TDOT contract CNZ225 bid tabulation
The ada curb ramp upgrades on various state routes. Let by Tennessee DOT on August 15, 2025, Counties Anderson, Cocke, Jefferson, Knox, And Sevier. 2 bids received; low bid $1,727,720 by Southern Constructors, Inc..
- Owner
- Tennessee DOT
- Letting
- 15 AUG 2025
- Pay items
- 13
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Southern Constructors, Inc. | $1,727,720 | Low |
| 2 | APAC-Atlantic, Inc. | $2,764,256 | +60% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Southern Constructors, Inc. | 2. APAC-Atlantic, Inc. |
|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $80,000 | $34,000 |
| 2 | Removal of trash and debris (202-01.03) | LS | 1 | $40,000 | $65,000 |
| 3 | Removal of rigid pavement, sidewalk, etc. (202-03) | SY | 352 | $22.00 | $80.00 |
| 4 | Removal of curb and gutter (description) (202-08.15) | LF | 3,052 | $13.00 | $35.00 |
| 5 | Furnishing & spreading topsoil (203-07) | CY | 115 | $68.00 | $300.00 |
| 6 | Concrete sidewalk (4 ") (701-01.01) | SF | 3,168 | $22.00 | $28.50 |
| 7 | Concrete curb ramp (retrofit) (701-02.01) | SF | 20,144 | $36.00 | $62.00 |
| 8 | Detectable warning surface (rehabilitation) (701-02.06) | SF | 2,036 | $50.00 | $70.00 |
| 9 | Concrete curb (702-01) | CY | 40 | $1,600.00 | $1,590.00 |
| 10 | Concrete combined curb & gutter (702-03) | CY | 92 | $1,000.00 | $1,770.00 |
| 11 | Traffic control (712-01) | LS | 1 | $300,000 | $520,000 |
| 12 | Mobilization (717-01) | LS | 1 | $195,000 | $264,000 |
| 13 | Seeding (with mulch) (801-01) | UNIT | 12 | $400.00 | $300.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.