TxDOT contract A00197422 bid tabulation

Resurface Roadway, US 57 (Zavala/Frio County Line to FM 140). Let by Texas DOT on August 5, 2026, Frio, San Antonio District. 6 bids received; low bid $7,430,847 by Clark Construction of Texas, Inc., -14% against the engineer's estimate of $8,663,166.

Owner
Texas DOT
Letting
05 AUG 2026
Pay items
73
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Clark Construction of Texas, Inc.$7,430,847Low-14%
2Hunter Industries, LTD.$7,521,170+1.0%-13%
3Anderson Columbia Co., Inc.$8,532,310+15%-2.0%
4Lone Star Paving Company$8,989,700+21%+4.0%
5Texas Materials Group, Inc.$8,993,047+21%+4.0%
6CK Newberry, LLC$9,680,425+30%+12%
TxDOT contract A00197422: bids by rank

Engineer's estimate: $8,663,166.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Clark Construction of Texas, Inc.2. Hunter Industries, LTD.3. Anderson Columbia Co., Inc.4. Lone Star Paving Company5. Texas Materials Group, Inc.6. CK Newberry, LLC
1Preparing row (100-7002)STA5$1,800.00$1,500.00$1,894.20$2,000.00$2,500.00$2,900.00$1,000.00
2Backfill (type A) (134-7001)STA7.68$231.00$150.00$115.50$500.00$325.00$520.00$700.00
3Compost manuf topsoil (4") (161-7002)SY3,113$2.00$2.00$2.74$4.00$4.00$3.90$3.25
4Drill seed (permanent_rural_sand) (164-7009)SY3,113$0.25$4.00$0.80$0.84$3.00$0.80$0.50
5Drill seed (temporary_warm_cool) (164-7015)SY3,113$0.25$4.00$0.70$0.74$1.00$0.70$0.50
6Vegetative watering (168-7001)TGL48.60$24.00$50.00$22.96$45.00$50.00$65.00$50.00
7D-GR HMA type D PG76-22 (341-7056)TON28,281$121.00$104.56$91.36$108.00$117.00$103.00$110.00
8D-GR HMA type D PG76-22 (level-UP) (341-7059)TON4,017$99.00$129.35$90.58$114.00$136.00$119.00$140.00
9Tom-C PG76-22 sac-B (347-7002)TON17,580$121.00$130.12$103.18$127.00$146.00$147.00$135.00
10Flexible pavement structure repair(5") (351-7004)SY16,951$35.00$36.36$33.51$38.00$42.00$37.50$45.00
11Planing asphalt concrete pavement(0" to 0.5") (354-7030)SY213,355$0.30$0.26$0.55$0.80$0.75$0.56$1.10
12Planing asphalt concrete pavement (2.5") (354-7082)SY26,860$1.40$2.25$1.43$2.30$2.85$2.55$2.00
13Planing asphalt concrete pavement (0" to 2-1/2") (354-7083)SY9,054$1.40$2.50$1.43$2.30$2.10$1.70$1.00
14Flowable fill (embankment) (401-7002)CY5$500.00$250.00$1,100.00$300.00$500.00$1,200.00$1,000.00
15Riprap (mow strip)(4 in) (432-7013)CY38$700.00$695.00$650.00$675.00$605.00$605.00$700.00
16Set (type II) (24 in) (CMP) (6: 1) (P) (467-7324)EACH4$2,860.00$2,400.00$3,600.00$2,200.00$2,295.00$2,295.00$3,500.00
17Set (type II) (des 2) (CMP) (6: 1) (P) (467-7422)EACH4$2,860.00$2,800.00$3,100.00$2,700.00$3,187.50$3,190.00$3,000.00
18Set (type II) (des 3) (CMP) (6: 1) (P) (467-7430)EACH4$2,860.00$3,200.00$3,855.00$3,400.00$3,187.50$3,190.00$3,200.00
19Clean existing culverts (480-7001)EACH25$2,500.00$500.00$2,300.00$4,500.00$2,905.00$2,905.00$3,000.00
20Mobilization (500-7001)LS1$401,163$211,000$534,678$400,000$605,000$785,000$900,000
21Barricades, signs and traffic handling (502-7001)MO13$2,000.00$2,165.00$3,290.52$2,500.00$10,100$2,600.00$5,000.00
22Portable changeable message sign (503-7001)DAY412$80.00$86.00$27.06$40.00$75.00$25.00$50.00
23TMA (stationary) (505-7001)DAY227$208.00$115.00$81.19$300.00$150.00$25.00$300.00
24TMA (mobile operation) (505-7003)DAY96$242.00$115.00$119.08$650.00$150.00$50.00$25.00
25Biodegradable erosion control logs (install) (8") (506-7043)LF720$5.00$8.00$7.25$7.65$6.00$7.25$6.50
26Biodegradable erosion control logs (remove) (506-7046)LF720$1.00$1.00$2.00$2.10$1.00$2.00$2.00
27One-way traffic control (flagger cont) (510-7001)HR510$65.00$1.00$77.00$20.00$25.00$60.00$40.00
28One-way traffic control (pilot car) (510-7002)HR2,060$90.00$1.00$93.50$50.00$25.00$145.00$150.00
29Driveways (ACP) (530-7010)SY2,055$64.00$32.34$22.20$41.00$41.00$34.00$20.00
30Mill rumble strips (asphalt) (shoulder) (533-7001)LF116,390$0.15$0.16$0.07$0.15$0.13$0.17$0.15
31Mill rumble strips (asphalt) (centerline) (533-7002)LF56,160$0.15$0.16$0.10$0.17$0.16$0.17$0.15
32Metal W-beam guard fence (timber post) (540-7001)LF350$28.00$40.00$25.75$28.00$35.00$25.75$30.00
