TxDOT contract A00127774 bid tabulation
Install/Rehabilitate Its, IH 37 (AT INTERS. IH37/SH 286 to 1.7 MI S OF SH358/IH37 INTERCHANGE). Let by Texas DOT on February 4, 2026, Nueces, Corpus Christi District. 6 bids received; low bid $3,168,237 by Traf-Tex, Inc., +8.1% against the engineer's estimate of $2,930,686.
- Owner
- Texas DOT
- Letting
- 04 FEB 2026
- Pay items
- 40
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Traf-Tex, Inc. | $3,168,237 | Low | +8.0% |
| 2 | Third Coast Services LLC | $3,305,561 | +4.0% | +13% |
| 3 | Creacom, Inc. | $3,887,822 | +23% | +33% |
| 4 | The Levy Company, Inc. | $4,605,891 | +45% | +57% |
| 5 | Light It Up Electric | $4,920,602 | +55% | +68% |
| 6 | Austin Traffic Signal Construction Co., Inc. | $5,881,134 | +86% | +101% |
Engineer's estimate: $2,930,686.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Traf-Tex, Inc. | 2. Third Coast Services LLC | 3. Creacom, Inc. | 4. The Levy Company, Inc. | 5. Light It Up Electric | 6. Austin Traffic Signal Construction Co., Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Drilled shaft (42 in) (416-7007) | LF | 96 | $665.82 | $484.50 | $395.48 | $776.28 | $780.00 | $630.00 | $750.00 |
| 2 | Drilled shaft (sign mounts) (54 in) (416-7033) | LF | 70 | $932.15 | $688.50 | $967.37 | $1,049.86 | $1,000.00 | $875.00 | $950.00 |
| 3 | Riprap (concrete)(4 in) (432-7001) | CY | 5 | $601.79 | $1,455.00 | $1,872.65 | $945.35 | $620.00 | $800.00 | $1,100.00 |
| 4 | Riprap (mow strip)(6 in) (432-7015) | CY | 80 | $677.60 | $589.00 | $742.89 | $1,466.83 | $910.00 | $1,200.00 | $750.00 |
| 5 | Mobilization (500-7001) | LS | 1 | $216,000 | $155,917 | $330,556 | $272,158 | $460,589 | $400,000 | $350,000 |
| 6 | Barricades, signs and traffic handling (502-7001) | MO | 11 | $6,500.00 | $2,749.50 | $2,820.20 | $8,802.87 | $12,400 | $10,000 | $12,500 |
| 7 | TMA (stationary) (505-7001) | DAY | 120 | $182.83 | $210.00 | $538.14 | $2,041.44 | $56.00 | $225.00 | $650.00 |
| 8 | Metal W-beam guard fence (timber post) (540-7001) | LF | 450 | $27.94 | $34.11 | $36.09 | $64.99 | $26.00 | $36.00 | $35.00 |
| 9 | Downstream anchor terminal section (540-7015) | EACH | 4 | $1,612.00 | $1,732.80 | $1,775.79 | $2,363.38 | $1,300.00 | $1,700.00 | $1,960.00 |
| 10 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,630.66 | $4,107.80 | $4,353.56 | $5,794.10 | $3,500.00 | $4,375.00 | $4,855.00 |
| 11 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 530 | $15.54 | $11.60 | $13.18 | $12.94 | $13.00 | $12.00 | $10.00 |
| 12 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 2,005 | $18.24 | $16.30 | $14.31 | $11.78 | $24.00 | $31.00 | $31.00 |
| 13 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 20,000 | $17.77 | $14.70 | $14.18 | $8.63 | $18.00 | $18.00 | $12.00 |
| 14 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 48,815 | $20.00 | $20.15 | $15.38 | $10.63 | $30.00 | $36.00 | $41.00 |
| 15 | ITS multi-duct CND (PVC-40)(steel encse) (619-7004) | LF | 1,305 | $62.98 | $60.60 | $64.57 | $163.85 | $150.00 | $200.00 | $72.00 |
| 16 | Fiber optic cable road marker (619-7014) | EACH | 140 | $125.00 | $157.50 | $121.96 | $187.52 | $140.00 | $150.00 | $155.00 |
| 17 | Electrical conductor (no.14) insulated (620-7002) | LF | 39,155 | $0.96 | $0.87 | $1.21 | $0.52 | $0.90 | $1.20 | $1.30 |
