TxDOT contract A00189537 bid tabulation
Widen Road - Add Lanes, SH 36 (CR 479 to CR 459). Let by Texas DOT on April 7, 2026, Callahan, Abilene District. 7 bids received; low bid $11,487,762 by Big Creek Construction, LTD., +7.6% against the engineer's estimate of $10,675,511.
- Owner
- Texas DOT
- Letting
- 07 APR 2026
- Pay items
- 101
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Big Creek Construction, LTD. | $11,487,762 | Low | +8.0% |
| 2 | Foutsco Paving Company, LLC | $11,595,676 | +1.0% | +9.0% |
| 3 | Prater Dirt Work LLC | $11,676,770 | +2.0% | +9.0% |
| 4 | CK Newberry, LLC | $11,879,498 | +3.0% | +11% |
| 5 | J. H. Strain & Sons, Inc. | $12,575,871 | +9.0% | +18% |
| 6 | A. L. Helmcamp, Inc. | $12,952,990 | +13% | +21% |
| 7 | Duininck, Inc. | $14,317,083 | +25% | +34% |
Engineer's estimate: $10,675,511.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Big Creek Construction, LTD. | 2. Foutsco Paving Company, LLC | 3. Prater Dirt Work LLC | 4. CK Newberry, LLC | 5. J. H. Strain & Sons, Inc. | 6. A. L. Helmcamp, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 87 | $750.00 | $1,500.00 | $500.00 | $2,500.00 | $1,000.00 | $1,650.00 | $4,000.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 23,067 | $13.00 | $17.00 | $12.00 | $12.00 | $15.00 | $15.00 | $22.00 |
| 3 | Embankment (final)(DC)(type A) (132-7002) | CY | 23,404 | $10.00 | $27.00 | $10.00 | $22.50 | $15.00 | $18.00 | $12.00 |
| 4 | Backfill (type B) (134-7002) | STA | 192 | $350.00 | $250.00 | $100.00 | $220.00 | $250.00 | $275.00 | $220.00 |
| 5 | Broadcast seed (permanent_rural_sand) (164-7033) | ACRE | 26.26 | $1,200.00 | $700.00 | $700.00 | $1,270.00 | $1,200.00 | $750.00 | $940.00 |
| 6 | Drill seed (temporary_warm) (164-7045) | ACRE | 13.18 | $940.00 | $550.00 | $250.00 | $874.00 | $825.00 | $575.00 | $780.00 |
| 7 | Drill seed (temporary_cool) (164-7046) | ACRE | 13.18 | $940.00 | $750.00 | $300.00 | $928.00 | $850.00 | $825.00 | $780.00 |
| 8 | Vegetative watering (168-7001) | TGL | 1,068.50 | $10.00 | $25.00 | $1.00 | $24.70 | $30.00 | $55.00 | $20.00 |
| 9 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 6,791 | $60.00 | $95.00 | $65.00 | $60.00 | $70.00 | $84.00 | $62.00 |
| 10 | Prime coat (MC-30) (310-7004) | GAL | 7,639 | $6.00 | $6.50 | $4.25 | $8.00 | $7.00 | $7.00 | $8.00 |
| 11 | SP mixes SP-B sac-B PG64-22 (344-7002) | TON | 4,440 | $115.00 | $130.00 | $145.00 | $137.00 | $135.00 | $138.53 | $149.00 |
| 12 | SP mixes SP-C sac-B PG70-22 (344-7021) | TON | 33,507 | $125.00 | $130.00 | $130.00 | $124.00 | $130.00 | $144.03 | $149.00 |
| 13 | Tack coat (344-7077) | GAL | 28,714 | $3.00 | $4.50 | $6.00 | $7.50 | $4.00 | $5.00 | $5.50 |
| 14 | Flexible pavement structure repair(4") (351-7003) | SY | 1,000 | $65.00 | $35.00 | $65.00 | $75.00 | $75.00 | $67.00 | $97.00 |
