TxDOT contract A00129803 bid tabulation

Surfacing/Roadway Restoration, SH 332 (FM 523 to End of Maintenance). Let by Texas DOT on June 5, 2025, Brazoria, Houston District. 5 bids received; low bid $2,104,777 by Durwood Greene Construction Co., -12% against the engineer's estimate of $2,384,508.

Owner
Texas DOT
Letting
05 JUN 2025
Pay items
58
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Durwood Greene Construction Co.$2,104,777Low-12%
2Elite Kings Construction, LLC$2,201,117+5.0%-8.0%
3Vulcan Materials Asphalt and Construction, LLC$2,247,344+7.0%-6.0%
4Cornerstone Paving and Construction, L.L.C.$2,298,863+9.0%-4.0%
5Texas Materials Group, Inc.$2,691,325+28%+13%
TxDOT contract A00129803: bids by rank

Engineer's estimate: $2,384,508.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Durwood Greene Construction Co.2. Elite Kings Construction, LLC3. Vulcan Materials Asphalt and Construction, LLC4. Cornerstone Paving and Construction, L.L.C.5. Texas Materials Group, Inc.
1Removing concrete (mowstrip) (104-7005)LF250$30.00$30.00$3.00$36.50$40.00$40.00
2Backfill (type A or B) (134-7004)STA141$200.00$210.00$140.00$205.25$415.00$370.00
3D-GR HMA type D sac-A PG76-22 (341-7057)TON7,506$145.00$130.00$154.00$127.00$135.00$169.00
4Flexible pavement structure repair(3") (351-7002)SY150$100.00$65.00$50.00$81.00$63.00$145.00
5Flexible pavement structure repair(14") (351-7013)SY200$150.00$125.00$5.00$224.00$150.00$264.00
6Plane & text asphalt concrete pavement(1.5") (354-7018)SY69,437$2.50$1.00$3.50$1.35$2.30$3.85
7Riprap (mow strip)(4 in) (432-7013)CY36$1,100.00$1,100.00$3.00$710.00$850.00$1,075.00
8Cleaning and sealing existing joints (438-7001)LF1,200$40.00$57.00$5.00$52.00$52.00$28.00
9Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH14$2,200.00$2,500.00$1,300.00$2,400.00$2,500.00$3,000.00
10Mobilization (500-7001)LS1$213,900$100,000$200,000$198,000$125,000$138,000
11Barricades, signs and traffic handling (502-7001)MO3$10,500$5,000.00$1,500.00$15,900$5,000.00$14,700
12TMA (stationary) (505-7001)DAY96$350.00$350.00$150.00$322.00$125.00$280.00
13TMA (mobile operation) (505-7003)DAY21$300.00$250.00$200.00$336.00$125.00$700.00
14Concrete curb (dowel) (529-7014)LF482$40.00$40.00$30.00$60.00$60.00$53.50
15Mill rumble strips (asphalt) (shoulder) (533-7001)LF28,150$1.05$0.20$2.00$0.13$0.10$0.08
16Mill rumble strips (asphalt) (centerline) (533-7002)LF18,000$0.75$0.20$2.00$0.13$0.10$0.07
17Metal W-beam guard fence (timber post) (540-7001)LF200$30.00$40.00$10.00$35.00$33.75$39.00
18TL-3 31" short radius (complete) (540-7039)EACH1$5,000.00$30,000$15.00$28,000$27,000$31,500
19Remove metal beam guard fence (542-7001)LF200$5.00$4.00$20.00$8.00$3.50$4.00
20Remove terminal anchor section (542-7002)EACH1$300.00$300.00$2,000.00$650.00$250.00$291.00
21Guardrail end treatment (install) (544-7001)EACH3$3,500.00$3,850.00$2,500.00$3,450.00$3,430.00$4,000.00
22Guardrail end treatment (remove) (544-7003)EACH3$275.00$400.00$2,500.00$500.00$350.00$400.00
23Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH54$570.00$830.00$230.00$785.00$927.00$1,050.00
24Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH31$795.00$850.00$400.00$1,050.00$1,098.00$1,300.00
25Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH1$910.00$875.00$400.00$4,500.00$5,882.00$6,800.00
26Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH4$977.00$875.00$400.00$835.00$756.00$850.00
27Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH1$1,138.00$1,250.00$400.00$920.00$808.00$950.00
28Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034)EACH2$1,225.00$1,400.00$400.00$3,100.00$4,211.00$4,900.00
29Install small roadside sign support and assembly TYS80(1)SB(P) (644-7037)EACH2$750.00$1,400.00$400.00$750.00$4,823.00$5,500.00
30Install small roadside sign support and assembly TYS80(1)SB(T) (644-7040)EACH2$754.00$1,400.00$400.00$900.00$1,162.00$1,300.00
31Remove SM RD SN sup&AM (644-7073)EACH95$73.00$160.00$400.00$125.00$78.00$90.00
32Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH110$25.00$25.00$8.00$35.00$19.00$22.00
33Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH14$35.00$50.00$12.00$45.00$25.00$29.00
34Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF1,004$4.50$7.00$1.00$3.00$6.00$7.00
35Work zone pavement marking removing (W)6"(solid) (662-7068)LF61,302$1.00$0.65$1.00$1.25$0.55$0.65
36Work zone pavement marking removing (Y)6"(solid) (662-7100)LF57,656$1.15$0.65$1.00$1.25$0.55$0.65
37Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018)LF262$1.80$3.50$1.00$1.30$2.00$2.30
38Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF2,007$1.50$2.75$1.00$0.95$2.50$2.90
39Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF502$8.22$7.50$1.00$5.70$7.00$8.15
40Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117)LF620$4.00$3.75$1.00$3.10$3.50$4.00
41Reflectorized pavement marking type III (W)(8")(solid) (666-7239)LF470$10.00$3.50$1.00$5.00$3.75$4.50
42Reflectorized pavement marking type III (W)(12")(solid) (666-7242)LF35$15.00$11.00$2.00$10.00$9.00$10.50
43Reflectorized pavement marking type III (Y)(12")(solid) (666-7252)LF1,302$6.50$9.00$1.00$10.00$5.63$6.50
44All-wther PM type I (W)6"(solid)(100MIL) (666-7309)LF28,880$1.20$0.92$1.00$0.90$0.88$1.00
45All-wther PM type I (W)6"(broken)(100MIL) (666-7310)LF25$1.25$0.96$1.00$0.90$0.88$1.00
46All-wther PM type I (Y)6"(solid)(100MIL) (666-7315)LF14,861$0.97$0.92$1.00$0.90$0.88$1.00
47All-wther PM type I (Y)6"(broken)(100MIL) (666-7316)LF2,680$1.53$0.92$1.00$0.90$0.88$1.00
48Prefabricated PM type C (W)(arrow) (668-7091)EACH13$242.50$275.00$1.00$240.00$325.00$375.00
49Prefabricated PM type C (W)(word) (668-7103)EACH14$335.00$325.00$1.00$340.00$356.00$400.00
50Prefabricated PM type C (W)(18")(yld tri) (668-7110)EACH14$45.00$60.00$1.00$40.00$48.00$56.00
51Reflectorized pavement marker type I-C (672-7002)EACH140$7.00$7.00$1.00$6.30$6.50$7.50
52Reflectorized pavement marker type II-A-A (672-7004)EACH1,780$5.62$7.00$1.00$6.30$6.50$7.50
53Fiber reinforced polymer patching materials (721-7001)LB1,801$25.00$20.00$7.00$18.00$18.00$29.00
54Cleaning / sweeping (spot) (738-7104)MI1$5,000.00$4,500.00$100.00$6,265.00$5,500.00$6,300.00
55CNC crack repair (discrete)(surface seal) (780-7004)LF1,200$60.00$36.00$1.00$32.00$32.00$23.00
56Underseal course (3006-7001)GAL22,970$4.50$7.50$5.00$7.30$9.80$4.40
57Mltply PV MK W/wty (W) (6") (solid) (6065-7001)LF10,651$0.85$3.00$1.00$1.00$3.00$3.50
58Mltply PV MK W/wty (Y) (6") (solid) (6065-7004)LF14,312$0.85$3.00$1.00$1.00$3.00$3.50
TxDOT contract A00129803: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of June 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy