TxDOT contract A00206735 bid tabulation

Hazard Elimination & Safety, HARRIS BRANCH PKWY (at Giles Ln to .). Let by Texas DOT on June 3, 2026, Travis, Austin District. 7 bids received; low bid $405,662 by E-Z Bel Construction, LLC, -21% against the engineer's estimate of $516,136.

Owner
Texas DOT
Letting
03 JUN 2026
Pay items
73
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1E-Z Bel Construction, LLC$405,662Low-21%
2Elecnor Belco Electric, Inc.$449,983+11%-13%
3Sice, Inc.$482,028+19%-7.0%
4Digg Commercial, LLC$497,835+23%-4.0%
5Austin Traffic Signal Construction Co., Inc.$527,562+30%+2.0%
6Florida Traffic Control Devices, Inc.$649,000+60%+26%
7Structural Integrity Group LLC$813,541+101%+58%
TxDOT contract A00206735: bids by rank

Engineer's estimate: $516,136.

Bid tabulation

LinePay itemUnitQuantityEstimate1. E-Z Bel Construction, LLC2. Elecnor Belco Electric, Inc.3. Sice, Inc.4. Digg Commercial, LLC5. Austin Traffic Signal Construction Co., Inc.6. Florida Traffic Control Devices, Inc.
1Removing concrete (pavement) (104-7001)SY269$25.00$15.00$9.00$68.59$12.00$60.00$26.75
2Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY148$37.00$31.00$7.50$50.40$18.00$53.00$32.70
3Removing concrete (curb) (104-7016)LF421$17.00$5.00$5.00$21.00$7.00$17.00$17.85
4Block sodding (162-7002)SY678$4.50$6.00$11.00$8.40$5.00$17.00$32.30
5Vegetative watering (168-7001)TGL10$175.00$345.00$537.00$28.00$40.00$275.00$3,232.00
6Drilled shaft (traffic signal pole) (48 in) (416-7046)LF52$625.00$600.00$495.00$701.63$350.00$600.00$707.00
7Mobilization (500-7001)LS1$50,650$36,000$42,000$46,336$20,000$43,000$64,900
8Barricades, signs and traffic handling (502-7001)MO5$5,000.00$1,150.00$6,814.00$5,968.05$2,500.00$4,500.00$3,538.00
9Portable changeable message sign (503-7001)DAY90$75.00$60.00$109.00$208.63$300.00$150.00$190.00
10TMA (stationary) (505-7001)DAY60$275.00$477.00$61.00$89.03$1,200.00$265.00$190.00
11Temporary SDMT cont fence (inlet protection) (506-7040)LF60$6.75$15.00$20.00$5.60$5.00$11.00$150.00
12Colored textured concrete (8") (528-7005)SY11.50$200.00$270.00$234.00$643.94$228.00$193.00$140.00
13Concrete curb (mono) (type II) (529-7007)LF482$11.50$24.00$27.00$42.00$6.00$52.00$44.60
14Concrete curb & gutter (type B) (mountable) (529-7024)LF53$50.00$25.00$30.00$68.59$15.00$52.00$66.00
15Concrete sidewalks (5") (531-7002)SY80$150.00$120.00$158.00$314.97$66.00$156.00$97.25
16Curb ramps (type 3) (531-7007)EACH2$3,250.00$2,100.00$2,337.00$1,819.83$1,200.00$4,500.00$5,725.00
17Curb ramps (type 7) (531-7010)EACH3$2,750.00$1,950.00$2,397.00$2,204.80$1,200.00$4,500.00$5,800.00
18Curb ramps (type 20) (531-7012)EACH3$5,500.00$4,750.00$2,778.00$4,094.62$1,200.00$5,500.00$6,915.00
19Curb ramps (type 22) (531-7014)EACH1$6,500.00$7,750.00$2,921.00$6,999.36$1,200.00$5,500.00$7,360.00
20Conduit (PVC) (schedule 40) (1/2") (618-7017)LF70$20.00$6.00$14.50$18.60$8.13$22.00$11.35
21Conduit (PVC) (schedule 40) (2") (618-7030)LF30$22.00$29.00$16.20$10.66$14.08$16.00$15.15
22Conduit (PVC) (schedule 40) (3") (618-7036)LF365$27.50$25.00$19.00$11.40$15.05$17.00$17.80
23Conduit (PVC) (schedule 40) (3") (bore) (618-7037)LF1,395$35.00$29.00$37.00$19.65$34.78$65.00$25.30
24Conduit (PVC) (schedule 40) (4") (618-7040)LF470$40.00$23.00$24.00$26.00$23.43$19.00$19.25
25Electrical conductor (no.8) insulated (620-7008)LF1,500$2.50$3.00$2.00$1.71$2.43$1.90$2.40
26Electrical conductor (no.6) bare (620-7009)LF2,130$3.75$2.00$2.50$1.85$2.89$2.00$2.35
27Electrical conductor (no.6) insulated (620-7010)LF440$4.00$2.00$2.50$2.27$3.04$3.00$3.00
28ITS GND box type 2 (484860)W/apron (623-7035)EACH1$9,000.00$12,600$8,855.00$8,862.99$9,333.50$9,000.00$11,070
29Ground box type D (162922)W/apron (624-7008)EACH10$1,750.00$1,300.00$1,730.00$2,092.40$1,705.00$1,900.00$1,700.00
30Elc SRV type D 120/240 070(NS)AL(E)SP(O) (628-7169)EACH1$10,000$9,255.00$8,261.00$9,548.08$9,784.50$6,500.00$8,860.00
31Aluminum signs (type A) (636-7001)SF37.50$50.00$56.00$30.00$54.87$37.23$48.00$35.40
32Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH2$1,000.00$1,200.00$1,640.00$1,924.82$800.80$1,200.00$1,313.00
33Remove SM RD SN sup&AM (644-7073)EACH3$75.00$100.00$120.00$139.99$165.00$138.00$238.00
34Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF365$12.50$10.00$15.00$16.80$11.00$11.00$13.00
35Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH2$225.00$150.00$239.00$279.98$275.00$165.00$194.00
36Reflectorized pavement marking type I (Y)4"(DOT)(100MIL) (666-7108)LF277$2.00$2.00$5.00$5.60$2.20$2.20$2.60
37Reflectorized pavement marking type II (W) 24" (solid) (666-7184)LF365$6.00$2.00$5.00$5.60$6.60$2.20$2.60
38Reflectorized pavement marking type II (W) (arrow) (666-7186)EACH2$132.00$40.00$90.00$104.99$220.00$44.00$52.00
39Reflectorized pavement marking type II (Y) 4" (DOT) (666-7209)LF277$0.65$1.00$3.00$2.80$1.81$1.10$1.30
40Eliminating existing PM & markers (4") (677-7001)LF734$0.50$2.60$1.50$1.40$1.65$3.00$3.35
41Eliminating existing PM & markers (8") (677-7004)LF5$0.75$8.00$24.00$2.80$3.30$9.00$10.35
42Eliminating existing PM & markers (24") (677-7008)LF35$5.00$24.00$7.20$8.40$5.50$26.00$31.00
43Eliminating existing PM & markers (18")(yld tri) (677-7023)EACH11$40.00$24.00$30.00$35.00$44.00$26.00$31.00
44Pavement surface preparation for marking (4") (678-7001)LF277$0.50$0.25$1.00$0.35$0.05$0.30$0.30
45Pavement surface preparation for marking (24") (678-7008)LF365$3.50$1.00$1.20$1.40$1.98$1.10$1.30
46Pavement surface preparation for marking (arrow) (678-7009)EACH2$47.50$20.00$60.00$35.00$44.00$22.00$25.85
47Ins HY traffic signal (DPT sup CNT & cab)(iso) (680-7005)EACH1$27,500$8,000.00$11,331$11,875$39,424$16,000$14,050
48Vehicle signal section (12")LED(green) (682-7001)EACH5$375.00$400.00$225.00$301.62$445.50$450.00$375.00
