TxDOT contract A00207984 bid tabulation

Landscape Development, IH 69 (Fort Bend County Line to Clay Street). Let by Texas DOT on February 6, 2025, Harris, Houston District. 4 bids received; low bid $3,952,210 by Yellowstone Landscape - Central, Inc., -11% against the engineer's estimate of $4,442,820.

Owner
Texas DOT
Letting
06 FEB 2025
Pay items
47
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Yellowstone Landscape - Central, Inc.$3,952,210Low-11%
2Green Sage Services LLC$4,624,991+17%+4.0%
3C. E. Barker, LTD.$10,234,574+159%+130%
4Central North Construction, LLC$13,571,902+243%+205%
TxDOT contract A00207984: bids by rank

Engineer's estimate: $4,442,820.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Yellowstone Landscape - Central, Inc.2. Green Sage Services LLC3. C. E. Barker, LTD.4. Central North Construction, LLC
1Preparing row (100-7001)ACRE0.70$20,000$4,800.00$1,450,000$570,000
2Preparation row (tree remove) (0"-12" diameter) (100-7003)EACH5$535.00$500.00$108.58$500.00
3Preparation row (tree remove) (12"-24" diameter) (100-7004)EACH678$725.00$704.44$525.00$271.44$1,500.00
4Erosion control compost (4") (161-7006)SY688.90$2.50$3.90$4.25$2.17$12.50
5Erosion control compost (vehicle) (161-7008)CY2,051.20$22.50$30.02$32.00$59.72$35.00
6General use compost (vehicle) (161-7010)CY596.20$30.79$34.00$59.72$40.00
7Block sodding (162-7002)SY5,021$5.50$5.05$4.45$8.69$7.00
8Fertilizer (166-7001)ACRE1.02$1,250.00$1,316.95$800.00$1,085.75$5,500.00
9Vegetative watering (168-7001)TGL52.80$35.00$42.40$38.00$2,860.95$85.00
10Irrigation system (type I) (170-7002)EACH1$115,000$1.00$128,000$162,863$350,000
11Irrigation system (type II) (170-7003)EACH1$72,530$195,000$651,450$200,000
12Soil amend (type I) (192-7008)SY9,105.50$0.15$0.14$0.45$1.63$1.75
13Plant bed preparation (type I) (192-7010)SY5,955$0.75$0.68$0.80$1.95$3.00
14Plant bed preparation (type II) (192-7011)SY3,350$0.31$0.80$1.63$3.00
15Plant bed preparation (type III) (192-7012)SY3,150.50$0.52$1.25$2.17$3.00
16Plant material (5 gal) (tree) (192-7035)EACH45$24.88$38.00$65.15$60.00
17Plant material (15 gal) (tree) (192-7037)EACH50$149.25$160.00$200.86$165.00
18Plant material (30 gal) (tree) (192-7039)EACH66$266.85$280.00$320.30$300.00
19Plant material (1 gal) (shrub) (192-7044)EACH14,429$10.00$9.00$9.70$15.20$15.00
20Plant material (3 gal) (shrub) (192-7046)EACH1,934$20.45$23.00$36.92$28.00
21Soil amend (type II) (192-7084)SY9,105.50$0.20$0.13$0.50$1.09$2.00
22Plant material (3 gal)(tree) (192-7094)EACH7,536$24.50$23.77$31.00$62.97$28.00
23Landscape establish (193-7001)MO20$9,500.00$8,208.96$12,000$16,286$28,000
24Landscape establish (193-7002)CYC5$45,000$59,701$37,000$23,887$150,000
25Landscape treat (193-7022)CYC28$12,300$14,392$19,000$19,001$125,000
26Landscape treat (type I) (193-7023)EACH1,401$1.00$0.97$1.20$162.86$10.00
27Landscape treat (type II) (193-7024)EACH4,203$0.35$0.30$1.25$43.43$8.00
28Landscape treat (type I) (193-7025)CYC0.95$130,000$222,387$460,000$217,150$425,000
29Landscape treat (type II) (193-7026)CYC2$50,000$47,761$54,000$182,406$56,000
30Landscape treat (type III) (193-7028)EACH12,358$2.00$2.13$1.50$81.43$5.00
31Landscape treat (type IV) (193-7029)EACH6$7,500.00$4,975.12$1,750.00$13,572$12,500
32Landscape treat (type V) (193-7030)EACH1$82,090$32,000$217,150$150,000
33Landscape treat (type VI) (193-7031)EACH1$8,656.72$14,500$135,719$100,000
34Landscape treat (type VII) (193-7032)EACH14$1,759.06$2,000.00$19,001$2,000.00
35Landscape treat (type IX) (193-7034)EACH2$3,750.00$6,716.42$4,000.00$32,399$25,000
36Landscape treat (type III) (193-7036)CYC1$75,000$85,000$93,000$1,005,405$265,000
37Landscape treat (type VI) (193-7039)CYC1$125,000$105,774$38,000$16,286$225,000
38Landscape treat (type VII) (193-7040)CYC4$39,500$30,970$68,000$30,944$105,000
39Class B concrete (miscellaneous) (420-7011)CY299.50$734.78$650.00$2,280.08$1,500.00
40Mobilization (500-7001)LS1$404,484$388,060$170,000$918,000$1,200,000
41Barricades, signs and traffic handling (502-7001)MO9$8,500.00$7,610.58$29,000$3,669.84$12,000
42TMA (stationary) (505-7001)DAY75$700.00$666.67$770.00$233.44$375.00
43TMA (mobile operation) (505-7003)DAY100$700.00$671.64$830.00$499.45$515.00
44Biodegradable erosion control logs (install) (8") (506-7043)LF14,000$2.72$5.50$6.51$6.50
45Biodegradable erosion control logs (remove) (506-7046)LF14,000$0.73$1.50$1.09$2.00
46Litter removal (734-7002)CYC56$11,000$6,130.06$8,000.00$5,564.47$36,000
47Debris removal (frontage roads) (735-7026)CYC2$20,125$15,000$12,000$10,993$75,000
TxDOT contract A00207984: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy