Install Traffic Signal, US 380 (at THOMAS J EGAN RD to in the City of Denton). Let by Texas DOT on October 9, 2025, Denton, Dallas District. 6 bids received; low bid $3,127,471 by Sice, Inc., -15% against the engineer's estimate of $3,685,758.
- Owner
- Texas DOT
- Letting
- 09 OCT 2025
- Pay items
- 104
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sice, Inc. | $3,127,471 | Low | -15% |
| 2 | O. Trevino Construction, LLC | $3,338,283 | +7.0% | -9.0% |
| 3 | Durable Specialties, Inc. | $3,552,254 | +14% | -4.0% |
| 4 | Grey Sky Construction LLC | $3,562,975 | +14% | -3.0% |
| 5 | American Lighting and Signalization, LLC | $3,674,955 | +18% | 0.0% |
| 6 | Yunex LLC | $3,819,479 | +22% | +4.0% |
Engineer's estimate: $3,685,758.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Sice, Inc. | 2. O. Trevino Construction, LLC | 3. Durable Specialties, Inc. | 4. Grey Sky Construction LLC | 5. American Lighting and Signalization, LLC | 6. Yunex LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (pavement) (104-7001) | SY | 444 | $30.67 | $90.00 | $55.00 | $20.00 | $74.00 | $57.00 | |
| 2 | Removing concrete (medians) (104-7008) | SY | 21 | $30.67 | $119.00 | $88.00 | $20.00 | $169.00 | $283.00 | |
| 3 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 147 | $100.00 | $30.67 | $79.00 | $88.00 | $20.00 | $169.00 | $57.00 |
| 4 | Removing concrete (curb & gutter) (104-7017) | LF | 846 | $50.00 | $19.17 | $26.00 | $28.00 | $20.00 | $37.00 | $29.00 |
| 5 | Remove (4"-8") TRT/untrt base & asphalt pavement (105-7004) | SY | 339 | $30.67 | $59.00 | $50.00 | $20.00 | $66.00 | $68.00 | |
| 6 | Excavation (roadway) (110-7001) | CY | 82 | $30.67 | $99.00 | $66.00 | $20.00 | $88.00 | $68.00 | |
| 7 | Block sodding (162-7002) | SY | 215 | $25.00 | $5.05 | $11.09 | $30.00 | $20.00 | $56.00 | $12.00 |
| 8 | Vegetative watering (168-7001) | TGL | 7.53 | $250.00 | $31.55 | $379.35 | $200.00 | $50.00 | $3.00 | $12.00 |
| 9 | FL BS(compacted in place)(type A,B or D GR4)(10") (247-7111) | SY | 200 | $63.90 | $83.00 | $99.00 | $30.00 | $132.00 | $102.00 | |
| 10 | Concrete pavement (CRCP)(fast TRK) (12") (360-7076) | SY | 200 | $287.56 | $230.00 | $231.00 | $200.00 | $441.00 | $238.00 | |
| 11 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 55 | $566.10 | $315.26 | $885.00 | $385.00 | $425.00 | $802.00 | |
| 12 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 91 | $689.82 | $342.96 | $940.00 | $450.00 | $534.00 | $747.00 | |
| 13 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 176 | $950.00 | $809.44 | $778.46 | $1,205.00 | $650.00 | $831.00 | $848.00 |
| 14 | Riprap (concrete)(4 in) (432-7001) | CY | 295 | $702.92 | $1,100.00 | $605.00 | $550.00 | $809.00 | $735.00 | |
| 15 | Mobilization (500-7001) | LS | 1 | $300,000 | $314,141 | $330,000 | $325,000 | $360,000 | $190,000 | $673,001 |
| 16 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $13,000 | $13,290 | $15,015 | $18,000 | $12,500 | $9,500.00 | $9,161.00 |