33Remove metal beam guard fence (542-7001)LF434$6.00$4.00$1.75$2.00$3.00$1.75$2.00
34Remove terminal anchor section (542-7002)EACH4$220.00$350.00$125.00$140.00$500.00$125.00$135.00
35Guardrail end treatment (install) (544-7001)EACH4$3,700.00$3,500.00$3,650.00$3,800.00$5,000.00$3,650.00$4,000.00
36Replace existing aluminum signs(type A) (636-7004)SF41$50.00$32.29$32.29$34.00$32.29$32.30$30.00
37Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH34$670.00$632.11$632.11$650.00$632.11$633.00$750.00
38Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH4$1,200.00$737.75$737.75$750.00$737.75$738.00$850.00
39Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH12$1,000.00$877.91$877.91$900.00$877.91$878.00$1,000.00
40Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH1$1,020.00$841.17$841.17$850.00$841.17$842.00$1,200.00
41Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH1$1,325.00$953.86$953.86$1,000.00$953.86$954.00$1,500.00
42Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032)EACH1$1,325.00$1,237.22$1,237.22$1,250.00$1,237.22$1,238.00$1,800.00
43Remove SM RD SN sup&AM (644-7073)EACH53$122.00$90.00$90.00$100.00$90.00$90.00$100.00
44Install delineator assembly (D-SW)SZ 1(WFLX)GF2 (658-7001)EACH6$40.00$21.85$25.00$24.00$21.85$22.00$22.00
45Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059)EACH69$80.00$85.00$85.00$90.00$85.00$85.00$85.00
46Remove delin & object marker assms (658-7078)EACH78$24.00$24.00$24.00$25.00$24.00$24.00$15.00
47Work zone pavement marking non-removing (W)6"(broken) (662-7005)LF11,114$0.25$0.22$0.22$0.23$0.22$0.22$0.25
48Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF177,004$0.25$0.19$0.19$0.20$0.19$0.19$0.20
49Work zone pavement marking non-removing (W)8"(solid) (662-7012)LF4,387$0.50$0.30$0.30$0.32$0.30$0.30$0.30
50Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF94$15.00$3.00$3.00$3.10$3.00$3.00$3.00
51Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF6,232$0.30$0.20$0.20$0.21$0.20$0.20$0.20
52Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF198,531$0.25$0.21$0.21$0.22$0.21$0.21$0.25
53Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH38,671$1.00$0.58$1.19$1.50$1.00$1.39$0.55
54Work zone pavement marking SHT terminal (tab)type Y (662-7113)EACH28,455$1.00$0.58$1.19$1.50$1.00$1.39$0.55
55Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF2,018$1.00$0.87$0.87$0.92$0.87$0.87$0.90
56Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF56$12.00$3.79$3.79$4.00$3.79$3.79$4.00
57Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH18$175.00$146.13$146.13$150.00$146.13$147.00$150.00
58Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH10$200.00$176.00$176.00$180.00$176.00$176.00$190.00
59Ref pavement marking type I(W)18"(yld tri)(100MIL) (666-7087)EACH16$70.00$37.23$37.23$40.00$37.23$38.00$40.00
60Pavement sler 6" (666-7347)LF232,790$0.15$0.19$0.19$0.20$0.19$0.19$0.20
61Pavement sler 8" (666-7348)LF2,018$0.45$0.25$0.25$0.26$0.25$0.25$0.25
62Pavement sler 24" (666-7352)LF56$0.60$2.00$2.00$2.00$2.00$2.00$2.00
63Pavement sler (arrow) (666-7353)EACH18$45.00$47.20$47.20$50.00$47.20$47.20$50.00
64Pavement sler (word) (666-7354)EACH10$65.00$49.33$49.33$50.00$49.33$49.33$50.00
65Pavement sler (yld tri) (666-7365)EACH16$5.00$10.00$10.00$10.00$10.00$10.00$10.00
66Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF11,686$0.55$0.49$0.49$0.52$0.49$0.49$0.50
67Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF116,795$0.55$0.50$0.50$0.53$0.50$0.50$0.50
68Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF4,068$0.55$0.49$0.49$0.52$0.49$0.49$0.50
69Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF100,241$0.55$0.50$0.50$0.53$0.50$0.50$0.50
70Reflectorized pavement marker type I-C (672-7002)EACH502$3.70$3.49$3.49$4.00$3.49$3.50$3.50
71Reflectorized pavement marker type II-A-A (672-7004)EACH1,638$3.70$3.46$3.46$4.00$3.46$3.50$3.50
72Underseal course (3006-7001)GAL76,155$3.85$0.01$4.54$3.90$0.25$3.95$4.00
73Bonding course (3007-7001)GAL61,109$3.60$0.01$3.14$2.00$0.01$0.01$4.00
TxDOT contract A00197422: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy