SCDOT contract 0275090 bid tabulation

2026 Aiken CTC Resurfacing. Let by South Carolina DOT on November 12, 2025, Aiken, District 7. 2 bids received; low bid $6,058,267 by Satterfield Construction Company, Inc..

Owner
South Carolina DOT
Letting
12 NOV 2025
Pay items
45
Data through
13 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Satterfield Construction Company, Inc.$6,058,267Low
2Blythe Construction, Inc.$6,348,647+5.0%
SCDOT contract 0275090: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Satterfield Construction Company, Inc.2. Blythe Construction, Inc.
0010Mobilization (1031000)LS1$350,000$317,400
0020Bonds and insurance (1032010)LS1$85,000$28,000
0030Removal & disposal of existing pavement (2023000)SY50$95.00$60.00
0040Removal of exist. guardrail (2027801)LF1,320$1.10$1.00
0050Borrow excavation (2033000)CY3,232$46.00$107.00
0060Excavation for shoulder paving (2036000)STA1,552.85$55.00$56.00
0070Hauling of excavated shoulder material (2072000)STA1,552.85$62.50$27.00
0080Maintenance stone (3059900)TON28$43.00$63.00
0090HMA shoulder widening course (3104000)TON8,668.15$84.00$93.75
0100Liquid asphalt binder PG64-22 (4011004)TON1,699.37$715.00$603.50
0110Aramid fiber (4011500)LB4,990$62.00$60.00
0120Full depth asph. pav. patching 4" unif. (4012040)SY2,325$46.00$70.50
0130Full depth asph. pav. patching 6" unif. (4012060)SY475$75.00$106.00
0140Milling existing asphalt pavement (variable) (4013990)SY5,275$7.20$21.00
0150Asphalt surface course type C (4040340)TON17,409.83$89.00$92.00
0160Asphalt surface course type D (4040350)TON1,229.68$115.00$128.00
0170Driveway paving-surface type D (4047230)TON1,372.50$215.00$305.00
0180Traffic control (6011000)LS1$425,000$506,500
0190Permanent construction signs (ground mounted) (6051120)SF1,448$5.90$5.35
02004" white broken lines -(gaps excluded)-fast dry paint (6240005)LF760$0.14$0.12
02104" white solid lines (PVT. edge lines)-fast dry paint (6240010)LF285,970$0.14$0.11
02208"white solid lines (crosswalk& channelization)fast dry paint (6240015)LF140$0.14$0.12
023024" white solid lines (stop/diagonal lines)-fast dry paint (6240025)LF920$0.55$0.50
02404" yellow broken lines(gaps exc) - fast dry paint (6240105)LF7,740$0.14$0.12
02504"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110)LF263,580$0.14$0.11
02604" white broken lines(gaps excl.)perm.PVMT.marking (6251005)LF380$0.55$0.48
02704" white solid lines (PVT. edge lines) perm.PVMT.marking (6251010)LF143,140$0.50$0.45
02808" white solid lines perm.PVMT.markings (6251015)LF70$3.30$3.00
029024" white solid lines (stop/diag lines)- perm.PVMT.marking (6251025)LF460$9.90$9.00
03004" yellow broken lines(gaps exc)perm.PVMT.marking (6251064)LF3,870$0.55$0.48
03104" yellow solid lines(PVT.edge lines) perm.PVMT.marking (6251074)LF131,790$0.50$0.45
03204" white solid lines (PVT. edge lines) epoxy paint slow cure (6261010)LF400$6.05$5.50
03304"yellow solid lines- PVT.edge&no passing zone - epoxy paint slow cure (6261110)LF400$6.05$5.50
0340Permanent yellow pavement markers BI-dir.- 4"X4" (6301100)EACH1,084$6.60$6.00
0350Milled-in rumble strip (6321000)MI19.71$841.50$1,064.62
0360Furnish & install 1.0" schedule 80 PVC conduit (6750275)LF20$27.50$17.50
0370Furnish & instl no. 14 copper wire,1-conductor for loop wire (6770413)LF450$11.00$1.15
0380Sawcut for loop detector (6780495)LF150$16.50$9.61
0390Detectable warning material (7204900)SF25$95.00$70.00
0400Pedestrian ramp construction (7209000)SY50$207.55$250.00
0410Surface applied detectable warning (7209100)SF10$79.95$70.00
0420MT3 leading end treatment TL3 (8051151)EACH12$4,063.45$3,700.00
0430MGS3 GR standard shoulder (8052100)LF300$32.25$22.00
0440MTBBC3 MASH thrie-beam barrier connector TL3 (8053253)EACH12$4,286.00$2,600.00
0450Permanent grassing for non-permitted resurfacing projects (8100102)ACRE16.16$3,025.00$2,750.00
SCDOT contract 0275090: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.

Every contract let that day: SCDOT letting of November 12, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy