TxDOT contract A00211088 bid tabulation
Bridge Maintenance, SH 349 (AT 2.2 MI SW OF SH 158 to .). Let by Texas DOT on November 5, 2025, Midland, Odessa District. 4 bids received; low bid $1,829,294 by Ragle Construction, Inc., -18% against the engineer's estimate of $2,220,100.
- Owner
- Texas DOT
- Letting
- 05 NOV 2025
- Pay items
- 49
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ragle Construction, Inc. | $1,829,294 | Low | -18% |
| 2 | Scout 5 Construction LLC | $1,989,222 | +9.0% | -10% |
| 3 | Gibson & Associates, Inc. | $2,291,500 | +25% | +3.0% |
| 4 | Dan Williams Company | $2,947,672 | +61% | +33% |
Engineer's estimate: $2,220,100.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ragle Construction, Inc. | 2. Scout 5 Construction LLC | 3. Gibson & Associates, Inc. | 4. Dan Williams Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Flowable fill (embankment) (401-7002) | CY | 24 | $280.00 | $175.00 | $600.00 | $650.00 | |
| 2 | Epoxy waterproof finish (type X) (427-7005) | SF | 6,203 | $15.00 | $9.00 | $5.00 | $9.90 | $15.00 |
| 3 | Penetrating concrete surface treatment (428-7001) | SY | 8,450 | $15.00 | $8.00 | $5.00 | $19.80 | $27.00 |
| 4 | Concrete structure repair (epoxy mortar) (429-7002) | SF | 11 | $250.00 | $25.00 | $548.90 | $600.00 | |
| 5 | Concrete structure repair(rapid deck rep(PRT DPT) (429-7004) | SF | 39 | $175.00 | $150.00 | $368.50 | $595.00 | |
| 6 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 1,140 | $180.00 | $140.00 | $150.00 | $231.00 | $115.00 |
| 7 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 268 | $385.00 | $150.00 | $150.00 | $247.50 | $325.00 |
| 8 | Concrete structure repair (standard) (429-7009) | SF | 76 | $150.00 | $100.00 | $198.00 | $325.00 | |
| 9 | Riprap (concrete)(flume) (432-7012) | CY | 13 | $650.00 | $1,000.00 | $1,650.00 | $1,500.00 | |
| 10 | Cleaning and sealing existing joints (CL5) (438-7006) | LF | 266 | $30.00 | $30.00 | $25.30 | $50.00 | |
| 11 | Cleaning existing joints (438-7008) | LF | 500 | $40.00 | $23.00 | $25.00 | $31.90 | $50.00 |
| 12 | Resizing and sealing joints (438-7009) | LF | 160 | $65.00 | $50.00 | $82.50 | $75.00 | |
| 13 | Concrete overlay (3 in) (439-7004) | SY | 1,479 | $150.00 | $150.00 | $100.00 | $186.50 | $125.00 |
| 14 | Multi-layer polymer overlay (439-7014) | SY | 2,892 | $45.00 | $35.00 | $44.00 | $85.00 | |
| 15 | Polyester polymer concrete overlay (1") (439-7021) | SY | 340 | $225.00 | $400.00 | $355.00 | $450.00 | |
| 16 | Rail (type SSTR)(HPC) (450-7025) | LF | 570 | $200.00 | $98.00 | $80.00 | $163.90 | $115.00 |
| 17 | Retrofit rail (type SSTR)(HPC) (451-7025) | LF | 56 | $425.00 | $40.00 | $350.00 | $209.00 | $300.00 |
| 18 | Hydro-demolition (3 in) (483-7012) | SY | 1,479 | $160.00 | $105.00 | $50.00 | $39.00 | $275.00 |
| 19 | Micromilling concrete slab (1 in) (483-7022) | SY | 340 | $60.00 | $300.00 | $134.20 | $60.00 | |
| 20 | Remove STR (rail) (496-7017) | LF | 570 | $60.00 | $7.00 | $500.00 | $40.00 | $5.00 |
| 21 | Mobilization (500-7001) | LS | 1 | $188,191 | $180,000 | $250,000 | $394,000 | $290,000 |
| 22 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $15,000 | $25,000 | $0.01 | $21,000 | $45,000 |
| 23 | Portable changeable message sign (503-7002) | EACH | 4 | $14,350 | $25,000 | $50,000 | $14,000 | $17,500 |
| 24 | TMA (stationary) (505-7001) | DAY | 70 | $175.00 | $975.00 | $0.01 | $687.00 | $285.00 |
| 25 | Metal W-beam guard fence (steel post) (540-7002) | LF | 400 | $42.00 | $28.00 | $25.00 | $30.80 | $50.00 |
| 26 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,325.00 | $2,000.00 | $2,500.00 | $2,200.00 | $4,500.00 |
| 27 | Remove metal beam guard fence (542-7001) | LF | 400 | $6.00 | $3.00 | $15.00 | $3.30 | $7.00 |
| 28 | RM metal beam guard fence trans (T101) (542-7005) | EACH | 4 | $260.00 | $150.00 | $1,000.00 | $165.00 | $450.00 |
| 29 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,850.00 | $3,200.00 | $3,500.00 | $3,520.00 | $5,000.00 |
| 30 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $300.00 | $200.00 | $500.00 | $220.00 | $450.00 |
| 31 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 6 | $45.00 | $50.00 | $49.50 | $100.00 | |
| 32 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 6 | $42.00 | $45.00 | $50.00 | $49.50 | $100.00 |
| 33 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 12 | $40.00 | $45.00 | $50.00 | $49.50 | $100.00 |
| 34 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 12 | $45.00 | $50.00 | $49.50 | $100.00 | |
| 35 | Pavement sler 6" (666-7347) | LF | 4,842 | $0.90 | $2.50 | $15.00 | $0.50 | $2.50 |
| 36 | Prefabricated PM type B (W)(6")(solid) (668-7009) | LF | 2,211 | $10.50 | $8.50 | $15.00 | $7.70 | $8.50 |
| 37 | Prefabricated PM type B (W)(6")(broken)contrast (668-7012) | LF | 420 | $15.00 | $15.00 | $15.40 | $15.00 | |
| 38 | Prefabricated PM type B (Y)(6")(solid) (668-7051) | LF | 2,211 | $7.50 | $8.50 | $15.00 | $7.70 | $8.50 |
| 39 | Reflectorized pavement marker type I-C (672-7002) | EACH | 21 | $20.00 | $25.00 | $11.00 | $20.00 | |
| 40 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 9 | $12.50 | $20.00 | $25.00 | $11.00 | $20.00 |
| 41 | Eliminating existing PM & markers (6") (677-7002) | LF | 1,746 | $4.00 | $3.50 | $0.50 | $4.00 | |
| 42 | Pavement surface preparation for marking (6") (678-7002) | LF | 4,842 | $3.00 | $3.00 | $5.00 | $0.44 | $3.00 |
| 43 | Replace rail element (W-beam) (770-7001) | LF | 150 | $16.00 | $50.00 | $17.60 | $20.00 | |
| 44 | Replace steel post W/O concrete FND (770-7007) | EACH | 8 | $80.00 | $100.00 | $88.00 | $250.00 | |
| 45 | Concrete rail repair (in-kind) (778-7001) | LF | 5 | $600.00 | $500.00 | $1,500.00 | $2,000.00 | |
| 46 | Concrete CRCK repair(discrete)(rout and seal) (780-7003) | LF | 90 | $35.00 | $50.00 | $27.50 | $100.00 | |
| 47 | CNC crack repair (discrete)(surface seal) (780-7004) | LF | 43 | $35.00 | $50.00 | $68.20 | $100.00 | |
| 48 | Bridge joint replacement (SEJ) (785-7011) | LF | 80 | $350.00 | $500.00 | $487.50 | $850.00 | |
| 49 | Concrete beam repair (CFRP) (788-7002) | EACH | 5 | $4,500.00 | $500.00 | $4,290.00 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way