RankBidderTotal bidAgainst the low bidAgainst the estimate
1Icos Management, LLC$1,837,551Low-16%
2Xit Paving and Construction Inc.$1,928,560+5.0%-12%
3Palmer Hall Construction$1,938,522+5.0%-12%
4Grey Sky Construction LLC$2,316,320+26%+5.0%
5Ed Bell Construction Company$2,319,613+26%+5.0%
6O. Trevino Construction, LLC$2,498,838+36%+14%
7Ragle Construction, Inc.$2,962,408+61%+35%
TxDOT contract A00190749: bids by rank

Engineer's estimate: $2,200,606.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Icos Management, LLC2. Xit Paving and Construction Inc.3. Palmer Hall Construction4. Grey Sky Construction LLC5. Ed Bell Construction Company6. O. Trevino Construction, LLC
1Removing concrete (mowstrip) (104-7005)LF460$22.00$17.00$9.00$100.00$15.00$25.00
2Backfill (type A or B) (134-7004)STA30$540.00$369.00$280.00$450.00$2,350.00$500.00
3Compost manuf topsoil (4") (161-7002)SY4,361$5.00$5.00$9.00$2.00$10.00$8.50$4.00
4Block sodding (162-7002)SY4,361$6.00$7.00$5.00$6.00$10.00$7.00$9.00
5Vegetative watering (168-7001)TGL649$75.00$1.00$20.00$10.00$30.00$60.00$79.00
6Class B concrete (flume) (420-7010)CY8$540.00$2,800.00$600.00$2,000.00$1,500.00$2,200.00
7Class C concrete (rail foundation) (420-7052)CY22$648.00$1,563.00$900.00$2,000.00$1,000.00$1,400.00
8Riprap (mow strip)(4 in) (432-7013)CY17.50$648.00$1,565.00$775.00$550.00$1,000.00$1,800.00
9Rail (type C221) (450-7032)LF120$324.00$83.00$199.00$250.00$420.00$335.00
10Rail (handrail)(type D) (450-7061)LF1,100$216.00$198.00$132.00$185.00$145.00$128.00
11Mobilization (500-7001)LS1$225,000$50,000$20,000$200,000$200,000$190,000$240,000
12Barricades, signs and traffic handling (502-7001)MO13$15,000$1.00$5,000.00$4,154.00$12,500$30,000$18,460
13Portable changeable message sign (503-7002)EACH6$12,000$1.00$2,010.00$16,500$20,000$2,500.00$10,000
14TMA (stationary) (505-7001)DAY398$250.00$1.00$216.00$275.00$250.00$157.50$180.00
15Temporary sediment control fence (install) (506-7039)LF2,000$5.00$2.00$4.00$4.00$4.00$2.75$8.00
16Temporary SDMT cont fence (inlet protection) (506-7040)LF1,500$15.00$1.00$9.00$6.00$6.00$3.00$12.00
17Temporary sediment control fence (remove) (506-7041)LF3,500$2.50$1.00$1.00$2.00$2.00$1.50$2.50
18Biodegradable erosion control logs (install) (12") (506-7044)LF1,500$11.00$1.00$6.00$6.00$18.00$5.00$9.00
19Biodegradable erosion control logs (remove) (506-7046)LF1,500$3.50$1.00$1.00$1.00$9.00$2.50$2.50
20PTB (furnish and install)(steel) (512-7072)LF490$110.00$72.00$150.00$100.00$42.00$60.00
21PTB (move)(steel) (512-7074)LF490$108.00$22.00$140.00$30.00$13.65$30.00
22PTB (remove)(steel) (512-7076)LF490$54.00$34.00$150.00$30.00$21.00$20.00
23Concrete curb (type IV) (529-7005)LF2,024$44.00$26.00$17.00$100.00$27.50$36.00
24Concrete curb (type C1) (529-7016)LF1,691$150.00$165.00$175.00$115.00$120.00$90.00$180.00
25Concrete curb (type F1) (529-7017)LF1,100$165.00$185.00$125.00$150.00$140.00$166.00
26Concrete sidewalks (4") (531-7001)SY6,653$80.00$82.00$86.00$74.00$65.00$90.00$100.00
27Curb ramps (type 7) (531-7010)EACH8$5,400.00$1,767.00$1,800.00$3,500.00$4,000.00$2,800.00
28Curb ramps (type 10) (531-7011)EACH3$3,200.00$6,600.00$1,971.00$1,800.00$3,500.00$4,000.00$3,050.00
29Metal W-beam guard fence (timber post) (540-7001)LF400$33.00$28.00$23.75$29.00$27.50$28.00
30Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$4,320.00$2,123.00$1,812.00$1,850.00$3,000.00$4,200.00
31Downstream anchor terminal section (540-7015)EACH2$3,240.00$1,675.00$1,129.00$1,850.00$1,650.00$1,650.00
32Remove metal beam guard fence (542-7001)LF380$4.00$3.00$2.75$3.00$3.30$3.50
33Remove terminal anchor section (542-7002)EACH2$540.00$223.00$275.00$500.00$220.00$220.00
34Guardrail end treatment (install) (544-7001)EACH2$5,400.00$3,214.00$2,820.00$3,850.00$3,200.00$3,200.00
35Guardrail end treatment (remove) (544-7003)EACH2$540.00$279.00$275.00$1,500.00$275.00$275.00
36Crash cushion attenuator (move & reset) (545-7002)EACH1$5,500.00$3,893.00$1,125.00$8,500.00$1,500.00$900.00
37Crash cushion attenuator (remove) (545-7004)EACH1$2,160.00$2,993.00$795.00$2,500.00$750.00$600.00
38Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH1$11,000$14,474$7,575.00$21,000$10,500$9,500.00
39Install delineator assembly (D-DY)SZ 1(BRF)GF2 (658-7052)EACH8$55.00$28.00$16.00$100.00$27.50$30.00
40Concrete scupper (5032-7001)EACH10$2,750.00$4,500.00$4,990.00$1,250.00$10,000$7,000.00
TxDOT contract A00190749: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of April 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy