TxDOT contract A00195528 bid tabulation
Rehabilitate Existing Roadway, FM 1269 (Garza County to FM 612). Let by Texas DOT on April 3, 2025, Scurry, Abilene District. 4 bids received; low bid $5,573,029 by CK Newberry, LLC, -27% against the engineer's estimate of $7,639,239.
- Owner
- Texas DOT
- Letting
- 03 APR 2025
- Pay items
- 55
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | CK Newberry, LLC | $5,573,029 | Low | -27% |
| 2 | A. L. Helmcamp, Inc. | $5,894,624 | +6.0% | -23% |
| 3 | RK Hall, LLC | $6,274,117 | +13% | -18% |
| 4 | Duininck, Inc. | $6,521,491 | +17% | -15% |
Engineer's estimate: $7,639,239.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. CK Newberry, LLC | 2. A. L. Helmcamp, Inc. | 3. RK Hall, LLC | 4. Duininck, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 6 | $3,800.00 | $3,000.00 | $5,000.00 | $6,941.67 | $2,100.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 24 | $150.00 | $215.00 | $80.00 | $33.00 | $31.50 |
| 3 | Embankment (final)(OC)(type A) (132-7001) | CY | 154 | $75.00 | $135.00 | $80.00 | $33.00 | $31.50 |
| 4 | Backfill (type A) (134-7001) | STA | 263.84 | $350.00 | $325.00 | $325.00 | $239.98 | $155.00 |
| 5 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 62,312 | $0.33 | $0.20 | $0.16 | $0.17 | $0.16 |
| 6 | Broadcast seed (temporary_warm) (164-7005) | SY | 31,156 | $0.20 | $0.20 | $0.26 | $0.14 | $0.14 |
| 7 | Broadcast seed (temporary_cool) (164-7006) | SY | 31,156 | $0.20 | $0.20 | $0.19 | $0.20 | $0.19 |
| 8 | Vegetative watering (168-7001) | TGL | 88 | $50.00 | $25.00 | $40.00 | $137.16 | $50.00 |
| 9 | Proof rolling (216-7001) | HR | 16 | $148.00 | $75.00 | $180.00 | $250.00 | $260.00 |
| 10 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 4,240 | $90.00 | $85.00 | $87.00 | $38.50 | $36.50 |
| 11 | Cement (275-7001) | TON | 1,145 | $330.00 | $280.00 | $250.00 | $310.16 | $260.00 |
| 12 | Cement TRT (existing material)(12") (275-7005) | SY | 468 | $6.50 | $9.00 | $5.60 | $4.68 | $4.45 |
| 13 | Cement TRT (existing material & new base)(8") (275-7007) | SY | 75,840 | $8.00 | $3.00 | $5.00 | $6.99 | $6.65 |
| 14 | Asphalt (RC-250) (316-7016) | GAL | 19,077 | $7.00 | $5.10 | $5.00 | $5.61 | $6.00 |
| 15 | Aggregate (type-B, GR-5)(sac-B) (316-7175) | CY | 611 | $180.00 | $159.00 | $180.00 | $201.46 | $260.00 |
| 16 | D-GR HMA type D PG70-22 (341-7048) | TON | 18,602 | $200.00 | $141.00 | $155.00 | $144.43 | $175.00 |
| 17 | Tack coat (341-7082) | GAL | 16,905 | $5.00 | $4.50 | $5.00 | $4.86 | $2.50 |
| 18 | Flexible pavement structure repair(4") (351-7003) | SY | 311 | $45.00 | $71.00 | $95.00 | $137.33 | $110.00 |
| 19 | Flexible pavement structure repair(6") (351-7005) | SY | 468 | $60.00 | $100.00 | $130.00 | $152.58 | $125.00 |
| 20 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 1,011 | $10.00 | $7.00 | $14.00 | $12.50 | $14.50 |
| 21 | Riprap (concrete)(5 in) (432-7002) | CY | 121 | $700.00 | $685.00 | $850.00 | $907.50 | $750.00 |
| 22 | Riprap (mow strip)(4 in) (432-7013) | CY | 288 | $700.00 | $735.00 | $800.00 | $907.50 | $750.00 |
| 23 | Mobilization (500-7001) | LS | 1 | $713,380 | $550,000 | $445,000 | $580,083 | $625,000 |
| 24 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $25,000 | $22,000 | $12,000 | $50,000 | $40,000 |
| 25 | TMA (stationary) (505-7001) | DAY | 158 | $350.00 | $325.00 | $150.00 | $150.00 | $260.00 |