| 17 | Portable changeable message sign (503-7002) | EACH | 10 | $200.00 | $15,201 | $20,000 | $75.00 | $20,000 | $47.00 | $20,758 |
| 18 | TMA (stationary) (505-7001) | DAY | 120 | $300.00 | $309.34 | $180.00 | $250.00 | $250.00 | $308.00 | $217.00 |
| 19 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 200 | $9.00 | $6.22 | $7.15 | $2.00 | $12.00 | $15.00 | $8.00 |
| 20 | Biodegradable erosion control logs (remove) (506-7046) | LF | 200 | $5.00 | $0.63 | $1.59 | $1.00 | $9.00 | $1.70 | $2.00 |
| 21 | Colored textured concrete (6") (527-7003) | SY | 14 | $786.00 | $470.00 | $242.00 | $150.00 | $324.00 | $255.00 | |
| 22 | Concrete curb & gutter (type II) (529-7009) | LF | 2,539 | $100.00 | $47.29 | $98.00 | $58.00 | $65.00 | $96.00 | $59.88 |
| 23 | Concrete sidewalks (4") (531-7001) | SY | 878 | $175.00 | $104.80 | $156.00 | $110.00 | $65.00 | $191.00 | $113.00 |
| 24 | Curb ramps (type 2) (531-7006) | EACH | 1 | $3,067.30 | $3,030.00 | $4,180.00 | $3,250.00 | $5,600.00 | $5,649.00 | |
| 25 | Curb ramps (type 5) (531-7008) | EACH | 1 | $4,500.00 | $3,067.30 | $2,650.00 | $5,390.00 | $3,250.00 | $7,000.00 | $6,778.00 |
| 26 | Curb ramps (type 7) (531-7010) | EACH | 31 | $4,500.00 | $2,811.70 | $2,810.00 | $3,960.00 | $3,250.00 | $5,600.00 | $5,649.00 |
| 27 | Curb ramps (type 22) (531-7014) | EACH | 6 | $4,217.54 | $10,250 | $5,280.00 | $3,250.00 | $7,000.00 | $5,649.00 | |
| 28 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 120 | $30.00 | $28.14 | $20.62 | $32.00 | $25.00 | $35.00 | $38.06 |
| 29 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 1,150 | $35.00 | $36.13 | $24.40 | $34.00 | $35.00 | $38.00 | $35.25 |
| 30 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 1,290 | $40.00 | $31.14 | $25.37 | $36.00 | $40.00 | $41.00 | $40.97 |
| 31 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 2,245 | $50.00 | $54.60 | $38.43 | $76.00 | $60.00 | $59.00 | $61.95 |
| 32 | Electrical conductor (no.12) insulated (620-7004) | LF | 4,340 | $3.00 | $1.19 | $2.54 | $2.00 | $3.00 | $4.50 | $2.88 |
| 33 | Electrical conductor (no.8) insulated (620-7008) | LF | 12,790 | $3.50 | $1.66 | $3.29 | $3.00 | $3.00 | $5.80 | $3.53 |
| 34 | Electrical conductor (no.6) bare (620-7009) | LF | 4,600 | $4.00 | $1.74 | $3.31 | $4.00 | $3.00 | $5.80 | $3.53 |
| 35 | Electrical conductor (no.6) insulated (620-7010) | LF | 140 | $4.00 | $2.37 | $4.00 | $4.00 | $3.00 | $6.30 | $3.99 |
| 36 | Ground box type D (162922)W/apron (624-7008) | EACH | 38 | $2,400.00 | $2,265.56 | $1,761.25 | $2,900.00 | $1,150.00 | $2,700.00 | $3,293.00 |
| 37 | Elc SRV type D 120/240 060(NS)SS(E)PS(U) (628-7147) | EACH | 4 | $12,000 | $8,186.83 | $15,674 | $12,000 | $12,500 | $11,000 | $10,470 |
| 38 | Aluminum signs (type A) (636-7001) | SF | 190 | $80.00 | $105.00 | $37.82 | $65.00 | $50.00 | $58.00 | $50.00 |
