TxDOT contract A00140450 bid tabulation

Advanced Traffic Management System, US 290 (Washington County Line to Harris County Line). Let by Texas DOT on April 4, 2025, Waller, Houston District. 3 bids received; low bid $11,686,064 by Allstate Signal & Construction, LLC, -28% against the engineer's estimate of $16,225,543.

Owner
Texas DOT
Letting
04 APR 2025
Pay items
47
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Allstate Signal & Construction, LLC$11,686,064Low-28%
2Third Coast Services LLC$13,219,341+13%-19%
3Sice, Inc.$14,299,429+22%-12%
TxDOT contract A00140450: bids by rank

Engineer's estimate: $16,225,543.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Allstate Signal & Construction, LLC2. Third Coast Services LLC3. Sice, Inc.
1Drilled shaft (42 in) (416-7007)LF360$450.00$384.27$290.03$707.98
2Drilled shaft (sign mounts) (54 in) (416-7033)LF255$700.00$691.78$976.85$1,041.35
3Riprap (mow strip)(4 in) (432-7013)CY136$800.00$586.69$548.97$989.14
4Mobilization (500-7001)LS1$1,180,000$100,000$1,321,934$859,876
5Barricades, signs and traffic handling (502-7001)MO18$16,389$7,994.44$5,177.38$5,541.35
6TMA (stationary) (505-7001)DAY270$285.58$535.00$575.27$367.22
7Temporary sediment control fence (install) (506-7039)LF2,000$4.50$2.50$3.99$2.78
8Temporary sediment control fence (remove) (506-7041)LF2,000$1.00$1.00$1.76$0.62
9Metal W-beam guard fence (timber post) (540-7001)LF4,200$29.00$25.73$13.30$31.04
10Downstream anchor terminal section (540-7015)EACH19$2,000.00$1,522.50$831.04$1,480.60
11Gdrail end TRT(inst)(wood post)(type III) (544-7006)EACH19$3,100.00$3,255.00$886.44$3,608.19
12Conduit (PVC) (schedule 40) (3") (concrete encse) (618-7038)LF163,435$20.00$12.15$11.53$13.34
13Conduit (PVC) (schedule 80) (2") (618-7054)LF11,660$17.00$8.09$7.96$9.05
14Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF5,540$28.00$32.29$38.76$24.65
15Conduit (PVC) (schedule 80) (3") (618-7060)LF2,120$21.00$15.26$9.42$9.92
16Conduit (PVC) (schedule 80) (3") (bore) (618-7061)LF15,580$30.00$24.48$31.14$28.75
17Conduit (RM) (3") (618-7082)LF4,850$70.00$49.87$47.75$112.77
18Conduit (prepare) (618-7090)LF2,320$1.50$1.00$3.52$1.23
19ITS multi-duct CND (PVC-40)(concrete encse) (619-7003)LF163,435$27.00$21.46$18.05$20.02
20ITS multi-duct CND (PVC-80)(bore) (619-7006)LF17,740$45.00$30.94$48.48$29.83
21ITS multi-duct CND (RMC) (619-7008)LF4,850$97.40$91.20$189.34$152.77
22Electrical conductor (no.14) insulated (620-7002)LF122,160$1.00$0.98$1.22$1.48
23Electrical conductor (no.8) bare (620-7007)LF4,475$1.82$2.14$1.62$1.24
24Electrical conductor (no.8) insulated (620-7008)LF9,000$1.88$2.37$1.62$1.41
25Electrical conductor (no.6) bare (620-7009)LF2,260$1.93$2.47$1.96$1.08
26Electrical conductor (no.6) insulated (620-7010)LF6,780$2.50$2.71$2.21$1.87
27Electrical conductor (no.4) bare (620-7011)LF2,500$3.65$3.34$2.49$2.83
28Electrical conductor (no.4) insulated (620-7012)LF5,725$3.96$3.61$2.77$2.56
29ITS GND box(pcast) type 1 (243636)W/aprn (623-7002)EACH180$4,500.00$4,492.00$4,260.99$3,900.79
30Ground box type A (122311) (624-7001)EACH58$1,000.00$720.00$817.92$681.86
31Elc SRV type D 120/240 100(NS)SS(N)SP(O) (628-7259)EACH26$8,000.00$7,045.00$6,239.60$7,647.32
32Install overhead sign support(35 FT bal tee) (650-7035)EACH5$62,000$45,650$54,972$70,347
33Sign walkway (36 in) with HNDRL (654-7004)LF125$400.00$338.00$471.07$597.16
34Install DMS (foundation MTD cabinet) (6004-7002)EACH5$15,000$11,400$4,021.78$13,230
35System integration (6009-7001)LS1$40,000$7,500.00$16,451$44,378
36ITS RVSD system (data collection only) (6010-7002)EACH15$10,000$10,100$12,134$13,697
37ITS pole (55 FT)(110 MPH) (6011-7027)EACH24$22,000$19,631$17,612$24,048
38ITS pole MNTD cab (type 2)(conf 1) (6011-7028)EACH24$5,500.00$6,160.00$7,304.56$4,562.77
39CCTV field equipment (digital) (6018-7002)EACH24$7,000.00$7,425.00$7,248.83$7,555.27
40Fiber optic CBL (single-mode)(12 fiber) (6027-7001)LF75,410$2.57$1.67$2.00$4.56
41Fiber optic fusion splice (6027-7004)EACH2,124$39.54$23.07$80.44$53.00
42Fiber optic patch panel (12 position) (6027-7005)EACH17$1,200.00$3,679.39$2,862.74$2,963.89
43Fiber optic CBL(single-mode)(144 fiber) (6027-7006)LF113,515$4.84$2.29$2.69$5.22
44Fiber optic patch panel (144 positions) (6027-7008)EACH10$3,272.50$4,474.56$3,252.81$13,424
45Fiber optic CBL (single-mode)(6 fiber) (6027-7011)LF48,040$1.58$1.70$1.30$3.74
46ITS GRND MNT cab (type 6)(conf 2) (6050-7009)EACH3$14,500$14,025$15,724$16,783
47Communications hub building (6053-7001)EACH3$35,000$31,750$41,477$39,680
TxDOT contract A00140450: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of April 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy