TxDOT contract A00194399 bid tabulation
Hazard Elimination & Safety, BOSQUE (0.1 Mi S of Wooded Acres to 0.1 mi N of 34th St.). Let by Texas DOT on August 5, 2026, McLennan, Waco District. 4 bids received; low bid $1,517,538 by Vaca Underground Utilities Inc, -18% against the engineer's estimate of $1,849,456.
- Owner
- Texas DOT
- Letting
- 05 AUG 2026
- Pay items
- 99
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Vaca Underground Utilities Inc | $1,517,538 | Low | -18% |
| 2 | E-Z Bel Construction, LLC | $1,934,459 | +27% | +5.0% |
| 3 | Florida Traffic Control Devices, Inc. | $2,195,195 | +45% | +19% |
| 4 | Road Solutions L.L.C. | $2,308,121 | +52% | +25% |
Engineer's estimate: $1,849,456.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Vaca Underground Utilities Inc | 2. E-Z Bel Construction, LLC | 3. Florida Traffic Control Devices, Inc. | 4. Road Solutions L.L.C. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (driveways) (104-7011) | SY | 72 | $27.86 | $25.00 | $50.00 | $76.30 | $25.00 |
| 2 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 118 | $41.80 | $25.00 | $50.00 | $64.00 | $60.00 |
| 3 | Removing concrete (curb ramp) (104-7015) | SY | 62 | $250.00 | $55.00 | $50.00 | $105.00 | $50.00 |
| 4 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 50 | $35.00 | $15.00 | $50.00 | $40.00 | $28.00 |
| 5 | Removing concrete (retaining walls) (104-7025) | SY | 6 | $105.00 | $750.00 | $200.00 | $185.00 | $77.00 |
| 6 | Removing concrete (flume) (104-7041) | SY | 10 | $39.80 | $25.00 | $200.00 | $117.00 | $68.00 |
| 7 | Block sodding (162-7002) | SY | 115 | $5.00 | $25.00 | $25.00 | $25.00 | $6.57 |
| 8 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 117 | $435.00 | $250.00 | $500.00 | $604.00 | $549.00 |
| 9 | Class B concrete (flume) (420-7010) | CY | 2 | $1,215.00 | $1,500.00 | $1,500.00 | $1,540.00 | $915.47 |
| 10 | Retaining wall (cast-in-place) (423-7016) | SF | 80 | $50.00 | $775.00 | $90.00 | $203.00 | $125.00 |
| 11 | Grate (471-7001) | EACH | 1 | $2,000.00 | $3,250.00 | $5,000.00 | $6,165.00 | $3,275.00 |
| 12 | Adjusting manholes (utility box) (479-7004) | EACH | 1 | $800.00 | $800.00 | $1,000.00 | $757.00 | $1,002.00 |
| 13 | Mobilization (500-7001) | LS | 1 | $130,000 | $80,000 | $190,000 | $200,000 | $240,000 |
| 14 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $2,000.00 | $3,500.00 | $4,500.00 | $12,115 | $6,176.78 |
| 15 | Portable changeable message sign (503-7001) | DAY | 80 | $134.00 | $65.00 | $100.00 | $180.00 | $127.04 |
| 16 | TMA (stationary) (505-7001) | DAY | 150 | $285.00 | $90.00 | $300.00 | $87.00 | $340.00 |
| 17 | TMA (mobile operation) (505-7002) | HR | 80 | $86.00 | $50.00 | $0.01 | $87.00 | $68.99 |
| 18 | Temporary sediment control fence (install) (506-7039) | LF | 1,000 | $6.00 | $1.00 | $4.00 | $4.75 | $3.71 |
| 19 | Temporary sediment control fence (remove) (506-7041) | LF | 1,000 | $2.00 | $1.00 | $1.00 | $2.10 | $1.04 |
| 20 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 150 | $9.00 | $1.00 | $4.00 | $13.50 | $5.67 |
| 21 | Biodegradable erosion control logs (remove) (506-7046) | LF | 150 | $3.00 | $1.00 | $1.00 | $6.00 | $1.31 |
| 22 | Concrete curb (type II) (529-7002) | LF | 296 | $35.00 | $28.00 | $85.00 | $210.00 | $50.00 |
| 23 | Concrete curb & gutter (type II) (529-7009) | LF | 372 | $77.00 | $28.00 | $125.00 | $228.00 | $58.00 |
| 24 | Concrete sidewalks (4") (531-7001) | SY | 409 | $122.00 | $70.00 | $110.00 | $180.00 | $95.00 |
| 25 | Curb ramps (type 1) (531-7005) | EACH | 30 | $3,411.00 | $2,500.00 | $2,800.00 | $4,800.00 | $4,500.00 |
| 26 | Curb ramps (type 5) (531-7008) | EACH | 13 | $4,667.00 | $3,300.00 | $6,500.00 | $5,045.00 | $4,500.00 |
| 27 | Curb ramps (type 21) (531-7013) | EACH | 4 | $3,500.00 | $3,200.00 | $5,000.00 | $6,090.00 | $4,500.00 |
| 28 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 1,325 | $20.00 | $12.00 | $20.00 | $15.50 | $20.00 |
| 29 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 720 | $29.00 | $12.00 | $23.00 | $17.35 | $23.00 |
| 30 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 90 | $25.00 | $13.00 | $30.00 | $16.40 | $21.00 |
| 31 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 2,615 | $65.00 | $19.00 | $38.00 | $27.55 | $43.00 |
| 32 | Electrical conductor (no.8) bare (620-7007) | LF | 2,352 | $2.10 | $2.00 | $2.50 | $1.80 | $2.00 |
| 33 | Electrical conductor (no.8) insulated (620-7008) | LF | 3,970 | $2.20 | $2.15 | $3.00 | $2.25 | $2.10 |
| 34 | Electrical conductor (no.6) bare (620-7009) | LF | 170 | $4.50 | $2.30 | $5.00 | $2.20 | $2.27 |
| 35 | Electrical conductor (no.6) insulated (620-7010) | LF | 340 | $5.30 | $2.75 | $5.00 | $2.80 | $2.38 |
| 36 | Ground box type D (162922)W/apron (624-7008) | EACH | 30 | $1,950.00 | $1,500.00 | $1,900.00 | $2,080.00 | $1,800.00 |
| 37 | Elc SRV type D 120/240 060(NS)SS(E)PS(U) (628-7147) | EACH | 5 | $8,150.00 | $7,000.00 | $9,000.00 | $9,545.00 | $11,000 |
| 38 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 1 | $550.00 | $500.00 | $1,500.00 | $918.00 | $983.40 |
| 39 | Remove SM RD SN sup&AM (644-7073) | EACH | 1 | $150.00 | $260.00 | $300.00 | $667.00 | $115.65 |
| 40 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 2,126 | $2.50 | $1.50 | $1.20 | $1.50 | $1.49 |
| 41 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 2,570 | $12.00 | $8.75 | $7.00 | $8.60 | $11.45 |
| 42 | Reflectorized pavement marking type II (Y)(curb) (666-7221) | LF | 56 | $0.20 | $3.50 | $3.00 | $3.70 | $3.10 |
| 43 | Pavement sler 6" (666-7347) | LF | 4,532 | $0.50 | $0.25 | $0.20 | $0.25 | $0.79 |
| 44 | Pavement sler 8" (666-7348) | LF | 2,126 | $1.50 | $0.60 | $0.45 | $0.55 | $1.44 |
| 45 | Pavement sler 24" (666-7352) | LF | 2,570 | $4.50 | $1.25 | $1.00 | $1.25 | $3.37 |
| 46 | Pavement sler (arrow) (666-7353) | EACH | 45 | $50.00 | $50.00 | $40.00 | $49.00 | $51.75 |
| 47 | Pavement sler (word) (666-7354) | EACH | 23 | $58.00 | $56.00 | $45.00 | $55.00 | $137.60 |
