TxDOT contract A00189537 bid tabulation

Widen Road - Add Lanes, SH 36 (CR 479 to CR 459). Let by Texas DOT on April 7, 2026, Callahan, Abilene District. 7 bids received; low bid $11,487,762 by Big Creek Construction, LTD., +7.6% against the engineer's estimate of $10,675,511.

Owner
Texas DOT
Letting
07 APR 2026
Pay items
101
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Big Creek Construction, LTD.$11,487,762Low+8.0%
2Foutsco Paving Company, LLC$11,595,676+1.0%+9.0%
3Prater Dirt Work LLC$11,676,770+2.0%+9.0%
4CK Newberry, LLC$11,879,498+3.0%+11%
5J. H. Strain & Sons, Inc.$12,575,871+9.0%+18%
6A. L. Helmcamp, Inc.$12,952,990+13%+21%
7Duininck, Inc.$14,317,083+25%+34%
TxDOT contract A00189537: bids by rank

Engineer's estimate: $10,675,511.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Big Creek Construction, LTD.2. Foutsco Paving Company, LLC3. Prater Dirt Work LLC4. CK Newberry, LLC5. J. H. Strain & Sons, Inc.6. A. L. Helmcamp, Inc.
1Preparing row (100-7002)STA87$750.00$1,500.00$500.00$2,500.00$1,000.00$1,650.00$4,000.00
2Excavation (roadway) (110-7001)CY23,067$13.00$17.00$12.00$12.00$15.00$15.00$22.00
3Embankment (final)(DC)(type A) (132-7002)CY23,404$10.00$27.00$10.00$22.50$15.00$18.00$12.00
4Backfill (type B) (134-7002)STA192$350.00$250.00$100.00$220.00$250.00$275.00$220.00
5Broadcast seed (permanent_rural_sand) (164-7033)ACRE26.26$1,200.00$700.00$700.00$1,270.00$1,200.00$750.00$940.00
6Drill seed (temporary_warm) (164-7045)ACRE13.18$940.00$550.00$250.00$874.00$825.00$575.00$780.00
7Drill seed (temporary_cool) (164-7046)ACRE13.18$940.00$750.00$300.00$928.00$850.00$825.00$780.00
8Vegetative watering (168-7001)TGL1,068.50$10.00$25.00$1.00$24.70$30.00$55.00$20.00
9FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176)CY6,791$60.00$95.00$65.00$60.00$70.00$84.00$62.00
10Prime coat (MC-30) (310-7004)GAL7,639$6.00$6.50$4.25$8.00$7.00$7.00$8.00
11SP mixes SP-B sac-B PG64-22 (344-7002)TON4,440$115.00$130.00$145.00$137.00$135.00$138.53$149.00
12SP mixes SP-C sac-B PG70-22 (344-7021)TON33,507$125.00$130.00$130.00$124.00$130.00$144.03$149.00
13Tack coat (344-7077)GAL28,714$3.00$4.50$6.00$7.50$4.00$5.00$5.50
14Flexible pavement structure repair(4") (351-7003)SY1,000$65.00$35.00$65.00$75.00$75.00$67.00$97.00
15Planing asphalt concrete pavement(1") (354-7050)SY203,124$3.00$1.00$0.50$1.30$0.50$1.00$1.30
16Planing asphalt concrete pavement (1" to 2") (354-7076)SY1,170$3.00$10.00$3.00$6.00$15.00$6.00$6.20
17Temporary special shoring (403-7001)SF5,732$35.00$32.00$15.00$32.20$60.00$120.00$52.00
18Drilled shaft (sign mounts) (24 in) (416-7028)LF32$300.00$240.00$400.00$260.00$390.00$250.00
19Riprap (concrete)(4 in) (432-7001)CY254$200.00$665.00$625.00$690.00$750.00$750.00$850.00
20Riprap (concrete)(5 in) (432-7002)CY33$250.00$670.00$775.00$736.00$750.00$800.00$900.00