| 15 | Planing asphalt concrete pavement(1") (354-7050) | SY | 203,124 | $3.00 | $1.00 | $0.50 | $1.30 | $0.50 | $1.00 | $1.30 |
| 16 | Planing asphalt concrete pavement (1" to 2") (354-7076) | SY | 1,170 | $3.00 | $10.00 | $3.00 | $6.00 | $15.00 | $6.00 | $6.20 |
| 17 | Temporary special shoring (403-7001) | SF | 5,732 | $35.00 | $32.00 | $15.00 | $32.20 | $60.00 | $120.00 | $52.00 |
| 18 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 32 | $300.00 | $240.00 | $400.00 | $260.00 | $390.00 | $250.00 | |
| 19 | Riprap (concrete)(4 in) (432-7001) | CY | 254 | $200.00 | $665.00 | $625.00 | $690.00 | $750.00 | $750.00 | $850.00 |
| 20 | Riprap (concrete)(5 in) (432-7002) | CY | 33 | $250.00 | $670.00 | $775.00 | $736.00 | $750.00 | $800.00 | $900.00 |
| 21 | Riprap (mow strip)(4 in) (432-7013) | CY | 328 | $200.00 | $645.00 | $700.00 | $707.25 | $675.00 | $750.00 | $900.00 |
| 22 | Riprap (stone protection)(12 in) (432-7041) | CY | 357 | $240.00 | $160.00 | $200.00 | $241.50 | $175.00 | $225.00 | $160.00 |
| 23 | Concrete box culvert (3 FT X 2 FT)(extend) (462-7056) | LF | 18 | $1,000.00 | $600.00 | $400.00 | $805.00 | $800.00 | $830.00 | $700.00 |
| 24 | Concrete box culvert (3 FT X 3 FT)(extend) (462-7057) | LF | 15 | $650.00 | $550.00 | $1,127.00 | $900.00 | $825.00 | $740.00 | |
| 25 | Concrete box culvert (4 FT X 4 FT)(extend) (462-7060) | LF | 11 | $1,250.00 | $700.00 | $685.00 | $1,541.00 | $1,150.00 | $900.00 | $850.00 |
| 26 | Concrete box culvert (5 FT X 2 FT)(extend) (462-7061) | LF | 5 | $1,350.00 | $800.00 | $900.00 | $1,587.00 | $1,050.00 | $900.00 | $850.00 |
| 27 | Concrete box culvert (6 FT X 3 FT)(extend) (462-7066) | LF | 136 | $765.00 | $1,050.00 | $555.00 | $1,265.00 | $1,250.00 | $970.00 | $950.00 |
| 28 | Concrete box culvert (10 FT X 10 FT)(extend) (462-7093) | LF | 72 | $2,150.00 | $1,500.00 | $1,620.00 | $2,714.00 | $2,150.00 | $1,150.00 | $1,600.00 |
| 29 | RC pipe (CL IV)(18 in) (464-7019) | LF | 48 | $87.00 | $154.00 | $115.00 | $175.00 | $145.00 | $68.00 | |
| 30 | RC pipe (CL IV)(24 in) (464-7021) | LF | 32 | $140.00 | $106.00 | $162.00 | $138.00 | $270.00 | $225.00 | $158.00 |
| 31 | Wingwall (PW - 1) (HW=3 FT) (466-7173) | EACH | 2 | $12,000 | $16,750 | $9,200.00 | $21,850 | $25,000 | $12,000 | $12,000 |
| 32 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 1 | $18,800 | $15,000 | $24,035 | $24,000 | $13,000 | $13,000 | |
| 33 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 5 | $22,000 | $33,200 | $22,600 | $54,625 | $55,000 | $17,500 | $26,000 |
| 34 | Wingwall (PW - 1) (HW=7 FT) (466-7177) | EACH | 1 | $30,000 | $35,000 | $80,000 | $51,750 | $55,000 | $30,000 | $32,000 |
| 35 | Wingwall (PW - 1) (HW=8 FT) (466-7178) | EACH | 1 | $40,000 | $50,800 | $32,200 | $72,450 | $85,000 | $31,000 | $44,000 |
| 36 | Wingwall (PW - 1) (HW=9 FT) (466-7179) | EACH | 1 | $5,000.00 | $57,800 | $52,000 | $98,900 | $100,000 | $48,000 | $58,000 |
