TxDOT contract A00215821 bid tabulation
Resurface Roadway, IH 45 (North of BNSF RR to North of W Canino Rd). Let by Texas DOT on August 6, 2026, Harris, Houston District. 5 bids received; low bid $5,092,365 by MBN Enterprises LLC, +13% against the engineer's estimate of $4,502,237.
- Owner
- Texas DOT
- Letting
- 06 AUG 2026
- Pay items
- 54
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | MBN Enterprises LLC | $5,092,365 | Low | +13% |
| 2 | Texas Materials Group, Inc. | $5,374,049 | +6.0% | +19% |
| 3 | Forde Construction Company, Inc. | $5,800,225 | +14% | +29% |
| 4 | Environmental Allies, Inc. | $5,822,286 | +14% | +29% |
| 5 | Durwood Greene Construction Co. | $6,777,781 | +33% | +51% |
Engineer's estimate: $4,502,237.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. MBN Enterprises LLC | 2. Texas Materials Group, Inc. | 3. Forde Construction Company, Inc. | 4. Environmental Allies, Inc. | 5. Durwood Greene Construction Co. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7005) | LF | 5,023 | $10.00 | $4.00 | $11.00 | $14.00 | $18.00 | $30.00 |
| 2 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 53 | $20.00 | $20.00 | $124.00 | $158.00 | $25.00 | $40.00 |
| 3 | Removing concrete (curb) (104-7016) | LF | 1,283 | $6.71 | $4.00 | $44.00 | $16.00 | $10.00 | $15.00 |
| 4 | Asphalt (AC-20-5TR or AC-20XP) (316-7067) | GAL | 41,054 | $3.25 | $2.40 | $4.30 | $4.30 | $7.00 | $3.50 |
| 5 | Aggregate (type-PB or PL, GR-4)(sac-B) (316-7245) | CY | 877 | $216.00 | $185.00 | $145.00 | $270.00 | $365.00 | $250.00 |
| 6 | SP mixes SP-D sac-A PG76-22 (344-7064) | TON | 16,912 | $120.00 | $158.00 | $154.50 | $146.00 | $152.00 | $165.00 |
| 7 | Tack coat (344-7077) | GAL | 6,842 | $3.71 | $5.00 | $4.00 | $4.00 | $5.00 | $4.00 |
| 8 | Planing asphalt concrete pavement(2") (354-7051) | SY | 34,623 | $1.60 | $3.00 | $4.00 | $2.50 | $4.00 | $2.50 |
| 9 | Planing asphalt concrete pavement(3") (354-7052) | SY | 79,415 | $1.67 | $3.00 | $4.00 | $2.60 | $4.50 | $4.00 |
| 10 | Full - depth repair CRCP (6") (361-7001) | CY | 388 | $1,037.00 | $740.00 | $1,025.00 | $2,000.00 | $825.00 | $2,100.00 |
| 11 | Full - depth repair CPJR (8") (361-7036) | CY | 423 | $951.00 | $720.00 | $1,025.00 | $1,700.00 | $1,150.00 | $1,800.00 |
| 12 | Riprap (mow strip)(4 in) (432-7013) | CY | 218 | $571.00 | $650.00 | $600.00 | $875.00 | $775.00 | $1,200.00 |
| 13 | Mobilization (500-7001) | LS | 1 | $404,000 | $400,000 | $116,000 | $155,000 | $350,000 | $372,000 |
| 14 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $8,000.00 | $7,000.00 | $5,000.00 | $10,500 | $7,900.00 | $17,000 |
| 15 | Portable changeable message sign (503-7002) | EACH | 4 | $5,083.00 | $9,000.00 | $10,250 | $8,000.00 | $12,000 | $12,000 |
| 16 | TMA (stationary) (505-7001) | DAY | 110 | $205.00 | $140.00 | $750.00 | $500.00 | $350.00 | $350.00 |
| 17 | TMA (mobile operation) (505-7003) | DAY | 15 | $290.00 | $200.00 | $725.00 | $250.00 | $450.00 | $350.00 |
| 18 | Concrete curb (dowel) (529-7014) | LF | 1,283 | $28.00 | $11.00 | $82.00 | $38.00 | $20.00 | $70.00 |
| 19 | Concrete sidewalks (6") (531-7003) | SY | 53 | $75.00 | $105.00 | $410.00 | $236.00 | $115.00 | $230.00 |
| 20 | Metal W-beam guard fence (timber post) (540-7001) | LF | 3,213 | $26.00 | $27.00 | $28.00 | $31.00 | $30.00 | $30.00 |
| 21 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 3 | $1,850.00 | $2,400.00 | $2,350.00 | $2,275.00 | $2,500.00 | $3,200.00 |
| 22 | Downstream anchor terminal section (540-7015) | EACH | 27 | $1,200.00 | $1,700.00 | $1,950.00 | $1,300.00 | $1,900.00 | $2,000.00 |
| 23 | Remove metal beam guard fence (542-7001) | LF | 3,075 | $2.50 | $5.00 | $7.30 | $2.10 | $4.00 | $3.50 |
| 24 | Remove terminal anchor section (542-7002) | EACH | 18 | $200.00 | $400.00 | $495.00 | $238.00 | $400.00 | $400.00 |