49Vehicle signal section (12")LED(green arrow) (682-7002)EACH4$375.00$400.00$225.00$301.62$453.20$450.00$375.00
50Vehicle signal section (12")LED(yel) (682-7003)EACH5$375.00$400.00$225.00$301.62$445.50$450.00$375.00
51Vehicle signal section (12")LED(yel arrow) (682-7004)EACH7$375.00$400.00$225.00$301.62$453.20$450.00$375.00
52Vehicle signal section (12")LED(red) (682-7005)EACH5$375.00$400.00$225.00$301.62$445.50$450.00$375.00
53Vehicle signal section (12")LED(red arrow) (682-7006)EACH4$375.00$400.00$225.00$301.62$453.20$450.00$375.00
54Pedestrian signal section (LED)(countdown) (682-7018)EACH12$1,000.00$750.00$763.00$657.47$1,002.10$600.00$800.00
55Backplate W/ref border(3 sec)(vent)aluminum (682-7042)EACH6$250.00$230.00$122.00$206.27$236.50$150.00$270.00
56Backplate W/ref border(4 sec)(vent)aluminum (682-7043)EACH3$300.00$250.00$189.00$283.26$280.50$225.00$285.00
57Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007)LF2,245$2.50$1.75$3.20$1.57$3.24$1.50$2.30
58Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031)LF1,576$3.25$2.00$3.50$1.83$3.54$2.00$2.85
59Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033)LF235$4.00$3.00$3.00$2.24$4.05$3.00$3.80
60Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046)LF520$7.50$7.00$6.00$5.65$7.51$6.00$23.50
61Ins traffic signal PL AM (mast)(install only) (686-7292)EACH3$5,000.00$1,450.00$1,498.00$1,499.21$4,263.00$5,000.00$2,275.00
62Pedestrian pole assembly (687-7001)EACH11$2,750.00$2,200.00$3,795.00$2,765.03$4,345.00$1,000.00$9,835.00
63Pedestrian detect push button (APS) (688-7001)EACH12$1,200.00$1,000.00$1,267.00$1,014.44$1,020.80$900.00$1,050.00
64Pedestrian detector controller unit (688-7003)EACH1$5,500.00$4,700.00$3,831.00$5,046.91$4,950.00$3,800.00$4,090.00
65Install spread spectrum antenna (690-7098)EACH1$1,000.00$270.00$260.00$477.22$1,584.00$500.00$232.85
66Install bbu system (690-7131)EACH1$1,000.00$1,000.00$1,039.00$1,590.82$2,508.00$1,000.00$710.00
67Subsurface util locate (non-paved area) (5061-7001)EACH11$850.00$640.00$893.00$489.96$400.00$600.00$1,080.00
68ITS com CBL (ethernet) (6005-7001)LF850$3.75$1.00$3.20$1.82$3.30$3.00$2.00
69VIVDS prosr sys (install only) (6006-7009)EACH1$1,000.00$1,000.00$2,077.00$565.48$550.00$250.00$1,432.00
70VIVDS cam assy (install only) (6006-7010)EACH3$1,000.00$430.00$520.00$596.53$2,398.00$500.00$630.00
71Installation of cellular modem (6015-7001)EACH1$1,000.00$700.00$260.00$238.99$605.00$150.00$118.00
72CCTV field equip (digital) (install only) (6018-7001)EACH1$1,000.00$1,000.00$1,039.00$795.37$1,320.00$500.00$945.00
73CCTV mount (pole) (6018-7003)EACH1$1,000.00$850.00$122.00$617.21$1,100.00$600.00$863.00
TxDOT contract A00206735: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of June 3, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way