TxDOT contract A00214298 bid tabulation
METAL BEAM GUARD FENCE REPAIR, IH0045 (Various Highways in Montgomery County to Various Highways in Montgomery County). Let by Texas DOT on February 10, 2026, Montgomery, Houston District. 6 bids received; low bid $444,263 by BK Field Operations LLC, -32% against the engineer's estimate of $656,645.
- Owner
- Texas DOT
- Letting
- 10 FEB 2026
- Pay items
- 54
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BK Field Operations LLC | $444,263 | Low | -32% |
| 2 | Rhino Equity, LLC | $503,372 | +13% | -23% |
| 3 | Roy Jorgensen Associates, Inc. | $542,775 | +22% | -17% |
| 4 | Hazmat International, Inc. | $542,798 | +22% | -17% |
| 5 | Above All Contracting LLC | $586,866 | +32% | -11% |
| 6 | Isi Contracting, Inc. | $681,474 | +53% | +4.0% |
Engineer's estimate: $656,645.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. BK Field Operations LLC | 2. Rhino Equity, LLC | 3. Roy Jorgensen Associates, Inc. | 4. Hazmat International, Inc. | 5. Above All Contracting LLC | 6. Isi Contracting, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7005) | LF | 125 | $11.00 | $20.00 | $5.00 | $10.00 | $18.50 | $20.00 | $48.00 |
| 2 | Backfill (type A) (134-7001) | STA | 25 | $191.65 | $30.00 | $100.00 | $100.00 | $5.00 | $25.00 | $1,510.00 |
| 3 | Riprap (mow strip)(4 in) (432-7013) | CY | 3 | $645.00 | $1,100.00 | $900.00 | $1,500.00 | $600.00 | $600.00 | $900.00 |
| 4 | Mobilization (callout) (500-7002) | EACH | 36 | $1,200.00 | $1.00 | $1.00 | $500.00 | $100.00 | $1.00 | $250.00 |
| 5 | Mobilization (emergency) (500-7033) | EACH | 3 | $950.00 | $1.00 | $1.00 | $500.00 | $250.00 | $500.00 | $1,000.00 |
| 6 | TMA (stationary) (505-7001) | DAY | 80 | $200.29 | $1.00 | $1.00 | $400.00 | $250.00 | $1.00 | $250.00 |
| 7 | TMA (mobile operation) (505-7003) | DAY | 75 | $157.69 | $1.00 | $1.00 | $10.00 | $250.00 | $1.00 | $150.00 |
| 8 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,125 | $23.78 | $28.00 | $35.00 | $36.00 | $22.50 | $35.00 | $26.00 |
| 9 | Metal W-beam guard fence (steel post) (540-7002) | LF | 150 | $32.69 | $10.00 | $10.00 | $40.00 | $50.00 | $50.00 | $50.00 |
| 10 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 3 | $2,417.38 | $2,400.00 | $2,000.00 | $2,500.00 | $2,000.00 | $2,000.00 | $1,734.00 |
| 11 | Short radius (28") (540-7013) | LF | 250 | $31.53 | $50.00 | $50.00 | $35.00 | $75.00 | $50.00 | $34.00 |
| 12 | Downstream anchor terminal section (540-7015) | EACH | 6 | $1,440.00 | $1,250.00 | $1,500.00 | $1,400.00 | $2,500.00 | $1,300.00 | $1,952.00 |
| 13 | Metal beam guard fence (long span system) (540-7027) | EACH | 5 | $357.35 | $600.00 | $1.00 | $250.00 | $10.00 | $800.00 | $408.00 |
| 14 | Remove terminal anchor section (542-7002) | EACH | 1 | $136.69 | $1.00 | $1.00 | $100.00 | $1.00 | $200.00 | $379.00 |
| 15 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $247.99 | $1.00 | $1.00 | $100.00 | $1.00 | $200.00 | $379.00 |
| 16 | Guardrail end treatment (install) (544-7001) | EACH | 1 | $3,198.04 | $3,500.00 | $3,500.00 | $3,200.00 | $6,000.00 | $4,000.00 | $3,163.00 |
| 17 | Guardrail end treatment (move & reset) (544-7002) | EACH | 1 | $845.00 | $500.00 | $1,000.00 | $300.00 | $500.00 | $500.00 | $737.00 |
| 18 | Guardrail end treatment (remove) (544-7003) | EACH | 1 | $266.91 | $7.00 | $1.00 | $1,200.00 | $1.00 | $500.00 | $627.00 |
| 19 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 3,000 | $5.00 | $1.00 | $5.00 | $3.00 | $3.50 | $5.00 | $9.00 |
| 20 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 4,000 | $25.00 | $1.00 | $5.00 | $5.00 | $5.00 | $20.00 | $12.50 |
| 21 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 4,000 | $5.00 | $1.00 | $5.00 | $3.00 | $4.00 | $5.00 | $9.00 |
| 22 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 250 | $25.00 | $10.00 | $5.00 | $5.00 | $5.00 | $20.00 | $13.00 |
| 23 | Replace delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7178) | EACH | 3,000 | $5.00 | $1.00 | $5.00 | $5.00 | $3.50 | $5.00 | $8.00 |
