TxDOT contract A00197321 bid tabulation
Install Advanced Traffic Management System, Various (Various locations on US 290 along IH 35 to to LP1). Let by Texas DOT on June 4, 2025, Travis, Austin District. 7 bids received; low bid $619,888 by Elecnor Belco Electric, Inc., -38% against the engineer's estimate of $995,886.
- Owner
- Texas DOT
- Letting
- 04 JUN 2025
- Pay items
- 29
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Elecnor Belco Electric, Inc. | $619,888 | Low | -38% |
| 2 | Sice, Inc. | $843,828 | +36% | -15% |
| 3 | Light It Up Electric | $857,431 | +38% | -14% |
| 4 | Lumin8 Transportation Technologies, LLC | $1,037,767 | +67% | +4.0% |
| 5 | Florida Traffic Control Devices, Inc. | $1,051,600 | +70% | +6.0% |
| 6 | Austin Traffic Signal Construction Co., Inc. | $1,239,200 | +100% | +24% |
| 7 | The Levy Company, Inc. | $1,331,873 | +115% | +34% |
Engineer's estimate: $995,886.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Elecnor Belco Electric, Inc. | 2. Sice, Inc. | 3. Light It Up Electric | 4. Lumin8 Transportation Technologies, LLC | 5. Florida Traffic Control Devices, Inc. | 6. Austin Traffic Signal Construction Co., Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mobilization (500-7001) | LS | 1 | $50,000 | $23,438 | $82,861 | $72,000 | $5,944.00 | $105,000 | $90,000 |
| 2 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $4,000.00 | $3,500.00 | $11,219 | $13,000 | $3,943.00 | $7,100.00 | $15,000 |
| 3 | Portable changeable message sign (503-7001) | DAY | 5 | $149.57 | $195.00 | $1,554.11 | $200.00 | $907.00 | $170.00 | $800.00 |
| 4 | TMA (stationary) (505-7001) | DAY | 5 | $280.00 | $300.00 | $1,918.86 | $500.00 | $1,152.00 | $170.00 | $500.00 |
| 5 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 100 | $8.00 | $11.00 | $7.02 | $7.00 | $41.00 | $29.60 | $11.00 |
| 6 | Biodegradable erosion control logs (remove) (506-7046) | LF | 100 | $3.00 | $5.00 | $2.16 | $2.00 | $18.00 | $7.40 | $5.00 |
| 7 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 200 | $25.00 | $28.00 | $52.34 | $35.00 | $30.00 | $18.90 | $45.00 |
| 8 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 600 | $29.00 | $34.00 | $56.53 | $38.00 | $32.00 | $25.40 | $55.00 |
| 9 | Electrical conductor (no.6) bare (620-7009) | LF | 865 | $2.80 | $3.00 | $1.82 | $3.00 | $3.60 | $2.10 | $4.00 |
| 10 | Electrical conductor (no.6) insulated (620-7010) | LF | 1,730 | $3.10 | $3.00 | $1.38 | $3.35 | $4.00 | $2.65 | $5.00 |
| 11 | Ground box type D (162922) (624-7007) | EACH | 1 | $1,500.00 | $1,500.00 | $3,680.93 | $1,350.00 | $1,342.00 | $809.50 | $4,000.00 |
| 12 | Removal of cables (690-7009) | LF | 2,820 | $1.90 | $1.00 | $0.79 | $2.50 | $2.00 | $1.20 | $2.00 |
| 13 | Removal of control cabinet(GRND MNT) (690-7038) | EACH | 6 | $750.00 | $1,000.00 | $10,087 | $1,500.00 | $2,828.00 | $1,163.00 | $2,000.00 |
| 14 | Replace underground conduit (690-7148) | LF | 1,500 | $27.00 | $6.80 | $27.70 | $35.00 | $51.00 | $18.80 | $100.00 |
| 15 | System integration (6009-7001) | LS | 1 | $50,000 | $10,000 | $50,800 | $33,000 | $30,790 | $19,500 | $15,000 |
| 16 | Ground box (prepare) (6013-7006) | EACH | 3 | $750.00 | $230.00 | $612.71 | $500.00 | $2,910.00 | $1,650.00 | $1,500.00 |
| 17 | Ground box (adjust) (6013-7007) | EACH | 1 | $750.00 | $455.00 | $3,797.88 | $2,000.00 | $5,760.00 | $500.00 | $1,000.00 |
| 18 | Cover (replace) (6013-7009) | EACH | 31 | $700.00 | $350.00 | $257.90 | $800.00 | $6,681.00 | $410.00 | $6,500.00 |
| 19 | CCTV field equipment (digital) (6018-7002) | EACH | 12 | $7,500.00 | $9,800.00 | $7,878.31 | $8,500.00 | $12,905 | $9,410.00 | $8,000.00 |
| 20 | Fiber optic CBL (single-mode)(12 fiber) (6027-7001) | LF | 7,670 | $4.30 | $2.50 | $4.00 | $2.00 | $2.62 | $6.75 | $5.00 |
| 21 | Fiber optic patch panel (12 position) (6027-7005) | EACH | 17 | $1,397.00 | $1,400.00 | $1,032.29 | $2,000.00 | $1,664.00 | $2,460.00 | $2,500.00 |
| 22 | Fiber optic patch panel (36 positions) (6027-7007) | EACH | 5 | $2,873.00 | $3,300.00 | $3,000.49 | $2,700.00 | $3,707.00 | $7,830.00 | $3,500.00 |
| 23 | Fiber optic patch panel (144 positions) (6027-7008) | EACH | 13 | $7,000.00 | $8,100.00 | $7,362.86 | $3,500.00 | $11,655 | $24,010 | $8,000.00 |
| 24 | Wireless WWD system (6028-7001) | EACH | 1 | $30,000 | $60,000 | $74,070 | $50,000 | $80,445 | $65,815 | $84,000 |
| 25 | WWD LED sign (6028-7002) | EACH | 2 | $10,000 | $11,000 | $3,707.05 | $9,900.00 | $10,294 | $11,985 | $6,000.00 |
| 26 | Preventive maintenance (6029-7001) | EACH | 5 | $2,000.00 | $2,500.00 | $1,184.02 | $1,500.00 | $3,853.00 | $2,910.00 | $9,000.00 |
| 27 | Ethernet switch (install only) (6036-7001) | EACH | 24 | $1,000.00 | $1,300.00 | $180.26 | $400.00 | $770.00 | $1,040.00 | $1,000.00 |
| 28 | Remove and replace DMS (6054-7001) | EACH | 6 | $70,000 | $14,000 | $15,817 | $38,000 | $13,244 | $17,310 | $21,000 |
| 29 | Remove existing lane control system (6080-7001) | EACH | 2 | $2,900.00 | $1,500.00 | $7,258.95 | $4,200.00 | $6,180.00 | $2,600.00 | $7,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.