| 39 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 8 | $653.87 | $712.88 | $1,100.00 | $1,150.00 | $947.00 | $814.00 | |
| 40 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 3 | $1,141.12 | $1,272.31 | $1,100.00 | $1,150.00 | $1,094.00 | $1,195.00 | |
| 41 | Install small roadside sign support and assembly (inst sign only) (644-7064) | EACH | 2 | $167.12 | $43.27 | $350.00 | $1,150.00 | $218.00 | $445.00 | |
| 42 | Remove SM RD SN sup&AM (644-7073) | EACH | 29 | $300.00 | $167.12 | $85.98 | $250.00 | $500.00 | $653.00 | $167.00 |
| 43 | Remove SM RD SN sup&AM (sign only) (644-7075) | EACH | 11 | $200.00 | $167.12 | $27.21 | $75.00 | $500.00 | $163.00 | $167.00 |
| 44 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,499 | $3.00 | $1.98 | $1.82 | $2.00 | $6.00 | $3.70 | $1.36 |
| 45 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 2,517 | $12.00 | $7.67 | $8.81 | $15.00 | $12.00 | $11.00 | $8.65 |
| 46 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 13 | $350.00 | $253.05 | $212.61 | $176.00 | $250.00 | $368.00 | $191.00 |
| 47 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 13 | $400.00 | $287.56 | $253.37 | $182.00 | $250.00 | $404.00 | $235.00 |
| 48 | Reflectorized pavement marking type I (Y)18"(solid)(100MIL) (666-7120) | LF | 178 | $6.39 | $5.51 | $9.00 | $12.00 | $5.90 | $8.00 | |
| 49 | RE PV marking type I(black)6"(shadow)(100MIL) (666-7138) | LF | 1,500 | $1.50 | $1.60 | $3.30 | $8.00 | $3.00 | $15.00 | $2.43 |
| 50 | Pavement sler 6" (666-7347) | LF | 9,353 | $2.00 | $0.26 | $0.55 | $0.20 | $3.00 | $0.37 | $0.23 |
| 51 | Pavement sler 8" (666-7348) | LF | 1,579 | $2.00 | $0.26 | $0.74 | $0.20 | $6.00 | $0.60 | $0.34 |
| 52 | Pavement sler 18" (666-7351) | LF | 178 | $0.64 | $1.65 | $2.00 | $12.00 | $2.20 | $1.76 | |
| 53 | Pavement sler 24" (666-7352) | LF | 2,517 | $4.00 | $1.28 | $2.20 | $2.00 | $12.00 | $5.90 | $1.76 |
| 54 | Pavement sler (arrow) (666-7353) | EACH | 13 | $100.00 | $21.73 | $49.57 | $17.00 | $250.00 | $44.00 | $33.00 |
| 55 | Pavement sler (word) (666-7354) | EACH | 13 | $125.00 | $21.73 | $60.59 | $22.00 | $250.00 | $66.00 | $40.00 |
| 56 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 4,892 | $1.50 | $1.09 | $1.87 | $1.00 | $3.00 | $2.90 | $0.91 |
| 57 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 3,062 | $2.50 | $1.09 | $1.87 | $1.00 | $3.00 | $2.90 | $0.91 |
| 58 | Reflectorized pavement marker type I-C (672-7002) | EACH | 51 | $5.43 | $7.71 | $5.00 | $6.00 | $8.80 | $8.00 | |
| 59 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 58 | $10.00 | $5.43 | $7.71 | $5.00 | $6.00 | $9.60 | $8.00 |
| 60 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 98 | $8.00 | $5.43 | $7.71 | $5.00 | $6.00 | $9.60 | $8.00 |
| 61 | Eliminating existing PM & markers (6") (677-7002) | LF | 7,840 | $2.00 | $0.68 | $0.80 | $1.00 | $3.00 | $1.80 | $1.13 |
