TxDOT contract A00129662 bid tabulation
Preventive Maintenance, IH 2 (FM 2557 to FM 1423). Let by Texas DOT on September 5, 2025, Hidalgo, Pharr District. 3 bids received; low bid $10,273,483 by Ioc Company LLC, -15% against the engineer's estimate of $12,098,637.
- Owner
- Texas DOT
- Letting
- 05 SEP 2025
- Pay items
- 70
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ioc Company LLC | $10,273,483 | Low | -15% |
| 2 | Foremost Paving, Inc. | $10,815,550 | +5.0% | -11% |
| 3 | Posillico Civil, Inc. | $11,951,074 | +16% | -1.0% |
Engineer's estimate: $12,098,637.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ioc Company LLC | 2. Foremost Paving, Inc. | 3. Posillico Civil, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7005) | LF | 865 | $15.00 | $11.00 | $14.00 | |
| 2 | Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009) | TON | 29,369 | $145.00 | $137.00 | $140.00 | |
| 3 | Stone-MTRX-asphalt SMA-F sac-A PG76-22 (346-7017) | TON | 33,059 | $140.00 | $125.00 | $120.00 | $140.00 |
| 4 | Flexible pavement structure repair(12") (351-7011) | SY | 3,893 | $25.00 | $67.00 | $20.84 | |
| 5 | Planing asphalt concrete pavement(2") (354-7051) | SY | 547,608 | $2.50 | $1.00 | $2.15 | $1.22 |
| 6 | Riprap (mow strip)(4 in) (432-7013) | CY | 126 | $500.00 | $595.00 | $484.00 | $485.00 |
| 7 | Mobilization (500-7001) | LS | 1 | $500,000 | $140,000 | $246,000 | $1,086,461 |
| 8 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $5,000.00 | $3,600.00 | $3,700.00 | $15,000 |
| 9 | TMA (stationary) (505-7001) | DAY | 180 | $100.00 | $0.10 | $161.00 | $68.79 |
| 10 | TMA (mobile operation) (505-7003) | DAY | 180 | $150.00 | $1.00 | $0.01 | $68.79 |
| 11 | Biodegradable erosion control logs (install) (6") (506-7042) | LF | 876 | $3.00 | $5.80 | $4.72 | |
| 12 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 3,264 | $7.00 | $3.00 | $5.90 | $4.72 |
| 13 | Biodegradable erosion control logs (remove) (506-7046) | LF | 4,140 | $1.00 | $0.75 | $1.30 | $4.72 |
| 14 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,781 | $30.00 | $28.32 | $28.70 | $28.32 |
| 15 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 20 | $2,250.00 | $2,084.00 | $2,104.90 | $2,084.00 |
| 16 | Downstream anchor terminal section (540-7015) | EACH | 6 | $1,483.00 | $1,497.90 | $1,483.00 | |
| 17 | Connector plate for thrie beam (540-7030) | EACH | 7 | $1,300.00 | $1,186.00 | $1,197.90 | $1,186.00 |
| 18 | Remove metal beam guard fence (542-7001) | LF | 1,656 | $3.00 | $4.50 | $4.60 | $4.50 |
| 19 | Remove terminal anchor section (542-7002) | EACH | 6 | $250.00 | $252.50 | $250.00 | |
| 20 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 18 | $350.00 | $250.00 | $252.50 | $250.00 |
| 21 | Guardrail end treatment (install) (544-7001) | EACH | 14 | $3,400.00 | $3,451.00 | $3,485.60 | $3,451.00 |
| 22 | Guardrail end treatment (remove) (544-7003) | EACH | 14 | $250.00 | $250.00 | $252.50 | $250.00 |
| 23 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 4 | $1,250.00 | $1,262.50 | $1,250.00 | |
| 24 | Crash cushion attenuator (remove) (545-7004) | EACH | 1 | $1,250.00 | $1,262.50 | $1,250.00 | |
| 25 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 1 | $8,450.00 | $8,534.50 | $8,450.00 | |
| 26 | Install delineator assembly (D-SW)SZ 1(WFLX)SRF (658-7006) | EACH | 44 | $125.00 | $126.30 | $125.00 | |
| 27 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BR) (658-7014) | EACH | 562 | $25.00 | $15.00 | $15.20 | $15.00 |
| 28 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 40 | $25.00 | $25.30 | $25.00 | |
| 29 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 175 | $15.00 | $15.20 | $15.00 | |
| 30 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BR) (658-7033) | EACH | 415 | $20.00 | $15.00 | $15.20 | $15.00 |
| 31 | Remove delin & object marker assms (658-7078) | EACH | 964 | $10.00 | $10.10 | $10.00 | |
| 32 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 24,737 | $1.00 | $1.12 | $1.10 | $0.65 |
| 33 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 4,462 | $1.00 | $1.40 | $1.10 | $0.65 |
| 34 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 18,890 | $1.25 | $0.88 | $0.90 | $0.88 |
| 35 | Reflectorized pavement marking type I (W)12"(lane drop)(100MIL) (666-7027) | LF | 27,280 | $4.00 | $0.94 | $1.00 | $0.94 |
| 36 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 6,166 | $1.10 | $1.20 | $1.10 | |
| 37 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 12,694 | $0.35 | $0.42 | $0.50 | $0.42 |
| 38 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 3,081 | $0.60 | $0.54 | $0.60 | $0.54 |
| 39 | Reflectorized pavement marking type II (W) 12" (lane drop) (666-7181) | LF | 6,230 | $1.50 | $0.78 | $0.80 | $0.78 |
| 40 | Reflectorized pavement marking type II (W) 12" (solid) (666-7182) | LF | 6,902 | $2.00 | $0.78 | $0.80 | $0.78 |
| 41 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 4,388 | $0.42 | $0.50 | $0.42 | |
| 42 | Reflectorized pavement marking type III (W)(6")(solid) (666-7236) | LF | 27,000 | $2.50 | $1.75 | $1.80 | $1.75 |
| 43 | Reflectorized pavement marking type III (W)(6")(broken) (666-7237) | LF | 8,346 | $3.00 | $1.95 | $2.00 | $1.95 |
| 44 | Reflectorized pavement marking type III (W)(8")(solid) (666-7239) | LF | 6,906 | $3.75 | $3.80 | $3.75 | |
| 45 | Reflectorized pavement marking type III (W)(12")(solid) (666-7242) | LF | 2,076 | $5.50 | $5.60 | $5.50 | |
| 46 | Reflectorized pavement marking type III (W)(12")(DOT) (666-7243) | LF | 745 | $8.00 | $5.50 | $5.60 | $5.50 |
| 47 | Reflectorized pavement marking type III (W)(24")(solid) (666-7244) | LF | 807 | $14.00 | $14.20 | $14.00 | |
| 48 | Reflectorized pavement marking type III (Y)(6")(solid) (666-7248) | LF | 24,545 | $2.50 | $1.75 | $1.80 | $1.75 |
| 49 | Reflectorized pavement marking type III (Y)(24")(solid) (666-7253) | LF | 2,060 | $14.00 | $14.20 | $14.00 | |
| 50 | Reflectorized pavement marking type III (W)(arrow) (666-7254) | EACH | 11 | $300.00 | $303.00 | $300.00 | |
| 51 | Reflectorized pavement marking type III (W)(double arrow) (666-7255) | EACH | 3 | $425.00 | $429.30 | $425.00 | |
| 52 | Reflectorized pavement marking type III (W)(word) (666-7257) | EACH | 11 | $350.00 | $353.50 | $350.00 | |
| 53 | Reflectorized pavement marking type III (W)(number) (666-7258) | EACH | 2 | $800.00 | $808.00 | $800.00 | |
| 54 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 35,170 | $0.65 | $0.72 | $0.80 | $0.72 |
| 55 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 87,357 | $0.65 | $0.68 | $0.70 | $0.68 |
| 56 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 77,910 | $0.65 | $0.68 | $0.70 | $0.68 |
| 57 | Prefabricated PM type B (W)(6")(broken)contrast (668-7012) | LF | 7,538 | $11.50 | $11.70 | $11.50 | |
| 58 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 31 | $250.00 | $150.00 | $151.50 | $150.00 |
| 59 | Prefabricated PM type C (W)(number) (668-7102) | EACH | 15 | $250.00 | $345.00 | $348.50 | $345.00 |
| 60 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 31 | $270.00 | $250.00 | $252.50 | $250.00 |
| 61 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 5,025 | $3.00 | $7.50 | $7.60 | $7.50 |
| 62 | Eliminating existing PM & markers (4") (677-7001) | LF | 59,991 | $0.65 | $0.40 | $0.50 | $0.40 |
| 63 | Eliminating existing PM & markers (8") (677-7004) | LF | 6,906 | $0.60 | $0.70 | $0.60 | |
| 64 | Eliminating existing PM & markers (12") (677-7006) | LF | 2,821 | $2.00 | $1.00 | $1.10 | $1.00 |
| 65 | Eliminating existing PM & markers (24") (677-7008) | LF | 2,867 | $3.50 | $3.60 | $3.50 | |
| 66 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 13 | $95.00 | $96.00 | $95.00 | |
| 67 | Eliminating existing PM & markers (double arrow) (677-7010) | EACH | 3 | $150.00 | $151.50 | $150.00 | |
| 68 | Eliminating existing PM & markers (number) (677-7014) | EACH | 2 | $95.00 | $96.00 | $95.00 | |
| 69 | Eliminating existing PM & markers (word) (677-7015) | EACH | 13 | $95.00 | $96.00 | $95.00 | |
| 70 | Bonding course (3007-7001) | GAL | 38,334 | $4.50 | $3.00 | $2.78 | $7.09 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 5, 2025. Compiled by Mirage Metrics.