| 37 | Wingwall (PW - 1) (HW=10 FT) (466-7180) | EACH | 1 | $55,000 | $68,000 | $56,700 | $103,500 | $115,000 | $48,000 | $61,000 |
| 38 | Wingwall (PW - 1) (HW=11 FT) (466-7181) | EACH | 2 | $6,000.00 | $88,300 | $60,000 | $149,500 | $165,000 | $60,000 | $91,000 |
| 39 | Wingwall (PW - 2) (HW=5 FT) (466-7189) | EACH | 1 | $17,000 | $44,000 | $25,300 | $5,405.00 | $60,000 | $22,000 | $32,000 |
| 40 | Wingwall (PW - 2) (HW=11 FT) (466-7195) | EACH | 1 | $60,000 | $95,700 | $1.00 | $1.00 | $135,000 | $60,000 | $93,000 |
| 41 | Set (type I)(S= 4 FT)(HW= 3 FT)(4:1)(C) (467-7068) | EACH | 3 | $10,000 | $8,200.00 | $4,700.00 | $7,245.00 | $8,100.00 | $11,500 | $10,000 |
| 42 | Set (type I)(S= 5 FT)(HW= 3 FT)(4:1)(C) (467-7096) | EACH | 1 | $12,000 | $8,700.00 | $6,850.00 | $7,705.00 | $8,000.00 | $11,500 | $12,500 |
| 43 | Set (type I)(S= 6 FT)(HW= 4 FT)(3:1)(C) (467-7128) | EACH | 5 | $10,000 | $6,800.00 | $8,500.00 | $10,235 | $11,000 | $13,900 | $18,000 |
| 44 | Set (type I)(S= 6 FT)(HW= 4 FT)(6:1)(C) (467-7130) | EACH | 7 | $16,000 | $5,300.00 | $14,000 | $7,935.00 | $10,000 | $14,700 | $23,000 |
| 45 | Set (type I)(S= 6 FT)(HW= 5 FT)(4:1)(C) (467-7133) | EACH | 7 | $15,000 | $6,350.00 | $12,588 | $9,315.00 | $10,500 | $14,750 | $19,000 |
| 46 | Set (type I)(S= 6 FT)(HW= 6 FT)(3:1)(C) (467-7136) | EACH | 5 | $11,000 | $8,425.00 | $9,274.00 | $11,500 | $13,000 | $14,950 | $22,000 |
| 47 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 4 | $1,325.00 | $1,700.00 | $1,667.50 | $2,200.00 | $2,500.00 | $1,100.00 | |
| 48 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 2 | $2,000.00 | $1,700.00 | $2,200.00 | $2,300.00 | $2,700.00 | $2,750.00 | $2,600.00 |
| 49 | Clean existing culverts (480-7001) | EACH | 12 | $6,000.00 | $2,800.00 | $1,500.00 | $3,450.00 | $3,500.00 | $3,500.00 | $2,200.00 |
| 50 | Removing structure (set) (496-7004) | EACH | 8 | $550.00 | $1,050.00 | $1,500.00 | $230.00 | $550.00 | $1,200.00 | $800.00 |
| 51 | Removing structure (wingwall) (496-7005) | EACH | 20 | $2,200.00 | $3,400.00 | $500.00 | $1,150.00 | $1,000.00 | $1,400.00 | $1,300.00 |
| 52 | Removing structure (pipe) (496-7007) | LF | 81 | $50.00 | $40.00 | $30.00 | $23.00 | $20.00 | $20.00 | $52.00 |
| 53 | Mobilization (500-7001) | LS | 1 | $945,000 | $1,100,000 | $545,000 | $1,030,000 | $1,150,000 | $1,075,000 | $1,145,000 |
| 54 | Barricades, signs and traffic handling (502-7001) | MO | 21 | $15,000 | $5,600.00 | $100,000 | $7,500.00 | $10,000 | $10,000 | $18,000 |
| 55 | TMA (stationary) (505-7001) | DAY | 222 | $300.00 | $350.00 | $1.00 | $200.00 | $350.00 | $275.00 | $300.00 |
| 56 | TMA (mobile operation) (505-7003) | DAY | 76 | $600.00 | $700.00 | $1.00 | $400.00 | $25.00 | $325.00 | $50.00 |
| 57 | Rock filter dams (install) (type 4) (506-7004) | LF | 190 | $100.00 | $65.00 | $89.00 | $30.00 | $55.00 | $125.00 | $94.00 |
| 58 | Rock filter dams (remove) (506-7011) | LF | 190 | $15.00 | $10.00 | $10.00 | $20.00 | $20.00 | $25.00 | $16.00 |
| 59 | Temporary sediment control fence (install) (506-7039) | LF | 28,886 | $4.00 | $1.00 | $1.00 | $4.54 | $4.00 | $8.00 | $4.30 |
| 60 | Temporary sediment control fence (remove) (506-7041) | LF | 28,886 | $2.00 | $0.50 | $0.50 | $1.23 | $1.10 | $2.00 | $0.85 |
| 61 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 2,175 | $7.00 | $5.50 | $1.00 | $7.10 | $6.50 | $10.00 | $6.80 |
| 62 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,175 | $2.00 | $2.00 | $0.50 | $1.00 | $0.75 | $2.50 | $1.00 |
| 63 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 390 | $40.00 | $108.00 | $250.00 | $134.00 | $150.00 | $145.00 | $125.00 |
| 64 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 1,080 | $15.00 | $9.00 | $35.00 | $26.00 | $35.00 | $27.00 | $60.00 |
| 65 | Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037) | LF | 390 | $15.00 | $9.50 | $35.00 | $26.00 | $55.00 | $30.00 | $65.00 |
| 66 | Driveways (ACP) (530-7010) | SY | 1,106 | $80.00 | $70.00 | $85.00 | $65.00 | $35.00 | $70.00 | $66.00 |
| 67 | Turnouts (rap) (530-7020) | SY | 206 | $10.00 | $50.00 | $200.00 | $30.00 | $25.00 | $45.00 | $60.00 |
| 68 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 82,285 | $0.20 | $0.22 | $0.15 | $0.23 | $0.15 | $0.25 | $0.20 |
| 69 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 40,327 | $0.20 | $0.22 | $0.15 | $0.14 | $0.20 | $0.25 | $0.21 |
| 70 | Metal W-beam guard fence (timber post) (540-7001) | LF | 4,275 | $25.00 | $32.00 | $24.00 | $26.00 | $25.00 | $30.00 | $23.00 |
| 71 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 487.50 | $30.00 | $110.00 | $82.00 | $85.00 | $100.00 | $100.00 | $98.00 |
| 72 | Metal beam guard fence (long span system) (540-7027) | EACH | 4 | $1,400.00 | $1,500.00 | $1,300.00 | $1,400.00 | $1,500.00 | $1,680.00 | $1,350.00 |
| 73 | Remove metal beam guard fence (542-7001) | LF | 3,950 | $2.50 | $3.00 | $2.50 | $6.00 | $2.00 | $1.20 | $2.00 |
| 74 | Guardrail end treatment (install) (544-7001) | EACH | 34 | $3,200.00 | $3,300.00 | $3,200.00 | $3,375.00 | $3,200.00 | $4,000.00 | $3,200.00 |
| 75 | Guardrail end treatment (remove) (544-7003) | EACH | 30 | $250.00 | $250.00 | $250.00 | $200.00 | $215.00 | $240.00 | $220.00 |
| 76 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 6 | $1,500.00 | $2,000.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,800.00 | $1,100.00 |
| 77 | Crash cushion attenuator (stockpile) (545-7003) | EACH | 2 | $500.00 | $1,000.00 | $2,100.00 | $2,000.00 | $1,500.00 | $2,400.00 | $1,100.00 |
| 78 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $6,500.00 | $10,000 | $9,000.00 | $10,000 | $9,200.00 | $11,000 | $9,200.00 |
| 79 | Wire fence (type A) (552-7001) | LF | 16 | $30.00 | $100.00 | $150.00 | $50.00 | $55.00 | $100.00 | $115.00 |
| 80 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 9 | $350.00 | $250.00 | $220.00 | $550.00 | $230.00 | $320.00 | $230.00 |
| 81 | Aluminum signs (type G) (636-7002) | SF | 65 | $40.00 | $30.00 | $40.00 | $30.00 | $45.50 | $31.00 | |
| 82 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 50 | $820.00 | $750.00 | $675.00 | $1,000.00 | $700.00 | $815.00 | $710.00 |
| 83 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 5 | $1,000.00 | $850.00 | $775.00 | $1,500.00 | $800.00 | $935.00 | $820.00 |
| 84 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 4 | $1,200.00 | $1,100.00 | $990.00 | $2,000.00 | $1,000.00 | $1,280.00 | $1,100.00 |
| 85 | Remove SM RD SN sup&AM (644-7073) | EACH | 36 | $120.00 | $125.00 | $100.00 | $300.00 | $100.00 | $150.00 | $100.00 |
| 86 | Install LRSS (struct steel) (647-7001) | LB | 628.43 | $9.00 | $7.80 | $15.00 | $8.00 | $10.35 | $8.00 | |
| 87 | Remove lrsa (647-7003) | EACH | 2 | $950.00 | $850.00 | $1,250.00 | $900.00 | $1,320.00 | $900.00 | |
| 88 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 90 | $55.00 | $50.00 | $42.00 | $35.00 | $50.00 | $42.00 | $45.00 |
| 89 | Install object marker assembly (OM-2Y)(WC)GNDLL(BI) (658-7247) | EACH | 52 | $100.00 | $85.00 | $75.00 | $100.00 | $75.00 | $75.00 | $80.00 |
| 90 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 384 | $15.00 | $12.00 | $8.00 | $11.50 | $5.00 | $5.75 | $11.00 |
| 91 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 85,120 | $0.60 | $0.35 | $0.18 | $0.35 | $0.25 | $0.21 | $0.32 |
| 92 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 8,400 | $2.00 | $0.75 | $0.10 | $1.00 | $0.60 | $2.50 | $0.54 |
| 93 | All-wther PM type I (W)6"(solid)(100MIL) (666-7309) | LF | 82,285 | $1.30 | $0.68 | $0.49 | $0.66 | $0.55 | $0.56 | $0.65 |
| 94 | All-wther PM type I (W)6"(broken)(100MIL) (666-7310) | LF | 11,460 | $1.30 | $0.71 | $0.49 | $0.75 | $0.55 | $0.56 | $0.68 |
| 95 | All-wther PM type I (W)6"(DOT)(100MIL) (666-7311) | LF | 1,810 | $1.30 | $1.00 | $0.49 | $0.98 | $0.55 | $0.56 | $0.89 |
| 96 | All-wther PM type I (Y)6"(solid)(100MIL) (666-7315) | LF | 80,654 | $1.30 | $0.68 | $0.49 | $0.71 | $0.55 | $0.56 | $0.65 |
| 97 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 120 | $20.00 | $15.00 | $20.00 | $13.80 | $20.00 | $25.00 | $13.00 |
| 98 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 10 | $300.00 | $1,000.00 | $550.00 | $1,035.00 | $550.00 | $635.00 | $950.00 |
| 99 | Reflectorized pavement marker type I-C (672-7002) | EACH | 574 | $6.00 | $6.00 | $5.00 | $5.81 | $5.00 | $5.75 | $5.30 |
| 100 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,009 | $7.00 | $7.00 | $4.25 | $6.89 | $4.50 | $4.90 | $6.50 |
| 101 | Eliminating existing PM & markers (6") (677-7002) | LF | 1,320 | $0.50 | $1.25 | $1.00 | $0.96 | $1.00 | $1.50 | $1.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.