| 62 | Eliminating existing PM & markers (8") (677-7004) | LF | 2,583 | $3.00 | $0.81 | $1.10 | $2.00 | $5.00 | $2.90 | $1.42 |
| 63 | Eliminating existing PM & markers (18") (677-7007) | LF | 192 | $3.20 | $4.41 | $4.00 | $12.00 | $4.40 | $6.00 | |
| 64 | Eliminating existing PM & markers (24") (677-7008) | LF | 558 | $6.00 | $3.84 | $4.41 | $5.00 | $12.00 | $7.40 | $12.00 |
| 65 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 8 | $120.00 | $63.90 | $110.16 | $44.00 | $250.00 | $147.00 | $113.00 |
| 66 | Eliminating existing PM & markers (double arrow) (677-7010) | EACH | 2 | $95.85 | $176.26 | $83.00 | $500.00 | $221.00 | $170.00 | |
| 67 | Eliminating existing PM & markers (word) (677-7015) | EACH | 6 | $125.00 | $63.90 | $126.68 | $50.00 | $250.00 | $184.00 | $113.00 |
| 68 | Eliminating existing PM & markers (36")(yld tri) (677-7024) | EACH | 23 | $12.78 | $66.10 | $11.00 | $50.00 | $74.00 | $80.00 | |
| 69 | Pavement surface preparation for marking (6") (678-7002) | LF | 9,353 | $0.50 | $0.09 | $0.22 | $0.10 | $3.00 | $0.50 | $0.03 |
| 70 | Pavement surface preparation for marking (8") (678-7004) | LF | 1,579 | $0.75 | $0.09 | $0.30 | $0.10 | $6.00 | $1.00 | $0.08 |
| 71 | Pavement surface preparation for marking (18") (678-7007) | LF | 178 | $0.27 | $1.10 | $0.50 | $12.00 | $1.50 | $0.45 | |
| 72 | Pavement surface preparation for marking (24") (678-7008) | LF | 2,517 | $2.00 | $0.38 | $3.30 | $1.00 | $12.00 | $5.90 | $0.61 |
| 73 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 13 | $70.00 | $12.78 | $55.08 | $11.00 | $250.00 | $66.00 | $15.00 |
| 74 | Pavement surface preparation for marking (word) (678-7016) | EACH | 13 | $75.00 | $12.78 | $60.59 | $17.00 | $250.00 | $88.00 | $18.00 |
| 75 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 207 | $2.50 | $0.96 | $1.10 | $0.10 | $50.00 | $2.20 | $1.00 |
| 76 | Ins HY traffic signal (DPT sup CNT & cab)(iso) (680-7005) | EACH | 4 | $50,000 | $34,680 | $26,018 | $40,000 | $50,000 | $40,000 | $47,466 |
| 77 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 35 | $450.00 | $413.32 | $334.93 | $800.00 | $350.00 | $469.00 | $403.00 |
| 78 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 20 | $450.00 | $409.38 | $342.37 | $800.00 | $350.00 | $469.00 | $403.00 |
| 79 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 43 | $450.00 | $410.67 | $334.92 | $800.00 | $350.00 | $469.00 | $403.00 |
| 80 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 20 | $450.00 | $413.88 | $342.37 | $800.00 | $350.00 | $469.00 | $403.00 |
| 81 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 43 | $450.00 | $410.67 | $334.92 | $800.00 | $350.00 | $469.00 | $403.00 |
| 82 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 10 | $450.00 | $413.88 | $342.37 | $800.00 | $350.00 | $469.00 | $403.00 |
| 83 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 40 | $950.00 | $915.07 | $897.00 | $1,400.00 | $2,500.00 | $956.00 | $934.00 |
