $6.00 |
| 145 | Concrete and crack sealer (0539-0100000J) | SF | 20,469 | $1.75 | $2.35 | $1.45 | $2.50 | $1.90 | $2.50 |
| 146 | Reinforced concrete bridge approach slabs (0545-0100100J) | SY | 390 | $500.00 | $703.50 | $707.07 | $525.00 | $450.00 | $390.00 |
| 147 | 18 inch storm sewer pipe, 5 FT depth (0445-035018AF) | LF | 36 | $205.00 | $139.50 | $113.50 | $125.00 | $220.00 | $160.00 |
| 148 | Emulsified asphalt in fog coat (0705-0101000M) | TON | 20 | $500.00 | $1,513.00 | $1,325.00 | $1,925.00 | $1,300.00 | $1,420.00 |
| 149 | Extra for asphalt approaches (0749-0100000E) | EACH | 17 | $1,500.00 | $2,537.00 | $2,225.00 | $595.00 | $3,386.46 | $3,810.00 |
| 150 | Aggregate shoulders (0641-0130000M) | TON | 3,000 | $45.00 | $44.50 | $33.75 | $82.00 | $48.00 | $48.00 |
| 151 | Concrete inlets, type G-2 (0470-0315000E) | EACH | 2 | $6,000.00 | $7,838.00 | $4,500.00 | $4,235.00 | $5,000.00 | $4,360.00 |
| 152 | Temporary delineators (0224-0147000E) | EACH | 20 | $100.00 | $105.00 | $110.00 | $103.00 | $125.00 | $68.00 |
| 153 | Pollution control plan (0290-0100000A) | LS | 1 | $500.00 | $2,730.00 | $5,000.00 | $2,650.00 | $3,000.00 | $1,500.00 |
| 154 | Temporary striping (0225-0153000F) | LF | 283,750 | $0.20 | $0.20 | $0.18 | $0.25 | $0.18 | $0.65 |
| 155 | Precompressed foam silicone joint seal (0585-0215000A) | LF | 517 | $106.38 | $121.86 | $87.49 | $83.17 | $77.37 | $94.58 |
| 156 | Cold plane pavement removal, 1 inches deep (0620-0118000J) | SY | 155,000 | $1.40 | $1.45 | $1.00 | $1.75 | $1.30 | $2.50 |
| 157 | Stripe removal (0225-0154000F) | LF | 210,000 | $0.32 | $0.35 | $0.32 | $0.35 | $0.32 | $0.40 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.
Every contract let that day: ODOT letting of October 30, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.