| 48 | Pavement sler (double arrow) (666-7356) | EACH | 5 | $58.00 | $62.00 | $50.00 | $61.00 | $53.00 |
| 49 | Pavement sler (bike arrow) (666-7368) | EACH | 1 | $14.00 | $37.00 | $30.00 | $36.00 | $50.00 |
| 50 | Pavement sler (bike symbol) (666-7369) | EACH | 1 | $30.00 | $55.50 | $45.00 | $55.00 | $50.00 |
| 51 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 150 | $1.80 | $2.50 | $2.00 | $2.50 | $0.92 |
| 52 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 4,382 | $1.60 | $2.50 | $2.00 | $2.50 | $0.92 |
| 53 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 45 | $264.00 | $275.00 | $225.00 | $277.00 | $289.22 |
| 54 | Prefabricated PM type C (W)(double arrow) (668-7093) | EACH | 5 | $433.00 | $500.00 | $395.00 | $485.00 | $257.50 |
| 55 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 23 | $320.00 | $340.00 | $275.00 | $338.00 | $327.71 |
| 56 | Prefabricated PM type C (W)(bike arrow) (668-7113) | EACH | 1 | $142.00 | $145.00 | $115.00 | $142.15 | $155.00 |
| 57 | Prefabricated PM type C (W)(bike symbol) (668-7115) | EACH | 1 | $232.00 | $300.00 | $250.00 | $307.00 | $250.00 |
| 58 | Eliminating existing PM & markers (24") (677-7008) | LF | 3,685 | $5.00 | $7.25 | $6.25 | $7.70 | $5.66 |
| 59 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 40 | $100.00 | $60.00 | $50.00 | $61.00 | $87.13 |
| 60 | Eliminating existing PM & markers (double arrow) (677-7010) | EACH | 5 | $115.00 | $80.00 | $70.00 | $86.00 | $75.00 |
| 61 | Eliminating existing PM & markers (word) (677-7015) | EACH | 21 | $100.00 | $75.00 | $65.00 | $80.00 | $87.55 |
| 62 | Pavement surface preparation for marking (6") (678-7002) | LF | 4,532 | $0.60 | $1.15 | $1.00 | $1.25 | $0.72 |
| 63 | Pavement surface preparation for marking (8") (678-7004) | LF | 2,126 | $0.15 | $1.75 | $1.50 | $1.85 | $0.78 |
| 64 | Pavement surface preparation for marking (24") (678-7008) | LF | 2,570 | $1.60 | $2.30 | $2.00 | $2.45 | $4.20 |
| 65 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 45 | $34.00 | $34.00 | $30.00 | $37.00 | $61.70 |
| 66 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 5 | $29.00 | $46.00 | $40.00 | $50.00 | $35.00 |
| 67 | Pavement surface preparation for marking (word) (678-7016) | EACH | 23 | $37.00 | $40.00 | $35.00 | $43.00 | $18.20 |
| 68 | Pavement surface preparation for marking (bike arrow) (678-7026) | EACH | 1 | $14.00 | $23.00 | $20.00 | $25.00 | $35.00 |
| 69 | Pavement surface preparation for marking (bike symbol) (678-7028) | EACH | 1 | $57.00 | $43.00 | $35.00 | $43.00 | $32.00 |
| 70 | Install highway traffic signal (system) (680-7003) | EACH | 5 | $22,000 | $35,000 | $33,000 | $34,240 | $58,000 |
| 71 | Removing traffic signals (680-7004) | EACH | 5 | $5,000.00 | $4,000.00 | $6,000.00 | $4,410.00 | $12,500 |
| 72 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 63 | $360.00 | $330.00 | $375.00 | $350.00 | $469.60 |
| 73 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 20 | $360.00 | $330.00 | $375.00 | $350.00 | $467.30 |
| 74 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 63 | $375.00 | $330.00 | $375.00 | $350.00 | $475.60 |
| 75 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 38 | $330.00 | $330.00 | $375.00 | $350.00 | $385.38 |
| 76 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 64 | $372.00 | $330.00 | $375.00 | $350.00 | $469.60 |
| 77 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 18 | $330.00 | $330.00 | $375.00 | $350.00 | $392.88 |
| 78 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 40 | $875.00 | $900.00 | $700.00 | $782.00 | $951.00 |
| 79 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 62 | $215.00 | $180.00 | $150.00 | $253.00 | $225.00 |
| 80 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 20 | $266.00 | $190.00 | $185.00 | $266.00 | $345.00 |
| 81 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 2,239 | $3.00 | $1.75 | $2.00 | $2.60 | $2.87 |
| 82 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 1,566 | $4.00 | $4.00 | $3.00 | $4.25 | $3.30 |
| 83 | Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042) | LF | 3,305 | $8.50 | $7.00 | $6.00 | $6.55 | $5.32 |
| 84 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 6,677 | $2.70 | $2.75 | $2.00 | $2.45 | $2.20 |
| 85 | Ins traffic signal PL AM(S)1 arm(24')lum (686-7027) | EACH | 2 | $12,000 | $12,500 | $13,000 | $12,350 | $15,370 |
| 86 | Ins traffic signal PL AM(S)1 arm(36') (686-7037) | EACH | 1 | $14,500 | $12,500 | $13,000 | $12,720 | $14,558 |
| 87 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 1 | $15,300 | $14,250 | $15,000 | $14,825 | $19,212 |
| 88 | Ins traffic signal PL AM(S)1 arm(40') (686-7041) | EACH | 2 | $14,700 | $13,000 | $13,000 | $14,310 | $15,210 |
| 89 | Ins traffic signal PL AM(S)1 arm(40')lum (686-7043) | EACH | 1 | $17,000 | $15,000 | $15,000 | $16,130 | $19,880 |
| 90 | Ins traffic signal PL AM(S)1 arm(48') (686-7049) | EACH | 1 | $16,100 | $14,000 | $15,000 | $15,165 | $24,210 |
| 91 | Ins traffic signal PL AM(S)1 arm(48')lum (686-7051) | EACH | 1 | $17,800 | $16,000 | $17,000 | $17,230 | $28,170 |
| 92 | Pedestrian pole assembly (687-7001) | EACH | 25 | $3,500.00 | $3,000.00 | $4,000.00 | $4,875.00 | $3,700.00 |
| 93 | Pedestrian detect push button (APS) (688-7001) | EACH | 40 | $1,300.00 | $750.00 | $1,100.00 | $1,033.00 | $850.00 |
| 94 | Pedestrian detector controller unit (688-7003) | EACH | 5 | $350.00 | $3,000.00 | $4,000.00 | $3,815.00 | $4,187.50 |
| 95 | VIVDS prosr sys (6006-7001) | EACH | 5 | $8,500.00 | $11,000 | $11,000 | $14,265 | $15,000 |
| 96 | VIVDS cam assy FXD LNS (6006-7002) | EACH | 20 | $5,700.00 | $3,500.00 | $5,000.00 | $3,860.00 | $4,500.00 |
| 97 | VIVDS cabling (6006-7007) | LF | 4,065 | $4.40 | $3.00 | $2.00 | $2.00 | $3.00 |
| 98 | Subsurface util locate (outside rdbed) (7019-7001) | EACH | 20 | $650.00 | $750.00 | $1,000.00 | $1,010.00 | $1,800.00 |
| 99 | Subsurface util locate (within rdbed) (7019-7002) | EACH | 20 | $720.00 | $750.00 | $1,000.00 | $1,010.00 | $2,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.