| 26 | TMA (mobile operation) (505-7003) | DAY | 18 | $450.00 | $325.00 | $150.00 | $300.00 | $945.00 |
| 27 | Temporary sediment control fence (install) (506-7039) | LF | 1,305 | $6.50 | $7.44 | $3.40 | $3.58 | $3.40 |
| 28 | Temporary sediment control fence (remove) (506-7041) | LF | 1,305 | $1.30 | $2.00 | $1.00 | $1.10 | $1.05 |
| 29 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 320 | $10.00 | $14.00 | $7.00 | $7.38 | $7.05 |
| 30 | Biodegradable erosion control logs (remove) (506-7046) | LF | 320 | $1.50 | $2.00 | $1.00 | $1.10 | $1.05 |
| 31 | Driveways (base) (530-7015) | SY | 2,309 | $30.00 | $12.00 | $30.00 | $21.93 | $19.00 |
| 32 | Driveways (surface treat) (530-7016) | SY | 5,152 | $45.00 | $10.00 | $30.00 | $27.27 | $24.50 |
| 33 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 56,700 | $0.30 | $0.15 | $0.17 | $0.15 | $0.10 |
| 34 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 28,350 | $0.30 | $0.15 | $0.17 | $0.15 | $0.15 |
| 35 | Metal W-beam guard fence (timber post) (540-7001) | LF | 4,015 | $30.00 | $29.00 | $24.00 | $28.05 | $24.00 |
| 36 | Remove metal beam guard fence (542-7001) | LF | 3,990 | $2.70 | $2.00 | $2.20 | $2.75 | $2.10 |
| 37 | Remove terminal anchor section (542-7002) | EACH | 10 | $200.00 | $220.00 | $320.00 | $275.00 | $315.00 |
| 38 | Guardrail end treatment (install) (544-7001) | EACH | 10 | $4,000.00 | $3,850.00 | $3,300.00 | $3,520.00 | $3,300.00 |
| 39 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 51 | $750.00 | $780.00 | $700.00 | $825.00 | $660.00 |
| 40 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 4 | $1,200.00 | $950.00 | $740.00 | $935.00 | $735.00 |
| 41 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 1 | $1,200.00 | $1,125.00 | $900.00 | $962.50 | $890.00 |
| 42 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 2 | $1,300.00 | $1,000.00 | $900.00 | $1,078.00 | $890.00 |
| 43 | Remove SM RD SN sup&AM (644-7073) | EACH | 55 | $110.00 | $140.00 | $110.00 | $110.00 | $105.00 |
| 44 | Install delineator assembly (D-SW)SZ 2(WC)GND (658-7009) | EACH | 17 | $55.00 | $90.00 | $65.00 | $71.50 | $63.00 |
| 45 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 42 | $40.00 | $25.00 | $44.00 | $36.30 | $44.00 |
| 46 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 3 | $200.00 | $140.00 | $65.00 | $82.50 | $63.00 |
| 47 | Remove delin & object marker assms (658-7078) | EACH | 17 | $20.00 | $30.00 | $22.00 | $16.50 | $21.00 |
| 48 | Work zone pavement marking removing (Y)6"(broken) (662-7098) | LF | 5,360 | $2.50 | $1.70 | $0.21 | $0.24 | $0.23 |
| 49 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 13,881 | $1.10 | $1.00 | $0.21 | $0.24 | $0.23 |
| 50 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 7,440 | $1.70 | $0.75 | $1.50 | $3.68 | $1.55 |
| 51 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 59,614 | $1.10 | $0.75 | $0.55 | $0.57 | $0.55 |
| 52 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 5,360 | $1.00 | $0.80 | $0.55 | $0.57 | $0.55 |
| 53 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 24,441 | $1.00 | $0.75 | $0.55 | $0.57 | $0.55 |
| 54 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 68 | $18.00 | $20.00 | $16.00 | $16.50 | $15.50 |
| 55 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 573 | $5.50 | $6.00 | $4.50 | $4.68 | $4.45 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 3, 2025. Compiled by Mirage Metrics.