TxDOT contract A00214289 bid tabulation
REHABILITATION OF EXISTING ROADWAY, FM0626 (FM0626 to FM3191 etc.). Let by Texas DOT on April 3, 2025, Karnes, Corpus Christi District. 4 bids received; low bid $1,289,866 by Hunter Industries, LTD., -11% against the engineer's estimate of $1,452,855.
- Owner
- Texas DOT
- Letting
- 03 APR 2025
- Pay items
- 20
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hunter Industries, LTD. | $1,289,866 | Low | -11% |
| 2 | CK Newberry, LLC | $1,297,809 | +1.0% | -11% |
| 3 | J. Carroll Weaver, Inc. | $1,368,744 | +6.0% | -6.0% |
| 4 | Clark Construction of Texas, Inc. | $1,576,289 | +22% | +8.0% |
Engineer's estimate: $1,452,855.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Hunter Industries, LTD. | 2. CK Newberry, LLC | 3. J. Carroll Weaver, Inc. | 4. Clark Construction of Texas, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Subgr widen (OC) (112-7001) | STA | 212 | $375.00 | $921.30 | $325.00 | $199.06 | $824.28 |
| 2 | Broadcast seed (permanent_rural_clay) (164-7034) | ACRE | 8 | $1,940.70 | $2,023.59 | $225.00 | $1,650.00 | $1,500.00 |
| 3 | FL BS (roadway del)(type A GR 1-2)(final pos) (247-7259) | CY | 5,991 | $90.63 | $71.86 | $76.00 | $95.25 | $85.70 |
| 4 | Cement (275-7001) | TON | 471 | $227.23 | $209.00 | $185.00 | $201.45 | $215.00 |
| 5 | Cement TRT (existing material & new base)(8") (275-7007) | SY | 38,720 | $3.00 | $3.60 | $2.50 | $1.55 | $4.10 |
| 6 | Asphalt (RC-250) (316-7016) | GAL | 10,326 | $6.25 | $5.30 | $5.00 | $4.98 | $4.65 |
| 7 | Asphalt(AC-15P, HFRS-2P or CRS-2P) (316-7070) | GAL | 29,286 | $5.00 | $4.31 | $4.00 | $3.95 | $5.05 |
| 8 | Aggregate (type-B, GR-5)(sac-B) (316-7175) | CY | 382 | $143.88 | $97.12 | $140.00 | $125.06 | $109.28 |
| 9 | Aggregate (type-PB, GR-3 or 3S)(sac-B) (316-7209) | CY | 834 | $108.42 | $125.66 | $140.00 | $170.97 | $139.16 |
| 10 | Mobilization (callout 1) (500-7003) | EACH | 2 | $40,000 | $5,844.90 | $40,000 | $40,000 | $48,500 |
| 11 | Mobilization (callout 2) (500-7004) | EACH | 2 | $40,000 | $5,844.90 | $50,000 | $40,000 | $48,500 |
| 12 | TMA (stationary) (505-7001) | DAY | 51 | $200.00 | $150.00 | $325.00 | $275.00 | $300.00 |
| 13 | TMA (mobile operation) (505-7002) | HR | 30 | $83.25 | $100.00 | $35.00 | $49.50 | $72.50 |
| 14 | Temporary sediment control fence (install) (506-7039) | LF | 640 | $5.00 | $8.15 | $5.00 | $5.39 | $4.90 |
| 15 | Temporary sediment control fence (remove) (506-7041) | LF | 640 | $1.65 | $2.04 | $1.00 | $0.83 | $1.50 |
| 16 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 528 | $1.48 | $1.63 | $0.50 | $0.72 | $2.00 |
| 17 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 42,240 | $0.78 | $0.58 | $0.60 | $0.64 | $0.58 |
| 18 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 3,193 | $0.78 | $1.10 | $1.10 | $1.21 | $1.10 |
| 19 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 25,781 | $0.78 | $0.58 | $0.60 | $0.64 | $0.58 |
| 20 | Reflectorized pavement marker type II-A-A (callout) (672-7019) | EACH | 372 | $5.50 | $7.50 | $7.50 | $8.25 | $7.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 3, 2025. Compiled by Mirage Metrics.