SCDOT contract 2056600 bid tabulation
Traffic Signal Upgrade - US 21 at SC 34. Let by South Carolina DOT on November 12, 2025, Fairfield, District 4. 3 bids received; low bid $240,274 by Lumin8 Transportation Technologies, LLC.
- Owner
- South Carolina DOT
- Letting
- 12 NOV 2025
- Pay items
- 27
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lumin8 Transportation Technologies, LLC | $240,274 | Low |
| 2 | Walker Brothers, Inc. | $299,687 | +25% |
| 3 | W.M. Roebuck, Incorporated | $399,300 | +66% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lumin8 Transportation Technologies, LLC | 2. Walker Brothers, Inc. | 3. W.M. Roebuck, Incorporated |
|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $16,280 | $38,500 | $10,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $2,775.00 | $3,624.00 | $11,630 |
| 0030 | Traffic control (6011000) | LS | 1 | $11,430 | $36,125 | $10,000 |
| 0040 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 300 | $19.30 | $5.50 | $15.00 |
| 0050 | Removal of pavement markings (6319505) | LF | 300 | $19.30 | $5.50 | $11.00 |
| 0060 | Furnish & install 1.0" schedule 80 PVC conduit (6750275) | LF | 60 | $6.75 | $18.10 | $20.00 |
| 0070 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 130 | $13.85 | $18.50 | $21.00 |
| 0080 | Furnish & install 3.0" schedule 80 PVC conduit (675027C) | LF | 30 | $13.75 | $28.00 | $25.00 |
| 0090 | Furnish additional conduit within directional bore (675027Z) | LF | 240 | $30.85 | $8.00 | $15.00 |
| 0100 | Furnish & install 2" schedule 80 HDPE conduit (directional bored) (6760065) | LF | 120 | $38.55 | $32.00 | $30.00 |
| 0110 | Furnish & install no. 14 copper wire, 8 conductor (black) (6770393) | LF | 1,310 | $4.45 | $5.75 | $6.00 |
| 0120 | Furnish & install no. 14 copper wire, 8 conductor (gray) (6770394) | LF | 800 | $5.10 | $5.85 | $6.00 |
| 0130 | Furnish & instl no. 14 copper wire,1-conductor for loop wire (6770413) | LF | 600 | $2.25 | $1.40 | $1.50 |
| 0140 | Sawcut for loop detector (6780495) | LF | 240 | $38.55 | $9.85 | $12.00 |
| 0150 | Furnish & install electrical service for traffic signal (6800499) | EACH | 1 | $9,790.00 | $1,850.00 | $1,500.00 |
| 0160 | F&I-17"X30"X24"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (680052C) | EACH | 4 | $1,425.00 | $1,095.00 | $750.00 |
| 0170 | Furnish & install 10' break- away alum pedestal pole and base (6825484) | EACH | 3 | $2,290.00 | $1,975.00 | $1,300.00 |
| 0180 | F&I - contr 332/336 cabinet assembly - base mounted 001 (6845511) | EACH | 1 | $22,360 | $24,175 | $26,000 |
| 0190 | Furnish & install - 12" 3 (6865723) | EACH | 8 | $1,412.30 | $895.00 | $1,100.00 |
| 0200 | F&I - 1-way-1SECT.(countdown hand/man emblem)ped.sig.head (6865783) | EACH | 8 | $840.50 | $980.00 | $900.00 |
| 0210 | F&I-ped push but.solid state W/ tone assem 9"X15"&sign (R- 10-3E or R10-4A) (6865797) | EACH | 8 | $586.25 | $650.00 | $1,100.00 |
| 0220 | Backplate W/ retrorefl.borders for traff. sig. (6865834) | EACH | 8 | $171.35 | $295.00 | $300.00 |
| 0230 | Removal,salvage,&disp.of existing traf. signal equipment (6885990) | LS | 1 | $9,477.15 | $5,500.00 | $4,000.00 |
| 0240 | Temporary adjustment of traffic signal equipment (6885993) | EACH | 1 | $1,571.50 | $20,000 | $1,000.00 |
| 0250 | Furnish & install concrete cabinet foundation (6887951) | EACH | 1 | $2,900.00 | $2,000.00 | $1,200.00 |
| 0260 | Design, furnish & install steel pole with twin mast arms including foundation galvanized mast arms (6888177) | EACH | 2 | $36,870 | $49,995 | $130,000 |
| 0270 | Detectable warning material (7204900) | SF | 50 | $131.15 | $125.00 | $75.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of November 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.