SCDOT contract 4347690 bid tabulation
N. Main Street and Manning Ave Revitalization Project. Let by South Carolina DOT on November 12, 2025, Sumter, District 1. 2 bids received; low bid $4,604,904 by Palmetto Corp. of Conway.
- Owner
- South Carolina DOT
- Letting
- 12 NOV 2025
- Pay items
- 147
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Palmetto Corp. of Conway | $4,604,904 | Low |
| 2 | Aos Specialty Contractors, Inc. | $4,999,817 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Palmetto Corp. of Conway | 2. Aos Specialty Contractors, Inc. |
|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $205,000 | $420,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $85,000 | $50,000 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 2 | $12,500 | $20,000 |
| 0040 | CPM progress schedule (1080300) | LS | 1 | $6,000.00 | $21,150 |
| 0050 | Clearing & grubbing within right of way (2011000) | LS | 1 | $167,650 | $95,000 |
| 0051 | Removal & disposal item no. P032341 - 01 (2022000) | LS | 1 | $2,000.00 | $6,325.00 |
| 0052 | Removal & disposal item no. P032341 - 02 (2022000) | LS | 1 | $2,000.00 | $1,935.00 |
| 0053 | Removal & disposal item no. P032341 - 03 (2022000) | LS | 1 | $1,050.00 | $1,850.00 |
| 0054 | Removal & disposal item no. P032341 - 04 (2022000) | LS | 1 | $17,500 | $11,850 |
| 0055 | Removal & disposal of existing pavement (2023000) | SY | 11,038 | $24.70 | $33.50 |
| 0056 | Removal & disposal item no. P032341 - 05 (2022000) | LS | 1 | $1,050.00 | $225.00 |
| 0057 | Removal & disposal item no. P032341 - 06 (2022000) | LS | 1 | $1,050.00 | $550.00 |
| 0058 | Removal & disposal item no. P032383 - 01 (2022000) | LS | 1 | $500.00 | $175.00 |
| 0059 | Removal & disposal item no. P032383 - 02 (2022000) | LS | 1 | $500.00 | $1,675.00 |
| 0060 | Unclassified excavation (2031000) | CY | 432 | $61.50 | $50.00 |
| 0061 | Removal & disposal item no. P032383 - 03 (2022000) | LS | 1 | $1,000.00 | $500.00 |
| 0062 | Removal & disposal item no. P032383 - 04 (2022000) | LS | 1 | $2,000.00 | $1,900.00 |
| 0063 | Removal & disposal item no. P032383 - 05 (2022000) | LS | 1 | $500.00 | $200.00 |
| 0064 | Removal & disposal item no. P032383 - 06 (2022000) | LS | 1 | $2,000.00 | $1,245.00 |
| 0065 | Removal & disposal item no. P032383 - 07 (2022000) | LS | 1 | $500.00 | $200.00 |
| 0066 | Removal & disposal item no. P032383 -08 (2022000) | LS | 1 | $500.00 | $315.00 |
| 0067 | Removal & disposal item no. P032383 - 09 (2022000) | LS | 1 | $1,000.00 | $775.00 |
| 0068 | Removal & disposal item no. P032383 - 10 (2022000) | LS | 1 | $3,000.00 | $8,855.00 |
| 0069 | Removal & disposal item no. P032383 - 11 (2022000) | LS | 1 | $500.00 | $275.00 |
| 0070 | Maintenance stone (3059900) | TON | 40 | $105.00 | $75.00 |
| 0071 | Removal & disposal item no. P032383 - 12 (2022000) | LS | 1 | $500.00 | $150.00 |
| 0072 | Removal & disposal item no. P032383 - 13 (2022000) | LS | 1 | $500.00 | $75.00 |
| 0073 | Removal & disposal item no. P032383 - 14 (2022000) | LS | 1 | $500.00 | $75.00 |
| 0074 | Removal & disposal item no. P032383 - 15 (2022000) | LS | 1 | $500.00 | $125.00 |
| 0075 | Removal & disposal item no. P032383 - 16 (2022000) | LS | 1 | $500.00 | $650.00 |
| 0076 | Removal & disposal item no. P032383 - 17 (2022000) | LS | 1 | $500.00 | $175.00 |
| 0080 | Liquid asphalt binder PG64-22 (4011004) | TON | 218 | $695.00 | $945.00 |
| 0090 | Full depth asph. pav. patching 8" unif (4012080) | SY | 52 | $257.00 | $155.00 |