| 84 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 41 | $300.00 | $720.80 | $242.57 | $250.00 | $250.00 | $285.00 | $277.00 |
| 85 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 12 | $350.00 | $810.39 | $326.20 | $300.00 | $350.00 | $344.00 | $337.00 |
| 86 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 2,330 | $3.50 | $5.62 | $3.58 | $3.00 | $3.00 | $5.50 | $3.66 |
| 87 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 825 | $3.75 | $5.76 | $3.58 | $3.00 | $3.00 | $6.00 | $4.05 |
| 88 | Traffic signal CBL (type A)(14 AWG)(10 conductor) (684-7036) | LF | 7,070 | $6.00 | $6.11 | $4.42 | $6.00 | $3.00 | $7.50 | $5.42 |
| 89 | Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046) | LF | 5,780 | $8.00 | $8.76 | $8.19 | $10.00 | $6.00 | $12.00 | $8.27 |
| 90 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 12,065 | $3.25 | $4.73 | $2.44 | $2.00 | $6.00 | $5.50 | $3.47 |
| 91 | Ins traffic signal PL AM(S)1 arm(28')lum&ilsn (686-7032) | EACH | 1 | $18,378 | $16,255 | $16,600 | $16,500 | $17,200 | $15,607 | |
| 92 | Ins traffic signal PL AM(S)1 arm(32')lum&ilsn (686-7036) | EACH | 4 | $19,018 | $17,693 | $17,900 | $20,000 | $17,936 | $16,695 | |
| 93 | Ins traffic signal PL AM(S)1 arm(36')lum&ilsn (686-7040) | EACH | 5 | $20,410 | $19,034 | $19,200 | $22,500 | $20,878 | $17,709 | |
| 94 | Ins traffic signal PL AM(S)1 arm(44')lum&ilsn (686-7048) | EACH | 1 | $21,819 | $21,115 | $20,100 | $25,000 | $26,026 | $19,284 | |
| 95 | Ins traffic signal PL AM(S)1 arm(48')lum&ilsn (686-7052) | EACH | 1 | $21,836 | $22,353 | $22,600 | $26,500 | $29,253 | $21,109 | |
| 96 | Ins traffic signal PL AM(S)1 arm(50')lum&ilsn (686-7056) | EACH | 2 | $39,772 | $39,019 | $45,800 | $50,000 | $43,226 | $32,723 | |
| 97 | Ins traffic signal PL AM(S)1 arm(55')lum&ilsn (686-7060) | EACH | 1 | $50,000 | $41,189 | $40,264 | $47,400 | $50,000 | $44,697 | $35,441 |
| 98 | Ins traffic signal PL AM(S)1 arm(60')lum&ilsn (686-7064) | EACH | 3 | $51,500 | $41,954 | $41,412 | $47,900 | $50,000 | $46,791 | $37,199 |
| 99 | Ins traffic signal PL AM(S)1 arm(65')lum&ilsn (686-7068) | EACH | 2 | $53,000 | $43,018 | $42,167 | $48,400 | $50,000 | $49,733 | $37,770 |
| 100 | Pedestrian pole assembly (687-7001) | EACH | 25 | $3,500.00 | $1,675.27 | $1,773.10 | $6,575.00 | $2,500.00 | $3,188.00 | $4,637.00 |
| 101 | Pedestrian detect push button (APS) (688-7001) | EACH | 40 | $1,500.00 | $1,710.83 | $1,081.46 | $1,250.00 | $1,850.00 | $1,625.00 | $1,058.00 |
| 102 | Pedestrian detector controller unit (688-7003) | EACH | 6 | $5,000.00 | $4,124.36 | $4,174.27 | $6,100.00 | $8,500.00 | $4,891.00 | $4,521.00 |
| 103 | VIVDS cam assy (install only) (6006-7010) | EACH | 7 | $1,800.00 | $887.18 | $722.03 | $2,200.00 | $3,500.00 | $2,205.00 | $1,333.00 |
| 104 | VIVDS cabling (install only) (6006-7012) | LF | 2,105 | $3.00 | $4.78 | $0.87 | $2.00 | $3.00 | $7.40 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.