TxDOT contract A00193343 bid tabulation
Hazard Elimination & Safety, SL 375 (MIDWAY DR to FRANCIS ST). Let by Texas DOT on August 6, 2026, El Paso, El Paso District. 4 bids received; low bid $6,996,636 by Albatross Construction LLC, +0.7% against the engineer's estimate of $6,949,288.
- Owner
- Texas DOT
- Letting
- 06 AUG 2026
- Pay items
- 41
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Albatross Construction LLC | $6,996,636 | Low | +1.0% |
| 2 | Martinez Bros. Contractors, LLC | $7,658,192 | +9.0% | +10% |
| 3 | Tri State Electric, LTD. | $7,911,043 | +13% | +14% |
| 4 | Digg Commercial, LLC | $8,808,153 | +26% | +27% |
Engineer's estimate: $6,949,288.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Albatross Construction LLC | 2. Martinez Bros. Contractors, LLC | 3. Tri State Electric, LTD. | 4. Digg Commercial, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (pavement) (104-7001) | SY | 7.22 | $25.00 | $201.25 | $201.25 | $525.00 | $500.00 |
| 2 | Excavation (special) (110-7003) | CY | 21 | $1,250.00 | $212.75 | $856.75 | $975.00 | $200.00 |
| 3 | Concrete pavement (CRCP) (11") (360-7005) | SY | 5.85 | $100.00 | $1,092.50 | $488.75 | $1,250.00 | $1,500.00 |
| 4 | Drilled shaft (high mast pole) (60 in) (416-7037) | LF | 1,280 | $900.00 | $974.34 | $977.50 | $956.14 | $1,000.00 |
| 5 | Riprap (concrete)(4 in) (432-7001) | CY | 61.44 | $500.00 | $902.75 | $690.00 | $575.00 | $800.00 |
| 6 | Riprap (mow strip)(4 in) (432-7013) | CY | 107.46 | $500.00 | $977.50 | $690.00 | $600.00 | $800.00 |
| 7 | Mobilization (500-7001) | LS | 1 | $34,000 | $354,457 | $270,000 | $10,000 | $500,000 |
| 8 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $13,000 | $3,742.10 | $14,939 | $16,519 | $6,000.00 |
| 9 | Portable changeable message sign (503-7001) | DAY | 180 | $155.00 | $111.80 | $115.00 | $295.00 | $100.00 |
| 10 | Portable changeable message sign (503-7002) | EACH | 2 | $1,250.00 | $20,125 | $14,950 | $10,300 | $2,500.00 |
| 11 | TMA (stationary) (505-7001) | DAY | 180 | $250.00 | $225.00 | $373.75 | $325.00 | $2,500.00 |
| 12 | Temporary sediment control fence (install) (506-7039) | LF | 400 | $5.00 | $5.69 | $8.05 | $12.75 | $15.00 |
| 13 | Temporary sediment control fence (remove) (506-7041) | LF | 400 | $1.50 | $2.82 | $1.15 | $3.50 | $1.00 |
| 14 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 60 | $7.50 | $30.28 | $8.05 | $15.50 | $35.00 |
| 15 | Biodegradable erosion control logs (remove) (506-7046) | LF | 60 | $1.50 | $18.78 | $1.15 | $7.00 | $1.00 |
| 16 | Permanent CTB (F-shape) (type 1) (514-7013) | LF | 330 | $90.00 | $402.50 | $165.60 | $395.00 | $150.00 |
| 17 | Metal W-beam guard fence (steel post) (540-7002) | LF | 2,750 | $35.00 | $55.20 | $43.70 | $60.00 | $30.00 |
| 18 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 11 | $3,000.00 | $3,450.00 | $2,990.00 | $4,500.00 | $2,213.00 |
| 19 | Downstream anchor terminal section (540-7015) | EACH | 18 | $2,200.00 | $1,897.50 | $2,012.50 | $5,632.00 | $1,217.00 |
| 20 | Remove downstream anchor terminal (542-7003) | EACH | 3 | $575.00 | $575.00 | $990.00 | $195.00 | |
| 21 | Guardrail end treatment (install) (544-7001) | EACH | 29 | $4,000.00 | $4,255.00 | $4,025.00 | $5,530.25 | $2,800.00 |
| 22 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $300.00 | $575.00 | $575.00 | $625.00 | $269.00 |
| 23 | Crash cushion attenuator (install)(S)(W)(TL2) (545-7015) | EACH | 9 | $18,000 | $16,675 | $11,500 | $9,500.00 | $1,500.00 |
| 24 | Remove RD IL asm (CTB mount) (610-7008) | EACH | 129 | $850.00 | $266.26 | $1,035.00 | $935.00 | $454.00 |
| 25 | Replace luminaire W/(150W EQ) LED (610-7011) | EACH | 16 | $700.00 | $420.72 | $575.00 | $750.00 | $510.00 |
| 26 | HI MST IL pole (150 FT)( 80 MPH) (613-7005) | EACH | 40 | $50,000 | $47,383 | $55,200 | $54,000 | $58,000 |
| 27 | LED HI MST IL asm (6 fixt) (type B) (614-7003) | EACH | 6 | $35,000 | $38,186 | $45,569 | $46,500 | $50,000 |
| 28 | LED HI MST IL asm(6 fixt) (type B)SHLD (614-7010) | EACH | 34 | $35,000 | $39,305 | $46,719 | $47,000 | $50,000 |
| 29 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 28,040 | $18.00 | $13.35 | $14.95 | $18.09 | $30.00 |
| 30 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 3,480 | $30.00 | $45.06 | $34.50 | $30.88 | $70.00 |
| 31 | Conduit (prepare) (618-7090) | LF | 1,380 | $8.15 | $8.05 | $4.14 | $2.00 | |
| 32 | Electrical conductor (no.8) insulated (620-7008) | LF | 9,315 | $1.43 | $2.30 | $3.65 | $2.16 | |
| 33 | Electrical conductor (no.6) insulated (620-7010) | LF | 98,070 | $2.50 | $1.89 | $2.30 | $4.00 | $2.80 |
| 34 | Ground box type A (122311)W/apron (624-7002) | EACH | 100 | $1,700.00 | $972.81 | $1,265.00 | $1,498.36 | $1,451.00 |
| 35 | Elc SRV type A 240/480 060(NS)SS(E)GC(O) (628-7044) | EACH | 3 | $9,385.33 | $11,500 | $10,000 | $7,500.00 | |
| 36 | Relocate lrsa (647-7002) | EACH | 1 | $4,000.00 | $3,585.06 | $3,450.00 | $9,182.27 | $1,636.00 |
| 37 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BR) (658-7014) | EACH | 22 | $25.00 | $57.50 | $57.50 | $18.00 | $15.00 |
| 38 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BR) (658-7017) | EACH | 138 | $35.00 | $57.50 | $57.50 | $45.00 | $30.00 |
| 39 | Ground box (prepare) (6013-7006) | EACH | 18 | $600.00 | $386.03 | $460.00 | $886.21 | $500.00 |
| 40 | Modify existing electrical service (6103-7001) | EACH | 6 | $600.00 | $6,771.66 | $4,600.00 | $2,500.00 | $1,130.00 |
| 41 | Remove existing cables (power) (6106-7002) | LF | 33,930 | $10.00 | $0.43 | $1.15 | $2.95 | $3.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.