| 0100 | Milling existing asphalt pavement 2.0" (4013120) | SY | 46,595 | $3.75 | $2.75 |
| 0110 | Milling existing asphalt pavement (variable) (4013990) | SY | 43 | $80.25 | $60.00 |
| 0120 | Asphalt surface course type B (4040320) | TON | 4,172 | $114.00 | $119.00 |
| 0130 | Milling existing concrete pav.(variable) (5013990) | SY | 12 | $285.00 | $119.00 |
| 0140 | Traffic control (6011000) | LS | 1 | $530,000 | $387,000 |
| 0150 | Permanent construction signs (ground mounted) (6051120) | SF | 736 | $5.50 | $11.00 |
| 0160 | Pavement markings(temp- paint) 4" white broken lines (609105A) | LF | 1,850 | $0.01 | $0.20 |
| 0170 | Pavement markings(temp- paint) 4" yellow broken lines (609105B) | LF | 11,822 | $0.15 | $0.20 |
| 0180 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 26,344 | $0.15 | $0.20 |
| 0190 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 47,190 | $0.15 | $0.20 |
| 0200 | Pavement markings(temporary-paint)-8" white solid lines (609125A) | LF | 6,762 | $0.10 | $0.25 |
| 0210 | Pavement markings(temporary-paint)- 24"white solid lines (609135A) | LF | 800 | $0.25 | $0.30 |
| 0220 | Pavement markings(temporary-paint)- white single arrow (609160A) | EACH | 38 | $10.00 | $12.00 |
| 0230 | Pavement markings(temp- thermoplastic)white combination arrws (609165C) | EACH | 2 | $50.00 | $60.00 |
| 0240 | Temporary yellow pavement markers BI-dir.- 4"X4" (6092155) | EACH | 452 | $7.50 | $9.00 |
| 0250 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 925 | $0.75 | $0.90 |
| 0260 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 13,172 | $0.50 | $0.60 |
| 0270 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 3,381 | $2.50 | $3.00 |
| 0280 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 400 | $8.50 | $10.00 |
| 0290 | White single arrows (LT, STRGHT, RT) thermo.-125 mil. (6271030) | EACH | 19 | $150.00 | $180.00 |
| 0300 | White combination arrows(STR&RT.or STR& LT)thermo-125MIL (6271040) | EACH | 1 | $150.00 | $180.00 |
| 0310 | 4" yellow broken lines(gaps exc)thermoplastic - 90 mil. (6271064) | LF | 5,911 | $0.50 | $0.60 |
| 0320 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 23,595 | $0.50 | $0.60 |
| 0330 | Bike lane symbol -preformed thermo - 60MIL (6280055) | EACH | 33 | $150.00 | $180.00 |
| 0340 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 226 | $7.50 | $9.00 |
| 0350 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 44 | $18.00 | $33.00 |
| 0360 | Flat sheet, type XI, size determined by MSG, overhead (6510108) | SF | 23 | $47.85 | $52.00 |
| 0370 | F&I mounting assembly for F.S. sign erctd on mast arm (6513020) | EACH | 3 | $500.00 | $715.00 |
| 0380 | U-section post for sign supports - 3P (6531210) | LF | 40 | $14.00 | $19.00 |
| 0390 | Furnish & install 1.0" schedule 80 PVC conduit (6750275) | LF | 1,320 | $17.50 | $17.25 |
| 0400 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 1,620 | $18.00 | $18.00 |
| 0410 | Furnish & install 3.0" schedule 80 PVC conduit (675027C) | LF | 423 | $78.00 | $23.75 |
| 0420 | Furnish & install 2.0" SCHD 80 PVC conduit (direction.bored) (675027S) | LF | 300 | $35.00 | $43.00 |
| 0430 | Furnish additional conduit within directional bore (675027Z) | LF | 893 | $6.48 | $12.00 |
| 0440 | Furnish & install 2" schedule 80 HDPE conduit (directional bored) (6760065) | LF | 183 | $35.00 | $43.00 |
| 0450 | Furnish & install no. 14 copper wire, 4 conductor - black (6770388) | LF | 910 | $5.11 | $6.00 |
| 0460 | Furnish & install no. 14 copper wire, 4 conductor - gray (6770389) | LF | 2,402 | $5.21 | $6.25 |
| 0470 | Furnish & install no. 14 copper wire, 8 conductor (black) (6770393) | LF | 3,797 | $5.40 | $6.25 |
| 0480 | Furnish & install no. 14 copper wire, 8 conductor (gray) (6770394) | LF | 1,304 | $5.70 | $6.35 |
| 0490 | Furnish & instl no. 14 copper wire,1-conductor for loop wire (6770413) | LF | 3,492 | $1.15 | $1.50 |
| 0500 | Sawcut for loop detector (6780495) | LF | 1,338 | $9.61 | $11.25 |
| 0510 | Furnish & install electrical service for traffic signal (6800499) | EACH | 2 | $3,000.00 | $1,425.00 |
| 0520 | F&I-13"X24"X18"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (6800518) | EACH | 7 | $831.17 | $830.00 |
| 0530 | F&I-17"X30"X24"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (680052C) | EACH | 9 | $1,051.00 | $1,185.00 |
| 0540 | Furnish & install 10' break- away alum pedestal pole and base (6825484) | EACH | 7 | $1,884.50 | $1,425.00 |
| 0550 | F&I - contr 332/336 cabinet assembly - base mounted 1 (6845511) | EACH | 2 | $23,800 | $26,685 |
| 0560 | Furnish & install -12" 4 (6865720) | EACH | 4 | $1,500.00 | $1,425.00 |
| 0570 | Furnish & install - 12" 3 (6865723) | EACH | 14 | $1,300.00 | $1,125.00 |
| 0580 | F&I - countdown pedestrian signal head (6865781) | EACH | 8 | $948.30 | $890.00 |
| 0590 | F&I - 1-way-1SECT.(countdown hand/man emblem)ped.sig.head (6865783) | EACH | 8 | $948.30 | $1,125.00 |
| 0600 | F&I-ped push but.solid state W/ tone assem 9"X15"&sign (R- 10-3E or R10-4A) (6865797) | EACH | 16 | $622.20 | $625.00 |
| 0610 | Furnish & install internally illuminated street name sign, including mast arm mounting (6865823) | EACH | 10 | $8,600.00 | $5,930.00 |
| 0620 | F&I vehicle traffic singal head mounting assembly for mast arm (6865831) | EACH | 8 | $621.08 | $705.00 |
| 0630 | Backplate W/ retrorefl.borders for traff. sig. (6865834) | EACH | 18 | $330.60 | $355.00 |
| 0640 | Removal,salvage,&disp.of existing traf. signal equipment (6885990) | LS | 1 | $2,590.02 | $11,265 |
| 0650 | Temporary adjustment of traffic signal equipment (6885993) | EACH | 2 | $10,500 | $17,785 |
| 0660 | Furnish & install concrete cabinet foundation (6887951) | EACH | 2 | $1,479.00 | $1,425.00 |
| 0670 | Design mast arm foundation (6888163) | EACH | 4 | $3,000.00 | $17,800 |
| 0680 | Powdercoating per mast arm over base (6888166) | EACH | 4 | $2,600.00 | $4,750.00 |
| 0690 | Powdercoating per mast arm over galvanized (6888167) | EACH | 2 | $2,600.00 | $4,150.00 |
| 0700 | Decorative option per mast arm (6888168) | EACH | 6 | $2,600.00 | $5,335.00 |
| 0710 | Design,furnish,install steel pole W/ mast arm W/O foundation (6888172) | EACH | 4 | $25,000 | $77,000 |
| 0720 | Install foundation for mast arm including concrete and rebar (6888174) | CY | 50 | $1,750.00 | $300.00 |
| 0730 | Design, furnish & install steel pole with twin mast arms including foundation 1 (6888177) | EACH | 2 | $45,000 | $95,000 |
| 0740 | Powdercoating option for 10' aluminum pedestal pole (6888194) | EACH | 7 | $440.00 | $890.00 |
| 0750 | Concrete sidewalk(4" uniform) (7204100) | SY | 9,717 | $74.05 | $75.00 |
| 0760 | Concrete sidewalk(6" uniform) (7204600) | SY | 1,468 | $176.25 | $110.00 |
| 0770 | Detectable warning material (7204900) | SF | 994 | $43.50 | $45.00 |
| 0780 | Concrete median (7206000) | SY | 20 | $311.75 | $110.00 |
| 0790 | Pedestrian ramp construction (7209000) | SY | 658 | $167.35 | $125.00 |
| 0791 | Reset chain-link fence (8072000) | LF | 321 | $50.00 | $40.00 |