| 18 | Electrical conductor (no.4) insulated (620-7012) | LF | 3,135 | $3.34 | $3.40 | $4.56 | $3.40 | $3.35 | $3.35 | $2.50 |
| 19 | Electrical conductor (no.2) insulated (620-7016) | LF | 9,335 | $4.47 | $6.50 | $7.51 | $5.38 | $4.95 | $4.60 | $4.50 |
| 20 | ITS GND box(pcast) type 1 (243636) (623-7001) | EACH | 125 | $3.02 | $3,645.00 | $4,071.56 | $5,729.76 | $4,900.00 | $4,600.00 | $9,250.00 |
| 21 | ITS GND box(pcast) type 2 (366036) (623-7007) | EACH | 15 | $3.28 | $5,526.00 | $6,936.34 | $10,229 | $8,100.00 | $8,300.00 | $10,200 |
| 22 | Remove ITS ground box (623-7041) | EACH | 1 | $1,215.41 | $800.00 | $836.98 | $2,906.57 | $2,200.00 | $1,200.00 | $750.00 |
| 23 | Ground box type D (162922)W/apron (624-7008) | EACH | 20 | $1,786.83 | $1,025.00 | $1,390.62 | $1,390.25 | $1,600.00 | $1,400.00 | $1,500.00 |
| 24 | Elc SRV type D 120/240 060(NS)SS(N)GC(O) (628-7152) | EACH | 5 | $11,277 | $7,200.00 | $7,832.79 | $10,407 | $8,300.00 | $10,300 | $7,500.00 |
| 25 | Install overhead sign support(30 FT bal tee) (650-7028) | EACH | 2 | $52,904 | $36,465 | $45,070 | $58,763 | $52,600 | $47,000 | $62,500 |
| 26 | Install DMS (pole MTD cabinet) (6004-7001) | EACH | 2 | $17,000 | $12,930 | $5,772.82 | $11,338 | $13,900 | $13,000 | $12,500 |
| 27 | Bbu system (external battery cabinet) (6007-7001) | EACH | 2 | $10,500 | $8,816.00 | $7,654.23 | $9,185.54 | $8,000.00 | $10,250 | $9,850.00 |
| 28 | System integration (6009-7001) | LS | 1 | $24,500 | $25,840 | $2,886.43 | $211,773 | $17,000 | $20,000 | $30,000 |
| 29 | ITS pole MNT cab (type 2)(conf 2) (6011-7002) | EACH | 4 | $8,745.00 | $7,237.80 | $7,337.04 | $8,026.60 | $6,100.00 | $8,200.00 | $9,400.00 |
| 30 | ITS pole (55 FT)(130 MPH) (6011-7007) | EACH | 4 | $23,768 | $18,828 | $22,870 | $29,571 | $25,600 | $22,000 | $28,500 |
| 31 | CCTV field equip (digital) (install only) (6018-7001) | EACH | 4 | $1,211.70 | $1,771.00 | $1,097.19 | $741.35 | $1,800.00 | $800.00 | $1,500.00 |
| 32 | Install of ethernet surge protect (6023-7003) | EACH | 15 | $1,000.00 | $326.50 | $246.45 | $266.80 | $62.00 | $900.00 | $500.00 |
| 33 | Fiber optic CBL (single-mode)(12 fiber) (6027-7001) | LF | 3,925 | $1.96 | $6.91 | $2.54 | $3.61 | $4.90 | $4.00 | $3.10 |
| 34 | Fiber optic patch panel (12 position) (6027-7005) | EACH | 15 | $1,777.69 | $529.62 | $1,558.55 | $1,178.95 | $1,300.00 | $1,200.00 | $2,850.00 |
| 35 | Fiber optic CBL(single-mode)(144 fiber) (6027-7006) | LF | 67,560 | $3.07 | $3.60 | $3.29 | $3.10 | $4.05 | $4.80 | $5.50 |
| 36 | Fiber optic patch panel (144 positions) (6027-7008) | EACH | 5 | $4,299.99 | $3,951.00 | $4,850.11 | $5,740.42 | $10,400 | $2,500.00 | $17,500 |
| 37 | FO splice enclosure (type 3) (6027-7010) | EACH | 26 | $2,033.79 | $1,459.80 | $4,496.01 | $1,725.23 | $1,750.00 | $1,800.00 | $7,800.00 |
| 38 | Ethernet switch (install only) (6036-7001) | EACH | 17 | $1,001.98 | $803.70 | $203.89 | $571.39 | $380.00 | $800.00 | $250.00 |
| 39 | ITS system support equipment (6037-7001) | LS | 1 | $25,381 | $5,886.00 | $4,616.52 | $46,796 | $1.00 | $8,000.00 | $50,500 |
| 40 | ITS GRND MNT cab (type 6)(conf 2) (6050-7009) | EACH | 2 | $23,900 | $18,107 | $13,278 | $23,567 | $18,400 | $18,000 | $14,750 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 4, 2026. Compiled by Mirage Metrics.