| 25 | Remove downstream anchor terminal (542-7003) | EACH | 3 | $250.00 | $300.00 | $332.00 | $250.00 | $250.00 | $300.00 |
| 26 | RM metal beam guard fence trans (TL-2) (542-7006) | EACH | 10 | $190.00 | $250.00 | $495.00 | $280.00 | $250.00 | $300.00 |
| 27 | Guardrail end treatment (install) (544-7001) | EACH | 30 | $3,111.00 | $3,500.00 | $2,815.00 | $3,825.00 | $3,750.00 | $3,850.00 |
| 28 | Guardrail end treatment (remove) (544-7003) | EACH | 32 | $250.00 | $300.00 | $250.00 | $355.00 | $275.00 | $350.00 |
| 29 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 31 | $27.00 | $45.00 | $14.00 | $32.00 | $38.00 | $45.00 |
| 30 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 60 | $25.00 | $45.00 | $14.00 | $32.00 | $38.00 | $45.00 |
| 31 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 22,600 | $0.35 | $0.60 | $0.50 | $0.35 | $0.40 | $0.30 |
| 32 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 12,706 | $0.65 | $1.00 | $2.00 | $0.65 | $0.50 | $0.45 |
| 33 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 4,848 | $3.45 | $5.00 | $1.50 | $2.12 | $2.50 | $2.50 |
| 34 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 40,704 | $0.35 | $0.60 | $0.30 | $0.35 | $0.35 | $0.30 |
| 35 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 5,368 | $1.30 | $1.50 | $1.60 | $1.32 | $5.50 | $3.50 |
| 36 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 264 | $1.20 | $2.00 | $2.30 | $0.95 | $1.15 | $5.00 |
| 37 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 6,353 | $1.30 | $1.20 | $1.10 | $0.95 | $1.15 | $1.00 |
| 38 | Reflectorized pavement marking type I (Y)8"(solid)(100MIL) (666-7114) | LF | 4,896 | $1.30 | $1.20 | $0.95 | $0.95 | $1.15 | $1.00 |
| 39 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 1,923 | $3.40 | $5.00 | $3.95 | $3.05 | $3.35 | $3.20 |
| 40 | All-wther PM type I (W)6"(solid)(100MIL) (666-7309) | LF | 30,042 | $0.75 | $1.00 | $0.95 | $0.65 | $1.00 | $0.90 |
| 41 | All-wther PM type I (W)6"(broken)(100MIL) (666-7310) | LF | 11,300 | $0.85 | $1.00 | $0.95 | $0.65 | $1.00 | $0.90 |
| 42 | All-wther PM type I (W)6"(DOT)(100MIL) (666-7311) | LF | 92 | $2.00 | $1.20 | $1.50 | $0.70 | $1.00 | $0.90 |
| 43 | All-wther PM type I (Y)6"(solid)(100MIL) (666-7315) | LF | 20,352 | $0.80 | $1.00 | $0.95 | $0.65 | $1.00 | $0.90 |
| 44 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 1,212 | $13.00 | $15.00 | $26.75 | $14.00 | $18.00 | $17.00 |
| 45 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 2 | $195.00 | $300.00 | $265.00 | $218.00 | $275.00 | $275.00 |
| 46 | Prefabricated PM type C (W)(double arrow) (668-7093) | EACH | 11 | $330.00 | $400.00 | $500.00 | $69.00 | $330.00 | $320.00 |
| 47 | Prefabricated PM type C (W)(uturn arrow) (668-7096) | EACH | 3 | $300.00 | $450.00 | $460.00 | $345.00 | $300.00 | $450.00 |
| 48 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 10 | $250.00 | $350.00 | $375.00 | $335.00 | $300.00 | $320.00 |
| 49 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 1,047 | $4.00 | $8.00 | $7.00 | $6.00 | $7.50 | $7.00 |
| 50 | Eliminating existing PM & markers (24") (677-7008) | LF | 511 | $2.20 | $5.00 | $1.40 | $3.50 | $3.00 | $2.20 |
| 51 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 2 | $42.00 | $100.00 | $38.00 | $75.00 | $85.00 | $60.00 |
| 52 | Eliminating existing PM & markers (double arrow) (677-7010) | EACH | 3 | $58.00 | $120.00 | $38.00 | $88.00 | $85.00 | $60.00 |
| 53 | Eliminating existing PM & markers (uturn arrow) (677-7012) | EACH | 3 | $50.00 | $120.00 | $48.00 | $88.00 | $85.00 | $100.00 |
| 54 | Eliminating existing PM & markers (word) (677-7015) | EACH | 5 | $42.00 | $120.00 | $48.00 | $75.00 | $85.00 | $60.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.