| 0792 | Moving item no. P032341 - 01 (8081000) | LS | 1 | $6,000.00 | $6,050.00 |
| 0793 | Moving item no. P032341 - 02 (8081000) | LS | 1 | $1,000.00 | $325.00 |
| 0794 | Moving item no. P032341 - 03 (8081000) | LS | 1 | $2,500.00 | $890.00 |
| 0795 | Moving item no. P032341 - 04 (8081000) | LS | 1 | $2,500.00 | $4,625.00 |
| 0796 | Moving item no. P032341 - 05 (8081000) | LS | 1 | $2,500.00 | $890.00 |
| 0797 | Moving item no. P032341 - 06 (8081000) | LS | 1 | $2,500.00 | $665.00 |
| 0798 | Moving item no. P032341 - 07 (8081000) | LS | 1 | $2,500.00 | $2,450.00 |
| 0799 | Moving item no. P032341 - 08 (8081000) | LS | 1 | $1,500.00 | $1,185.00 |
| 0800 | Right of way marker(rebar and cap) (8091010) | EACH | 173 | $40.00 | $300.00 |
| 0801 | Moving item no. P032341 - 09 (8081000) | LS | 1 | $500.00 | $400.00 |
| 0802 | Moving item no. P032341 - 10 (8081000) | LS | 1 | $1,000.00 | $1,150.00 |
| 0803 | Moving item no. P032341 - 11 (8081000) | LS | 1 | $1,000.00 | $1,190.00 |
| 0804 | Moving item no. P032341 - 12 (8081000) | LS | 1 | $9,000.00 | $3,500.00 |
| 0805 | Moving item no. P032341 - 13 (8081000) | LS | 1 | $3,000.00 | $1,275.00 |
| 0806 | Moving item no. P032341 - 14 (8081000) | LS | 1 | $5,000.00 | $7,425.00 |
| 0807 | Moving item no. P032341 - 15 (8081000) | LS | 1 | $500.00 | $300.00 |
| 0808 | Moving item no. P032341 - 16 (8081000) | LS | 1 | $500.00 | $275.00 |
| 0809 | Moving item no. P032341 - 17 (8081000) | LS | 1 | $2,500.00 | $550.00 |
| 0810 | Right of way plat (8091050) | LS | 1 | $7,500.00 | $4,750.00 |
| 0811 | Moving item no. P032341 - 18 (8081000) | LS | 1 | $25,000 | $3,000.00 |
| 0812 | Moving item no. P032341 - 19 (8081000) | LS | 1 | $500.00 | $550.00 |
| 0813 | Moving item no. P032341 - 20 (8081000) | LS | 1 | $4,000.00 | $1,350.00 |
| 0814 | Moving item no. P032341 - 21 (8081000) | LS | 1 | $1,000.00 | $550.00 |
| 0815 | Moving item no. P032341 - 22 (8081000) | LS | 1 | $2,500.00 | $850.00 |
| 0816 | Moving item no. P032341 - 23 (8081000) | LS | 1 | $500.00 | $525.00 |
| 0817 | Moving item no. P032341 - 24 (8081000) | LS | 1 | $500.00 | $250.00 |
| 0818 | Moving item no. P032341 - 25 (8081000) | LS | 1 | $6,000.00 | $890.00 |
| 0819 | Moving item no. P032383 - 01 (8081000) | LS | 1 | $1,050.00 | $350.00 |
| 0820 | Permanent cover (8100100) | ACRE | 1.56 | $1,476.76 | $2,850.00 |
| 0821 | Moving item no. P032383 - 02 (8081000) | LS | 1 | $1,050.00 | $750.00 |
| 0830 | Temporary cover (8100200) | ACRE | 0.78 | $932.25 | $2,600.00 |
| 0840 | Compost (8101105) | CY | 42 | $65.95 | $100.00 |
| 0850 | Fertilizer (nitrogen) (8104005) | LB | 156 | $1.94 | $2.50 |
| 0860 | Fertilizer (phosphoric acid) (8104010) | LB | 156 | $1.94 | $2.50 |
| 0870 | Fertilizer (potash) (8104015) | LB | 156 | $1.94 | $2.50 |
| 0880 | Agricultural granular lime (8105005) | LB | 3,120 | $0.94 | $0.40 |
| 0890 | Selective watering (8109050) | GAL | 108,600 | $0.10 | $0.15 |
| 0900 | Mowing (8109901) | ACRE | 4.68 | $433.00 | $650.00 |
| 0910 | Inlet structure filter - type F (weighted) (8152004) | LF | 560 | $10.50 | $15.00 |
| 0920 | Silt fence (8153000) | LF | 3,000 | $3.44 | $5.50 |
| 0930 | Stabilized construction entrance (8156490) | SY | 1,100 | $29.00 | $8.00 |
| 0940 | Bus shelter (5'X16') (8990053) | EACH | 3 | $29,500 | $42,000 |
| 0950 | Imprinted asphalt (8990064) | SY | 959 | $198.00 | $239.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of November 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.