TxDOT contract A00196291 bid tabulation
Purchase And Install Signs & Equip, Various (Various Locations on IH 410 to .). Let by Texas DOT on May 1, 2025, Bexar, San Antonio District. 3 bids received; low bid $2,368,226 by Dan Williams Company, -14% against the engineer's estimate of $2,761,060.
- Owner
- Texas DOT
- Letting
- 01 MAY 2025
- Pay items
- 32
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Dan Williams Company | $2,368,226 | Low | -14% |
| 2 | BK Field Operations LLC | $2,616,677 | +10% | -5.0% |
| 3 | Aaron Concrete Contractors, LLC | $2,980,282 | +26% | +8.0% |
Engineer's estimate: $2,761,060.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Dan Williams Company | 2. BK Field Operations LLC | 3. Aaron Concrete Contractors, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7003) | SY | 182 | $34.00 | $30.00 | $9.00 | $130.00 |
| 2 | Furn & place topsoil (4") (160-7002) | SY | 6,524 | $12.00 | $4.25 | $8.00 | $7.00 |
| 3 | Roll sodding (162-7008) | SY | 6,524 | $10.00 | $8.50 | $8.00 | $12.00 |
| 4 | Vegetative watering (168-7001) | TGL | 101.80 | $55.00 | $10.00 | $1.00 | $35.00 |
| 5 | Class C concrete (rail foundation) (420-7052) | CY | 743.40 | $750.00 | $575.00 | $550.00 | $900.00 |
| 6 | Rail (type SSTR) (450-7024) | LF | 4,030 | $105.00 | $80.00 | $225.00 | $130.00 |
| 7 | Rail (type T80PP) (450-7051) | LF | 1,120 | $255.00 | $150.00 | $425.00 | $175.00 |
| 8 | Mobilization (500-7001) | LS | 1 | $234,862 | $230,000 | $65,000 | $250,000 |
| 9 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $5,000.00 | $24,500 | $1.00 | $1,700.00 |
| 10 | Portable changeable message sign (503-7001) | DAY | 246 | $105.00 | $125.00 | $60.00 | $45.00 |
| 11 | TMA (stationary) (505-7001) | DAY | 128 | $500.00 | $175.00 | $1.00 | $200.00 |
| 12 | TMA (mobile operation) (505-7002) | HR | 14 | $110.00 | $70.00 | $400.00 | $115.00 |
| 13 | Construction exits (install) (type 1) (506-7020) | SY | 784 | $45.00 | $25.00 | $14.00 | $32.00 |
| 14 | Construction exits (remove) (506-7024) | SY | 784 | $15.00 | $8.00 | $5.00 | $5.00 |
| 15 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 12,214 | $7.50 | $4.00 | $4.00 | $7.00 |
| 16 | Biodegradable erosion control logs (remove) (506-7046) | LF | 12,214 | $2.00 | $1.00 | $1.00 | $1.50 |
| 17 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 1 | $2,500.00 | $3,500.00 | $5,000.00 | $3,200.00 |
| 18 | Remove metal beam guard fence (542-7001) | LF | 2,750 | $3.50 | $10.00 | $2.00 | $4.80 |
| 19 | Remove terminal anchor section (542-7002) | EACH | 19 | $1,200.00 | $500.00 | $250.00 | $540.00 |
| 20 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $325.00 | $500.00 | $250.00 | $340.00 |
| 21 | Guardrail end treatment (remove) (544-7003) | EACH | 19 | $500.00 | $500.00 | $100.00 | $340.00 |
| 22 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 21 | $30,000 | $32,000 | $23,000 | $40,000 |
| 23 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 2 | $950.00 | $2,000.00 | $2,000.00 | $1,780.00 |
| 24 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $200.00 | $200.00 | $500.00 | $180.00 |
| 25 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 34 | $20.00 | $45.00 | $10.00 | $18.00 |
| 26 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 58 | $20.00 | $45.00 | $10.00 | $18.00 |
| 27 | Litter removal (734-7002) | CYC | 8 | $2,500.00 | $500.00 | $4,000.00 | $5,500.00 |
| 28 | Debris removing-CNTR med/MN LNS/ramps (735-7001) | MI | 10.50 | $2,500.00 | $200.00 | $300.00 | $2,200.00 |
| 29 | Cleaning / sweeping (center median) (738-7004) | CYC | 8 | $2,500.00 | $1,000.00 | $500.00 | $2,400.00 |
| 30 | Cleaning / sweeping (outside main lane) (738-7028) | CYC | 8 | $2,500.00 | $1,000.00 | $500.00 | $2,400.00 |
| 31 | Cleaning / sweeping (frontage road) (738-7050) | CYC | 8 | $2,500.00 | $1,000.00 | $500.00 | $1,200.00 |
| 32 | Cleaning / sweeping(entrance/exit ramp) (738-7071) | CYC | 8 | $2,500.00 | $1,000.00 | $500.00 | $1,200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 1, 2025. Compiled by Mirage Metrics.