21Riprap (mow strip)(4 in) (432-7013)CY328$200.00$645.00$700.00$707.25$675.00$750.00$900.00
22Riprap (stone protection)(12 in) (432-7041)CY357$240.00$160.00$200.00$241.50$175.00$225.00$160.00
23Concrete box culvert (3 FT X 2 FT)(extend) (462-7056)LF18$1,000.00$600.00$400.00$805.00$800.00$830.00$700.00
24Concrete box culvert (3 FT X 3 FT)(extend) (462-7057)LF15$650.00$550.00$1,127.00$900.00$825.00$740.00
25Concrete box culvert (4 FT X 4 FT)(extend) (462-7060)LF11$1,250.00$700.00$685.00$1,541.00$1,150.00$900.00$850.00
26Concrete box culvert (5 FT X 2 FT)(extend) (462-7061)LF5$1,350.00$800.00$900.00$1,587.00$1,050.00$900.00$850.00
27Concrete box culvert (6 FT X 3 FT)(extend) (462-7066)LF136$765.00$1,050.00$555.00$1,265.00$1,250.00$970.00$950.00
28Concrete box culvert (10 FT X 10 FT)(extend) (462-7093)LF72$2,150.00$1,500.00$1,620.00$2,714.00$2,150.00$1,150.00$1,600.00
29RC pipe (CL IV)(18 in) (464-7019)LF48$87.00$154.00$115.00$175.00$145.00$68.00
30RC pipe (CL IV)(24 in) (464-7021)LF32$140.00$106.00$162.00$138.00$270.00$225.00$158.00
31Wingwall (PW - 1) (HW=3 FT) (466-7173)EACH2$12,000$16,750$9,200.00$21,850$25,000$12,000$12,000
32Wingwall (PW - 1) (HW=4 FT) (466-7174)EACH1$18,800$15,000$24,035$24,000$13,000$13,000
33Wingwall (PW - 1) (HW=5 FT) (466-7175)EACH5$22,000$33,200$22,600$54,625$55,000$17,500$26,000
34Wingwall (PW - 1) (HW=7 FT) (466-7177)EACH1$30,000$35,000$80,000$51,750$55,000$30,000$32,000
35Wingwall (PW - 1) (HW=8 FT) (466-7178)EACH1$40,000$50,800$32,200$72,450$85,000$31,000$44,000
36Wingwall (PW - 1) (HW=9 FT) (466-7179)EACH1$5,000.00$57,800$52,000$98,900$100,000$48,000$58,000
37Wingwall (PW - 1) (HW=10 FT) (466-7180)EACH1$55,000$68,000$56,700$103,500$115,000$48,000$61,000
38Wingwall (PW - 1) (HW=11 FT) (466-7181)EACH2$6,000.00$88,300$60,000$149,500$165,000$60,000$91,000
39Wingwall (PW - 2) (HW=5 FT) (466-7189)EACH1$17,000$44,000$25,300$5,405.00$60,000$22,000$32,000
40Wingwall (PW - 2) (HW=11 FT) (466-7195)EACH1$60,000$95,700$1.00$1.00$135,000$60,000$93,000
41Set (type I)(S= 4 FT)(HW= 3 FT)(4:1)(C) (467-7068)EACH3$10,000$8,200.00$4,700.00$7,245.00$8,100.00$11,500$10,000
42Set (type I)(S= 5 FT)(HW= 3 FT)(4:1)(C) (467-7096)EACH1$12,000$8,700.00$6,850.00$7,705.00$8,000.00$11,500$12,500
43Set (type I)(S= 6 FT)(HW= 4 FT)(3:1)(C) (467-7128)EACH5$10,000$6,800.00$8,500.00$10,235$11,000$13,900$18,000
44Set (type I)(S= 6 FT)(HW= 4 FT)(6:1)(C) (467-7130)EACH7$16,000$5,300.00$14,000$7,935.00$10,000$14,700$23,000
45Set (type I)(S= 6 FT)(HW= 5 FT)(4:1)(C) (467-7133)EACH7$15,000$6,350.00$12,588$9,315.00$10,500$14,750$19,000
46Set (type I)(S= 6 FT)(HW= 6 FT)(3:1)(C) (467-7136)EACH5$11,000$8,425.00$9,274.00$11,500$13,000$14,950$22,000
47Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH4$1,325.00$1,700.00$1,667.50$2,200.00$2,500.00$1,100.00
48Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH2$2,000.00$1,700.00$2,200.00$2,300.00$2,700.00$2,750.00$2,600.00
49Clean existing culverts (480-7001)EACH12$6,000.00$2,800.00$1,500.00$3,450.00$3,500.00$3,500.00$2,200.00
50Removing structure (set) (496-7004)EACH8$550.00$1,050.00$1,500.00$230.00$550.00$1,200.00$800.00
51Removing structure (wingwall) (496-7005)EACH20$2,200.00$3,400.00$500.00$1,150.00$1,000.00$1,400.00$1,300.00
52Removing structure (pipe) (496-7007)LF81$50.00$40.00$30.00$23.00$20.00$20.00$52.00
53Mobilization (500-7001)LS1$945,000$1,100,000$545,000$1,030,000$1,150,000$1,075,000$1,145,000
54Barricades, signs and traffic handling (502-7001)MO21$15,000$5,600.00$100,000$7,500.00$10,000$10,000$18,000
55TMA (stationary) (505-7001)DAY222$300.00$350.00$1.00$200.00$350.00$275.00$300.00
56TMA (mobile operation) (505-7003)DAY76$600.00$700.00$1.00$400.00$25.00$325.00$50.00
57Rock filter dams (install) (type 4) (506-7004)LF190$100.00$65.00$89.00$30.00$55.00$125.00$94.00
58Rock filter dams (remove) (506-7011)LF190$15.00$10.00$10.00$20.00$20.00$25.00$16.00
59Temporary sediment control fence (install) (506-7039)LF28,886$4.00$1.00$1.00$4.54$4.00$8.00$4.30
60Temporary sediment control fence (remove) (506-7041)LF28,886$2.00$0.50$0.50$1.23$1.10$2.00$0.85
61Biodegradable erosion control logs (install) (12") (506-7044)LF2,175$7.00$5.50$1.00$7.10$6.50$10.00$6.80
62Biodegradable erosion control logs (remove) (506-7046)LF2,175$2.00$2.00$0.50$1.00$0.75$2.50$1.00
63Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF390$40.00$108.00$250.00$134.00$150.00$145.00$125.00
64Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF1,080$15.00$9.00$35.00$26.00$35.00$27.00$60.00
65Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037)LF390$15.00$9.50$35.00$26.00$55.00$30.00$65.00
66Driveways (ACP) (530-7010)SY1,106$80.00$70.00$85.00$65.00$35.00$70.00$66.00
67Turnouts (rap) (530-7020)SY206$10.00$50.00$200.00$30.00$25.00$45.00$60.00
68Mill rumble strips (asphalt) (shoulder) (533-7001)LF82,285$0.20$0.22$0.15$0.23$0.15$0.25$0.20
69Mill rumble strips (asphalt) (centerline) (533-7002)LF40,327$0.20$0.22$0.15$0.14$0.20$0.25$0.21
70Metal W-beam guard fence (timber post) (540-7001)LF4,275$25.00$32.00$24.00$26.00$25.00$30.00$23.00
71Metal W - beam guard fence (low fill culvert) (540-7018)LF487.50$30.00$110.00$82.00$85.00$100.00$100.00$98.00
72Metal beam guard fence (long span system) (540-7027)EACH4$1,400.00$1,500.00$1,300.00$1,400.00$1,500.00$1,680.00$1,350.00
73Remove metal beam guard fence (542-7001)LF3,950$2.50$3.00$2.50$6.00$2.00$1.20$2.00
74Guardrail end treatment (install) (544-7001)EACH34$3,200.00$3,300.00$3,200.00$3,375.00$3,200.00$4,000.00$3,200.00
75Guardrail end treatment (remove) (544-7003)EACH30$250.00$250.00$250.00$200.00$215.00$240.00$220.00
76Crash cushion attenuator (move & reset) (545-7002)EACH6$1,500.00$2,000.00$1,500.00$1,500.00$1,500.00$1,800.00$1,100.00
77Crash cushion attenuator (stockpile) (545-7003)EACH2$500.00$1,000.00$2,100.00$2,000.00$1,500.00$2,400.00$1,100.00
78Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH2$6,500.00$10,000$9,000.00$10,000$9,200.00$11,000$9,200.00
79Wire fence (type A) (552-7001)LF16$30.00$100.00$150.00$50.00$55.00$100.00$115.00
80Mailbox install-S (TWG-post) type 2 (560-7002)EACH9$350.00$250.00$220.00$550.00$230.00$320.00$230.00
81Aluminum signs (type G) (636-7002)SF65$40.00$30.00$40.00$30.00$45.50$31.00
82Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH50$820.00$750.00$675.00$1,000.00$700.00$815.00$710.00
83Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH5$1,000.00$850.00$775.00$1,500.00$800.00$935.00$820.00
84Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH4$1,200.00$1,100.00$990.00$2,000.00$1,000.00$1,280.00$1,100.00
85Remove SM RD SN sup&AM (644-7073)EACH36$120.00$125.00$100.00$300.00$100.00$150.00$100.00
86Install LRSS (struct steel) (647-7001)LB628.43$9.00$7.80$15.00$8.00$10.35$8.00
87Remove lrsa (647-7003)EACH2$950.00$850.00$1,250.00$900.00$1,320.00$900.00
88Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH90$55.00$50.00$42.00$35.00$50.00$42.00$45.00
89Install object marker assembly (OM-2Y)(WC)GNDLL(BI) (658-7247)EACH52$100.00$85.00$75.00$100.00$75.00$75.00$80.00
90Work zone pavement marking removing (W)24"(solid) (662-7077)LF384$15.00$12.00$8.00$11.50$5.00$5.75$11.00
91Work zone pavement marking removing (Y)6"(solid) (662-7100)LF85,120$0.60$0.35$0.18$0.35$0.25$0.21$0.32
92Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH8,400$2.00$0.75$0.10$1.00$0.60$2.50$0.54
93All-wther PM type I (W)6"(solid)(100MIL) (666-7309)LF82,285$1.30$0.68$0.49$0.66$0.55$0.56$0.65
94All-wther PM type I (W)6"(broken)(100MIL) (666-7310)LF11,460$1.30$0.71$0.49$0.75$0.55$0.56$0.68
95All-wther PM type I (W)6"(DOT)(100MIL) (666-7311)LF1,810$1.30$1.00$0.49$0.98$0.55$0.56$0.89
96All-wther PM type I (Y)6"(solid)(100MIL) (666-7315)LF80,654$1.30$0.68$0.49$0.71$0.55$0.56$0.65
97Prefabricated PM type C (W)(24")(solid) (668-7089)LF120$20.00$15.00$20.00$13.80$20.00$25.00$13.00
98Prefabricated PM type C (W)(LN reduct arrow) (668-7100)EACH10$300.00$1,000.00$550.00$1,035.00$550.00$635.00$950.00
99Reflectorized pavement marker type I-C (672-7002)EACH574$6.00$6.00$5.00$5.81$5.00$5.75$5.30
100Reflectorized pavement marker type II-A-A (672-7004)EACH1,009$7.00$7.00$4.25$6.89$4.50$4.90$6.50
101Eliminating existing PM & markers (6") (677-7002)LF1,320$0.50$1.25$1.00$0.96$1.00$1.50$1.10
TxDOT contract A00189537: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of April 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy