TxDOT contract A00187963 bid tabulation
Rehabilitate Existing Roadway, FM 943 (3.6 MI SOUTH OF POLK COUNTY LINE, SOUTH to FM 1003). Let by Texas DOT on July 1, 2026, Hardin, Beaumont District. 3 bids received; low bid $6,974,719 by Durwood Greene Construction Co., +18% against the engineer's estimate of $5,913,740.
- Owner
- Texas DOT
- Letting
- 01 JUL 2026
- Pay items
- 69
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Durwood Greene Construction Co. | $6,974,719 | Low | +18% |
| 2 | Texas Materials Group, Inc. | $7,235,078 | +4.0% | +22% |
| 3 | Hayden Paving, Inc. | $8,177,812 | +17% | +38% |
Engineer's estimate: $5,913,740.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Durwood Greene Construction Co. | 2. Texas Materials Group, Inc. | 3. Hayden Paving, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 159.82 | $850.00 | $825.00 | $669.00 | $1,000.00 |
| 2 | Embankment (final)(OC)(type C) (132-7005) | CY | 81 | $15.00 | $90.00 | $206.25 | $175.00 |
| 3 | Backfill (type A or B) (134-7004) | STA | 438.72 | $180.00 | $350.00 | $340.00 | $450.00 |
| 4 | Hydro mulch seed (permanent_rural_sandy) (164-7017) | SY | 48,746 | $0.51 | $0.50 | $0.50 | $1.00 |
| 5 | Hydro mulch seed (temporary_warm) (164-7021) | SY | 12,187 | $0.35 | $0.35 | $0.50 | $1.00 |
| 6 | Vegetative watering (168-7001) | TGL | 513 | $5.50 | $25.00 | $13.50 | $140.00 |
| 7 | D-GR HMA type D PG70-22 (341-7048) | TON | 10,884 | $125.00 | $140.00 | $155.75 | $170.00 |
| 8 | Tack coat (341-7082) | GAL | 7,916 | $3.00 | $4.00 | $4.25 | $2.50 |
| 9 | Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009) | TON | 14,513 | $150.00 | $220.00 | $224.00 | $270.00 |
| 10 | Tack coat (346-7028) | GAL | 7,916 | $4.00 | $4.00 | $4.25 | $2.50 |
| 11 | Flexible pavement structure repair(8") (351-7007) | SY | 659 | $137.00 | $97.00 | $166.25 | $85.00 |
| 12 | Plane asphalt pavement (0" to 3.5") (354-7095) | SY | 2,100 | $15.00 | $10.00 | $9.00 | $7.50 |
| 13 | Cut & restoring pavement (400-7006) | SY | 218 | $250.00 | $200.00 | $314.00 | $280.00 |
| 14 | Cem stabil BKFL (400-7010) | CY | 1,071 | $200.00 | $80.00 | $136.25 | $185.00 |
| 15 | Trench excavation protection (402-7001) | LF | 562 | $7.00 | $10.00 | $115.25 | $12.00 |
| 16 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 91 | $200.00 | $265.00 | $146.75 | $275.00 |
| 17 | Headwall (CH - FW - 0) (diameter= 60 in) (466-7013) | EACH | 2 | $9,000.00 | $19,000 | $25,000 | $20,000 |
| 18 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 12 | $1,050.00 | $1,400.00 | $1,200.00 | $1,000.00 |
| 19 | Set (type II) (18 in) (TP) (6: 1) (C) (467-7311) | EACH | 8 | $1,050.00 | $1,400.00 | $1,467.00 | $1,000.00 |
| 20 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 12 | $1,850.00 | $1,800.00 | $2,093.00 | $2,200.00 |
| 21 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 22 | $2,450.00 | $2,000.00 | $1,988.50 | $2,700.00 |
| 22 | Set (type II) (24 in) (TP) (4: 1) (C) (467-7330) | EACH | 2 | $1,850.00 | $1,800.00 | $2,093.00 | $2,200.00 |
| 23 | Set (type II) (24 in) (TP) (6: 1) (P) (467-7332) | EACH | 2 | $2,000.00 | $2,000.00 | $2,930.25 | $2,700.00 |
| 24 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 3 | $3,000.00 | $2,900.00 | $2,616.25 | $3,200.00 |
| 25 | Set (type II) (30 in) (TP) (4: 1) (C) (467-7350) | EACH | 6 | $3,000.00 | $2,900.00 | $3,379.00 | $3,200.00 |
| 26 | Set (type II) (36 in) (RCP) (4: 1) (C) (467-7366) | EACH | 6 | $4,000.00 | $3,200.00 | $3,505.75 | $4,250.00 |
| 27 | Set (type II) (42 in) (RCP) (4: 1) (C) (467-7378) | EACH | 2 | $5,210.00 | $5,500.00 | $7,116.25 | $5,300.00 |
| 28 | Set (type II) (48 in) (RCP) (4: 1) (C) (467-7390) | EACH | 4 | $9,440.00 | $4,200.00 | $7,745.00 | $6,300.00 |
| 29 | Set (type II) (60 in) (RCP) (4: 1) (C) (467-7406) | EACH | 5 | $10,000 | $8,500.00 | $10,465 | $9,500.00 |
| 30 | Set (type II) (48 in) (TP) (4:1) (C) (467-7470) | EACH | 12 | $9,440.00 | $6,000.00 | $7,953.50 | $6,900.00 |
| 31 | Set (type II) (60 in) (TP) (4:1) (C) (467-7471) | EACH | 6 | $10,000 | $8,500.00 | $10,465 | $9,500.00 |
| 32 | Thermoplastic pipe (PP) (18") (468-7001) | LF | 130 | $62.00 | $80.00 | $146.75 | $62.00 |
| 33 | Thermoplastic pipe (PP) (24") (468-7002) | LF | 112 | $140.00 | $120.00 | $162.25 | $150.00 |
| 34 | Thermoplastic pipe (PP) (30") (468-7003) | LF | 156 | $160.00 | $130.00 | $199.00 | $197.00 |
| 35 | Thermoplastic pipe (PP) (48") (468-7006) | LF | 366 | $200.00 | $190.00 | $220.00 | $234.00 |
| 36 | Thermoplastic pipe (PP) (60") (468-7013) | LF | 146 | $250.00 | $320.00 | $366.50 | $304.00 |
| 37 | Removing structure (pipe) (496-7007) | LF | 910 | $46.00 | $80.00 | $31.50 | $68.00 |
| 38 | Mobilization (500-7001) | LS | 1 | $560,000 | $460,000 | $170,000 | $180,000 |
| 39 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $5,000.00 | $7,500.00 | $890.00 | $5,000.00 |
| 40 | Portable changeable message sign (503-7002) | EACH | 2 | $7,000.00 | $12,000 | $15,600 | $8,000.00 |
| 41 | TMA (stationary) (505-7001) | DAY | 113 | $260.00 | $300.00 | $314.00 | $500.00 |
| 42 | TMA (mobile operation) (505-7003) | DAY | 3 | $178.00 | $500.00 | $523.25 | $500.00 |
| 43 | Rock filter dams (install) (type 2) (506-7002) | LF | 320 | $50.00 | $55.00 | $44.50 | $220.00 |
| 44 | Rock filter dams (remove) (506-7011) | LF | 320 | $4.00 | $10.00 | $10.50 | $53.00 |
| 45 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 1,180 | $13.80 | $10.00 | $5.25 | $10.00 |
| 46 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,180 | $2.00 | $1.00 | $1.10 | $1.65 |
| 47 | One-way traffic control (port traffic signal) (510-7003) | MO | 2 | $6,985.00 | $6,700.00 | $4,762.00 | $6,000.00 |
| 48 | Intersections (ACP) (530-7002) | SY | 572 | $40.00 | $55.00 | $175.00 | $105.00 |
| 49 | Driveways (ACP) (530-7010) | SY | 68 | $54.00 | $120.00 | $70.00 | $105.00 |
| 50 | Driveways (base) (530-7015) | SY | 1,003 | $46.00 | $35.00 | $71.50 | $43.00 |
| 51 | Turnouts (ACP) (530-7018) | SY | 805 | $80.00 | $100.00 | $175.00 | $105.00 |
| 52 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 43,872 | $0.22 | $0.24 | $0.19 | $0.20 |
| 53 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 27 | $355.00 | $325.00 | $288.00 | $300.00 |
| 54 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 5 | $400.00 | $360.00 | $288.00 | $325.00 |
| 55 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 12 | $825.00 | $800.00 | $623.00 | $800.00 |
| 56 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 18 | $757.00 | $425.00 | $356.00 | $600.00 |
| 57 | Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012) | EACH | 2 | $830.00 | $1,100.00 | $863.50 | $750.00 |
| 58 | Remove SM RD SN sup&AM (644-7073) | EACH | 20 | $126.00 | $130.00 | $146.75 | $90.00 |
| 59 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 72 | $175.00 | $120.00 | $100.00 | $100.00 |
| 60 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 9,750 | $0.53 | $0.30 | $0.75 | $0.50 |
| 61 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 20,703 | $0.53 | $0.30 | $0.75 | $0.50 |
| 62 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 7,926 | $2.38 | $2.00 | $0.85 | $1.00 |
| 63 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 87,196 | $0.62 | $1.05 | $1.00 | $1.00 |
| 64 | Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419) | LF | 9,750 | $0.58 | $0.65 | $0.74 | $1.00 |
| 65 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 20,703 | $0.58 | $0.65 | $0.74 | $1.00 |
| 66 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 51 | $15.50 | $24.00 | $18.50 | $20.00 |
| 67 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 112 | $51.70 | $50.00 | $57.75 | $32.00 |
| 68 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 760 | $4.60 | $7.00 | $7.00 | $5.50 |
| 69 | Litter removal (734-7001) | ACRE | 32.23 | $16.00 | $500.00 | $184.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2026. Compiled by Mirage Metrics.