| 24 | Replace delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7184) | EACH | 1,500 | $5.00 | $1.00 | $5.00 | $15.00 | $5.00 | $20.00 | $13.00 |
| 25 | Replace delineator assembly (D-SY)SZ 1(BRF)CTB(BI) (658-7202) | EACH | 1,500 | $5.00 | $1.00 | $5.00 | $5.00 | $4.00 | $5.00 | $8.00 |
| 26 | Replace rail element (W-beam) (770-7001) | LF | 1,500 | $20.20 | $1.00 | $18.00 | $20.00 | $32.50 | $25.00 | $22.00 |
| 27 | Replace rail element (thrie-beam) (770-7002) | LF | 50 | $67.34 | $5.00 | $25.00 | $25.00 | $25.00 | $60.00 | $36.00 |
| 28 | Repl rail elmnt(thrie-BM trans to W-BM) (770-7003) | EACH | 25 | $93.27 | $5.00 | $300.00 | $50.00 | $250.00 | $500.00 | $953.00 |
| 29 | Replace short radius sys (TL-2) (770-7004) | EACH | 5 | $80.60 | $1.00 | $1.00 | $10.00 | $1,000.00 | $100.00 | $773.00 |
| 30 | Replace short radius sys (TL-3) (770-7005) | EACH | 5 | $20,000 | $1.00 | $1.00 | $10.00 | $1,000.00 | $100.00 | $773.00 |
| 31 | Replace timber post W/O concrete FND (770-7006) | EACH | 50 | $60.83 | $450.00 | $50.00 | $50.00 | $50.00 | $30.00 | $107.00 |
| 32 | Replace steel post W/O concrete FND (770-7007) | EACH | 25 | $102.78 | $1.00 | $1.00 | $50.00 | $50.00 | $50.00 | $144.00 |
| 33 | Replace timber post W/ concrete FND (770-7008) | EACH | 25 | $61.15 | $600.00 | $50.00 | $150.00 | $50.00 | $100.00 | $145.00 |
| 34 | Replace steel post W/ concrete FND (770-7009) | EACH | 25 | $123.57 | $1.00 | $100.00 | $50.00 | $30.00 | $100.00 | $165.00 |
| 35 | Realign posts (770-7010) | EACH | 5 | $7.97 | $500.00 | $25.00 | $125.00 | $100.00 | $100.00 | $50.00 |
| 36 | Rem obsolete get & repl W/ SGT (770-7013) | EACH | 30 | $2,751.12 | $3,900.00 | $3,700.00 | $4,000.00 | $3,000.00 | $3,800.00 | $3,250.00 |
| 37 | Repl single gdrail terminal impact head (770-7015) | EACH | 35 | $1,113.41 | $1,900.00 | $1,100.00 | $1,050.00 | $750.00 | $600.00 | $1,261.00 |
| 38 | Replace single gdrail terminal rail (770-7016) | LF | 1,500 | $19.33 | $30.00 | $50.00 | $35.00 | $75.00 | $30.00 | $36.00 |
| 39 | Replace single gdrail terminal post (770-7017) | EACH | 250 | $66.37 | $1.00 | $65.00 | $80.00 | $30.00 | $100.00 | $53.00 |
| 40 | Replace blockout (770-7018) | EACH | 100 | $9.79 | $400.00 | $50.00 | $20.00 | $50.00 | $50.00 | $26.00 |
| 41 | Reset SGT impact head (770-7020) | EACH | 5 | $69.04 | $2,500.00 | $750.00 | $650.00 | $100.00 | $250.00 | $330.00 |
| 42 | Replace SGT object marker (770-7021) | EACH | 35 | $43.17 | $1.00 | $30.00 | $30.00 | $25.00 | $30.00 | $35.00 |
| 43 | Replace SGT cable anchor (770-7022) | EACH | 15 | $59.17 | $400.00 | $150.00 | $500.00 | $50.00 | $100.00 | $50.00 |
| 44 | Replace SGT cable assembly (770-7023) | EACH | 5 | $67.43 | $500.00 | $150.00 | $500.00 | $50.00 | $100.00 | $156.00 |
| 45 | Replace SGT strut (770-7024) | EACH | 15 | $130.37 | $1.00 | $200.00 | $80.00 | $50.00 | $100.00 | $109.00 |
| 46 | Raise rail (770-7025) | LF | 75 | $2.73 | $10.00 | $25.00 | $25.00 | $10.00 | $25.00 | $10.00 |
| 47 | Repair rail element (curved rail) (770-7027) | LF | 300 | $20.92 | $1.00 | $35.00 | $15.00 | $2.50 | $50.00 | $75.00 |
| 48 | Replace posts (TL-4)(gibraltar) (771-7005) | EACH | 75 | $78.05 | $130.00 | $185.00 | $150.00 | $300.00 | $200.00 | $44.00 |
| 49 | Cable splice / turnbuckle (TL-4) (771-7010) | EACH | 5 | $169.78 | $1.00 | $1.00 | $100.00 | $10.00 | $300.00 | $380.00 |
| 50 | Repair concrete foundation (TL-4) (771-7012) | EACH | 5 | $146.91 | $1.00 | $1.00 | $100.00 | $1.00 | $50.00 | $1,249.00 |
| 51 | Repair or replace cable barrier terminal sec(TL-4) (771-7014) | EACH | 3 | $1,785.13 | $1,000.00 | $1,500.00 | $1,250.00 | $1,000.00 | $2,500.00 | $3,650.00 |
| 52 | Replace cable (TL-4) (771-7016) | LF | 250 | $1.86 | $1.00 | $1.00 | $1.50 | $2.50 | $10.00 | $6.00 |
| 53 | Check / RE-tension cable (TL-4) (771-7018) | EACH | 15 | $125.38 | $1.00 | $400.00 | $250.00 | $1.00 | $150.00 | $4.00 |
| 54 | Replace post hardware (TL-4) (771-7020) | EACH | 25 | $3.47 | $200.00 | $100.00 | $100.00 | $1.00 | $50.00 | $100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 10, 2026. Compiled by Mirage Metrics.