TxDOT contract A00181046 bid tabulation
Bridge Replacement, LOMA BLANCO RD (Loma Blanca Rd., NBI #: 212140AA0101002 to @ Del Puerto Creek). Let by Texas DOT on January 7, 2025, Starr, Pharr District. 8 bids received; low bid $600,289 by STX Civil, -8.9% against the engineer's estimate of $659,164.
- Owner
- Texas DOT
- Letting
- 07 JAN 2025
- Pay items
- 31
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | STX Civil | $600,289 | Low | -9.0% |
| 2 | Lucania Contractors LLC | $600,406 | 0.0% | -9.0% |
| 3 | RBM Contractors LLC | $681,517 | +14% | +3.0% |
| 4 | Reim Construction, Inc. | $697,037 | +16% | +6.0% |
| 5 | Ioc Company LLC | $890,916 | +48% | +35% |
| 6 | Foremost Paving, Inc. | $906,876 | +51% | +38% |
| 7 | CK Newberry, LLC | $1,028,443 | +71% | +56% |
| 8 | Icos Management, LLC | $1,070,270 | +78% | +62% |
Engineer's estimate: $659,164.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. STX Civil | 2. Lucania Contractors LLC | 3. RBM Contractors LLC | 4. Reim Construction, Inc. | 5. Ioc Company LLC | 6. Foremost Paving, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 8 | $5,000.00 | $6,000.00 | $2,000.00 | $6,650.00 | $1,920.00 | $8,800.00 | $7,500.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 56 | $30.00 | $28.00 | $40.00 | $74.00 | $67.50 | $100.00 | $117.17 |
| 3 | Embankment (final)(DC)(type A) (132-7002) | CY | 562 | $100.00 | $13.00 | $70.00 | $39.14 | $64.50 | $75.00 | $48.38 |
| 4 | FL BS (compacted in place)(type E GR 4)(final pos) (247-7195) | CY | 111 | $40.00 | $110.00 | $300.00 | $76.00 | $145.00 | $175.00 | $209.33 |
| 5 | Cem TRT(PLNT MX) (CL N)(type E)(GR 4) (276-7415) | TON | 5 | $1,000.00 | $500.00 | $2,000.00 | $750.00 | $590.00 | $3,000.00 | $325.54 |
| 6 | Prime coat (MC-30) (310-7004) | GAL | 495 | $15.00 | $15.00 | $15.00 | $16.54 | $7.40 | $75.00 | $13.86 |
| 7 | Asphalt (AC-15P, AC-20-5TR or AC-20XP) (316-7071) | GAL | 755 | $15.00 | $20.00 | $15.00 | $33.00 | $13.00 | $30.00 | $27.61 |
| 8 | Asphalt (AC-15P or AC-10-2TR) (316-7073) | GAL | 849 | $15.00 | $20.00 | $15.00 | $33.00 | $12.50 | $30.00 | $24.99 |
| 9 | Aggregate (type-PD, GR-3)(sac-B) (316-7222) | CY | 19 | $150.00 | $350.00 | $400.00 | $305.00 | $265.00 | $1,000.00 | $121.20 |
| 10 | Aggregate (type-PD, GR-4 or 4S)(sac-B) (316-7225) | CY | 27 | $150.00 | $350.00 | $350.00 | $405.00 | $281.00 | $1,000.00 | $121.20 |
| 11 | Cem stabil BKFL (400-7010) | CY | 55 | $200.00 | $200.00 | $300.00 | $95.00 | $154.00 | $200.00 | $330.00 |
| 12 | Riprap (mow strip)(4 in) (432-7013) | CY | 24 | $750.00 | $650.00 | $650.00 | $780.00 | $1,030.00 | $1,000.00 | $1,045.00 |
| 13 | Rail (type T223) (450-7008) | LF | 28 | $150.00 | $240.00 | $450.00 | $325.00 | $519.00 | $1,500.00 | $660.00 |
| 14 | Concrete box culvert (12 FT X 4 FT) (462-7047) | LF | 60 | $2,000.00 | $2,585.00 | $2,700.00 | $2,895.00 | $2,830.00 | $3,015.92 | $2,420.00 |
| 15 | Wingwall (FW - 0) (HW=7 FT) (466-7149) | EACH | 2 | $16,000 | $22,700 | $20,000 | $37,000 | $26,250 | $40,000 | $52,800 |
| 16 | Set (type I)(S= 12 FT)(HW= 7 FT)(3:1)(C) (467-7276) | EACH | 2 | $30,500 | $30,000 | $25,000 | $36,000 | $35,000 | $71,500 | |
| 17 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 2 | $45,000 | $20,000 | $20,000 | $29,500 | $25,000 | $10,000 | $55,000 |
| 18 | Mobilization (500-7001) | LS | 1 | $30,000 | $45,000 | $50,000 | $32,000 | $95,000 | $90,000 | $75,000 |
| 19 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $20,000 | $2,500.00 | $1,500.00 | $5,800.00 | $700.00 | $2,500.00 | $10,000 |
| 20 | Temporary sediment control fence (install) (506-7039) | LF | 1,266 | $10.00 | $5.00 | $6.00 | $5.15 | $7.50 | $13.00 | $5.50 |
| 21 | Temporary sediment control fence (remove) (506-7041) | LF | 1,266 | $5.00 | $2.00 | $2.00 | $3.00 | $3.00 | $5.00 | $1.10 |
| 22 | Metal W-beam guard fence (timber post) (540-7001) | LF | 100 | $40.00 | $38.00 | $32.00 | $53.51 | $39.50 | $45.50 | $55.00 |
| 23 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,750.00 | $3,425.00 | $2,350.00 | $2,617.11 | $3,590.00 | $2,249.00 | $2,530.00 |
| 24 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,750.00 | $2,290.00 | $1,950.00 | $1,715.66 | $2,400.00 | $1,474.00 | $1,650.00 |
| 25 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,750.00 | $4,285.00 | $3,750.00 | $4,885.27 | $4,760.00 | $4,199.00 | $4,620.00 |
| 26 | Remove SM RD SN sup&AM (644-7073) | EACH | 6 | $400.00 | $678.00 | $250.00 | $11.63 | $648.00 | $9.75 | $275.00 |
| 27 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 8 | $50.00 | $42.00 | $60.00 | $39.43 | $44.00 | $200.00 | $110.00 |
| 28 | Install object marker assembly (OM-2X)(WC)GND (658-7055) | EACH | 2 | $21.00 | $150.00 | $19.72 | $22.00 | $200.00 | $110.00 | |
| 29 | All-wther PM type I (W)6"(solid)(100MIL) (666-7309) | LF | 1,262 | $2.50 | $15.00 | $5.50 | $9.00 | $19.50 | $15.00 | $2.20 |
| 30 | All-wther PM type I (Y)6"(broken)(100MIL) (666-7316) | LF | 632 | $2.50 | $15.00 | $6.25 | $9.00 | $19.50 | $15.00 | $2.20 |
| 31 | Bird exclusion method (5029-7001) | SF | 992 | $15.72 | $11.00 | $1.00 | $10.47 | $9.00 | $1.00 | $9.90 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.