TxDOT contract A00192970 bid tabulation
Hazard Elimination & Safety, IH 10 (0.37 MI W OF FM 563 to 0.36 MI E OF FM 563). Let by Texas DOT on October 8, 2025, Chambers, Beaumont District. 10 bids received; low bid $1,064,705 by Allstate Signal & Construction, LLC, -4.3% against the engineer's estimate of $1,112,605.
- Owner
- Texas DOT
- Letting
- 08 OCT 2025
- Pay items
- 23
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Allstate Signal & Construction, LLC | $1,064,705 | Low | -4.0% |
| 2 | Deco Contractors, Inc. | $1,074,363 | +1.0% | -3.0% |
| 3 | Third Coast Services LLC | $1,082,631 | +2.0% | -3.0% |
| 4 | Structural Integrity Group LLC | $1,091,434 | +3.0% | -2.0% |
| 5 | Creacom, Inc. | $1,138,381 | +7.0% | +2.0% |
| 6 | Traf-Tex, Inc. | $1,197,284 | +12% | +8.0% |
| 7 | Florida Traffic Control Devices, Inc. | $1,231,450 | +16% | +11% |
| 8 | Light It Up Electric | $1,275,151 | +20% | +15% |
| 9 | Sice, Inc. | $1,282,743 | +20% | +15% |
| 10 | Select Maintenance, L.L.C. | $1,429,595 | +34% | +28% |
Engineer's estimate: $1,112,605.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Allstate Signal & Construction, LLC | 2. Deco Contractors, Inc. | 3. Third Coast Services LLC | 4. Structural Integrity Group LLC | 5. Creacom, Inc. | 6. Traf-Tex, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Backfill (type B) (134-7002) | STA | 10.65 | $200.00 | $355.00 | $350.00 | $211.83 | $63.40 | $402.12 | $173.00 |
| 2 | Drilled shaft (high mast pole) (60 in) (416-7037) | LF | 270 | $850.00 | $748.89 | $695.00 | $640.26 | $761.01 | $633.36 | $981.35 |
| 3 | Riprap (concrete)(4 in) (432-7001) | CY | 16 | $600.00 | $450.60 | $800.00 | $1,481.76 | $645.05 | $1,429.95 | $1,985.00 |
| 4 | Riprap (mow strip)(4 in) (432-7013) | CY | 59 | $640.00 | $501.83 | $975.00 | $732.00 | $585.30 | $1,206.15 | $615.00 |
| 5 | Mobilization (500-7001) | LS | 1 | $110,230 | $86,500 | $100,000 | $108,263 | $96,259 | $79,687 | $96,478 |
| 6 | Barricades, signs and traffic handling (502-7001) | MO | 3 | $4,000.00 | $6,657.00 | $2,250.00 | $18,879 | $11,359 | $3,163.16 | $1,242.00 |
| 7 | TMA (stationary) (505-7001) | DAY | 36 | $200.00 | $200.00 | $250.00 | $413.63 | $200.00 | $455.80 | $410.00 |
| 8 | Temporary sediment control fence (install) (506-7039) | LF | 150 | $4.00 | $5.00 | $11.00 | $6.71 | $1.00 | $4.90 | $6.60 |
| 9 | Temporary sediment control fence (remove) (506-7041) | LF | 150 | $4.00 | $2.00 | $1.00 | $7.52 | $0.10 | $2.01 | $1.00 |
| 10 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 58 | $7.00 | $5.75 | $7.00 | $27.57 | $1.00 | $17.06 | $12.30 |
| 11 | Biodegradable erosion control logs (remove) (506-7046) | LF | 58 | $3.00 | $2.00 | $1.00 | $19.45 | $0.10 | $17.35 | $5.05 |
| 12 | Metal W-beam guard fence (timber post) (540-7001) | LF | 825 | $28.00 | $23.10 | $28.00 | $28.15 | $21.00 | $36.80 | $25.55 |
| 13 | Downstream anchor terminal section (540-7015) | EACH | 4 | $1,700.00 | $1,738.00 | $1,900.00 | $1,447.11 | $1,580.00 | $1,524.23 | $2,375.00 |
| 14 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,320.00 | $3,190.00 | $3,500.00 | $3,265.84 | $2,900.00 | $4,357.83 | $3,800.00 |
| 15 | HI MST IL pole (150 FT)(100 MPH) (613-7006) | EACH | 6 | $57,000 | $59,716 | $58,250 | $53,185 | $59,298 | $64,186 | $58,188 |
| 16 | LED HI MST IL asm (6 fixt) (type A) (614-7002) | EACH | 6 | $37,000 | $35,520 | $37,750 | $36,754 | $35,747 | $41,459 | $40,475 |
| 17 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 2,667 | $15.00 | $12.90 | $8.95 | $7.32 | $15.74 | $7.79 | $13.70 |
| 18 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 315 | $15.20 | $15.90 | $12.00 | $9.96 | $27.95 | $16.84 | $28.00 |
| 19 | Electrical conductor (no.6) bare (620-7009) | LF | 2,982 | $1.80 | $2.36 | $1.85 | $1.51 | $1.76 | $1.37 | $2.50 |
| 20 | Electrical conductor (no.6) insulated (620-7010) | LF | 5,964 | $2.00 | $2.66 | $2.15 | $1.73 | $2.23 | $1.72 | $2.65 |
| 21 | Ground box type A (122311)W/apron (624-7002) | EACH | 13 | $1,600.00 | $1,145.00 | $952.00 | $728.04 | $1,272.61 | $929.73 | $1,159.00 |
| 22 | Elc SRV type A 240/480 100(SS)SS(E)SP(O) (628-7091) | EACH | 2 | $6,000.00 | $9,380.00 | $7,500.00 | $13,428 | $5,369.35 | $9,824.22 | $11,640 |
| 23 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 12 | $28.00 | $49.50 | $48.45 | $37.16 | $45.00 | $42.97 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.